Documents filed under Legal

ERT Wiggins v. Ontario: Decision revoking wind turbine permit

Ert_16-036_wiggins_v_ontario_-_decision-2017-08-16_thumb In this important decision by the Ontario Environmental Review Tribune, the Tribune officially revokes Wpd Canada's permit to install eight 137-meter (450 feet) tall wind turbines in close proximity to the Collingwood Regional Airport and a private air field owned by Kevin and Gail Elwood. In its October 2016 decision, the ERT had determined that the appellants met the test that showed there would be harm to human health. The ERT also agreed that irreversible harm to the natural environment, specifically to bats, warranted further investigation. Wpd Canada was granted an opportunity to show that mitigation could resolve the concerns. The ERT in this decision held that the risk to human health and safety was unacceptable. A portion of the decision is provided below (paragraphs 15-20) pertaining to the turbines impairing safe air travel. The full decision of the ERT can be found by clicking the links on this page.
16 Aug 2017

Falmouth Wind Turbines 1 and 2: Court Order to cease and desist operation

Judge_moriarity_decision_june_2017_thumb In this important ruling issued by Massachusetts Superior Court Judge Cornelius J. Moriarty II, the court ordered that the decision of the Falmouth MA Zoning Board of Appeals be affirmed to the extent that the operation of Wind 1 and Wind 2 constitute a nuisance and that the Town of Falmouth cease and desist operation of the wind turbines immediately. The full order can be accessed by clicking the document icon located on this page.  
21 Jun 2017

Greater Sage-Grouse on Steens Mountain: Final Ruling

12-596_order_granting_motion_to_vacate_4-18-17_thumb In this important ruling by the U.S. District Court for the District of Oregon, the court vacated the Secretary of the Interior’s approval of the proposed Steens Mountain wind project which would have sited up to 69 turbines and a 230 kv transmission line in area critical for sage grouse. The order is provided below and can also be accessed by clicking the links on this page. 
18 Apr 2017

Camp Perry Wind Complaint

Campperrycomplaintasfiled-1_thumb Two leading bird conservation groups, American Bird Conservancy (ABC) and Black Swamp Bird Observatory (BSBO), have filed a lawsuit against the Ohio Air National Guard (ANG) over its plans to build and operate a wind turbine at its Camp Perry facility. Located in Port Clinton, Ohio, on the shore of Lake Erie, Camp Perry lies in a major bird migration corridor, close to numerous Bald Eagle nests, and is likely to kill species protected under the Endangered Species Act such as Kirtland's Warbler and Piping Plover. The complaint can be accessed by clicking the links on this page. A portion of the complaint is provided below.
27 Mar 2017

ABC brief supporting disclosure of bird-bat mortality: Blue Creek Wind facility

Brief_thumb This brief, filed before the Ohio Court of Common Pleas in Franklin County, Ohio, responds to Iberdrola's (Avangrid Renewables) action to stop any public disclose of bird/bat mortality data at its Blue Creek wind facility. Iberdrola has argued that the number of birds and bats killed by its turbines is a “trade secret” protected under Ohio law. The introduction and summary of arguments for why Iberdrola's claims are not supported by Ohio law are provided below. The full brief can be accessed by clicking the links on this page. The original complaint can be found here. 
7 Mar 2017

Penn Forest Township prevails against Atlantic Wind (Iberdrola)

Atlanticwindvspennforesttwp-opinion_thumb Atlantic Wind (aka Iberdrola) filed a complaint on September 26, 2016 (amended on November 7, 2016) before the Pennsylvania Carbon County Court of Common Pleas arguing that the venue to hear its Bethlehem Watershed wind turbine proposal was unsafe and that the location  should be changed and an independent hearing officer appointed. Atlantic Wind alleged that threats of violence by the public impacted the company's ability to receive a fair hearing before the Township zoning board. Atlantic Wind also requested an injunction barring the zoning board from holding further hearings until the court could rule. In this ruling the Court of Common Pleas ruled against Atlantic Wind. The full order can be accessed by clicking the links on this page. A portion of the order is provided below.  
17 Feb 2017

Denial of Flat Rock Wind upheld by Appeals Court: Decision

Flatrockwind-rushcountyin-appealorder_thumb An application prepared by Apex Clean Energy to construct and operate the Flat Rock wind facility was submitted to the Rush County Board of Zoning Appeals (the “BZA”) on March 15, 2015. The 180 MW project consisted of 95-3 MW turbines with approximately 66 turbines located in Rush County and the remaining turbines to be sited in Henry County. The Rush County BZA ultimately approved the application with the condition that the setback distance between the wind turbines and non-participating properties be 2,300 feet. The County's ordinance established a setback distance of 1,000 feet. Apex filed a petition before the Rush County Superior Court for judicial review of the BZA’s decision. On May 27, 2016, a judge issued findings of fact and conclusions of law that upheld the BZA’s approval with the 2,300-foot setback provision. Apex appealed the decision to the Indiana Court of Appeals. The decision by the Appeals Count was in favor of Rush County. The full decision can be accessed by clicking the links on the page. A portion of the decision is provided below.
14 Feb 2017

Iberdrola - Tule Wind construction suspension order

Blm-tulewind-tempconstructionsuspension_thumb The attached communications between the Bureau of Land Management (BLM) and Iberdrola/Tule Wind detail the BLM's notice to suspend construction of the 186 MW wind project due to repeated violations of the right-of-way permit issued by the BLM. The Tule facility initiated construction on December 6, 2016. The notice to stop construction was issued on January 20, 2017. Construction has now resumed. Both the notice to suspend construction and to resume construction, which includes Iberdrola's response to the BLM, can be accessed by selecting the document links on this page, A portion of BLM's notice is provided below. 
13 Feb 2017

Court order: DOE failed to consider environmental impacts on Mexico

Esj_court_ruling_for_bad_27s_msj_1-30-17_thumb This important decision by the U.S. District Court of the Southern District in California found that the Department of Energy failed to follow NEPA when it issued a permit to construct a transmission line that crossed over from Mexico into the United States. The Court order that since the U.S. portion of the Line and the Mexican portion of the Line were literally "two links of a single chain" connecting the Substation to the ESJ Wind Farm, the DOE was required to consider the impacts of the project on Mexico. Portions of the decision are shown below. The full report can be accessed by clicking the document link on this page.
30 Jan 2017

Dan's Mountain Wind Force Certificate: DENIED

Dans_mountain_order-maryland_thumb On January 14, 2016, Dan's Mountain Wind Force LLC filed an application for Certificate of Public Convenience and Necessity (CPCN) with the Maryland PSC to construct a 59.9 megawatt wind energy facility in Allegany County Maryland. The application to the PSC came after the company could not obtain a permit though the County's permitting process and after they asked for and received an exemption from the state for a CPCN back in 2008. Dan's Mountain returned to the PSC in an effort to go around the County's denials. Following an adjudicative hearing, this order was issued by the PSC denying the project. The Findings and Conclusions by Terry J. Romine, the Chief Public Utility Law Judge for the Maryland PSC, can be found below. The full order can be accessed by clicking the document icon on this page. 
25 Jan 2017

Apex Mills Branch Solar Denied Permit: DECISION

Kent-county-apex-solar-denied-decision_thumb Public Utility Law Judge Dennis H. Sober of the Maryland Public Service Commission, has denied a permit for Apex Clean Energy, Inc to construct the Mills Branch Solar project proposed for Kent County Maryland. The project was expected to have a nameplate capacity of 60 MW spread across 330 acres of Maryland farmland. The project was opposed by the Kent County board of Commissioners and residents in the area. Apex previously tried to site a wind energy facility in the same area on 5,000 acres but opposition to the turbines forced the company to change from wind to solar. A portion of Judge Sober's decision is provided below. The full decision can be accessed by clicking the document icon on this page.
11 Jan 2017

Order denying permit for APEX Timbermill Wind proposal

Timbermill_order_thumb In a 3-2 vote, the Perquimans County Board denied an application by Apex Clean Energy to erect the Timbermill wind energy facility. Timbermill, if approved, would have sited 57 turbines, each standing 599-feet tall. The order detailing the decision can be accessed by selecting the document icon on this page. The Conclusion of the order provided below.
22 Nov 2016

Recent Court Decisions Raise Important Considerations for Renewable Energy Projects

This important white paper provides perspective on how the courts are likely to respond to wind projects that might produce significant adverse impacts on the environment. Summary considerations excerpted from the paper are provided here while the full paper is shown below and accessible from the links on this page. Important Considerations It is clear that renewable energy projects sited on or across Federally-administered lands will be carefully reviewed by Federal courts. From these cases, at least three key considerations emerge, including: Courts are generally unwilling to credit environmental analyses without actual survey data, especially where sensitive species or sensitive areas are present; The use of mitigation measures to mask an apparent lack of baseline data does not appear to be a defensible position; and Careful and consistent managing of the administrative record is key to surviving a legal challenge to a project.
25 Jul 2016

Court rules in favor of county setback regulations

Image2016-06-01-153709_thumb In regards to the request for a judicial review filed by Apex, Judge Bailey of Greensburg entered his judgment on June 1, 2016 affirming the Rush County Board of Zoning Appeals July 1, 2015 decision, with the Setback Condition. If no appeal is filed, the judicial review will conclude. A brief summary of the ruling can be found below. The order issued by the judge can be accessed by clicking the link(s) on this page. 
1 Jun 2016

Steens Mountain wind project rejected: Onda v. Jewell

13-36078_thumb The Ninth District Court of Appeals has ruled in favor of the Oregon Natural Desert Association, and rejected a wind turbine project on Steens Mountain in southeast Oregon. The 104-megawatt project proposed by  Columbia Energy Partners would have erected 70 wind turbines and a high-capacity transmission line on Steens Mountain. The approximately 100 MW Echanis project would be sent power to Southern California as part of an agreement with Southern California Edison. The project also included a high-capacity transmission lines that cut across potential sage grouse habitat within the protected Steens Cooperative Project. A summary of the order is provided below. The full decision can be found by clicking the links on this page. Also attached to this page are the legal arguments presented by the government and by the environmental groups from March 2016.
27 May 2016

Vermont Supreme Court order: Rutland Solar project

Vermont-supreme-court-op15-230_thumb This split ruling by the Vermont Supreme Court regarding a permit granted for a 2.3-megawatt solar facility provides a useful examination of the debate over whether the views of local communities should hold significant weight when state siting boards have permitting authority. Ultimately the court ruled in favor of the project permit but a dissenting opinion issued by Judge Reiber offers a stinging response to the Vermont Public Service Board's decision to ignore community views when it permitted the project. Judge Reiber's opinion is provided below. The order can be accessed at the links included on this page. 
29 Apr 2016

Falmouth Zoning Board of Appeals Ruling

308985283-falmouth-zoning-board-of-appeals-ruling_thumb In this detailed ruling issued by the Falmouth Zoning Board of Adjustment in reference to Wind 1, one of two Vestas 1,65 MW turbines sited at the town's water treatment center, the board listed 38 separate finding on whether a permit should be issued that would allow the turbine to continue operating. The turbine was shut down following a court ruling that found the turbine was erected the town without first securing a permit. Some of the 38 findings are provided below. The full document can be accessed by clicking the links on this page.  
15 Apr 2016

Petition for Judicial Review of BPA Interconnection Approval: Whistling Ridge Energy Project

15-72788_opening_brief_filed_stamped_3-29-16_thumb Friends of the Columbia Gorge and Save Our Scenic Area have petitioned the court to review Bonneville Power Administration’s ("BPA") June 24, 2015 Record of Decision (“ROD”) approving the interconnection of the Whistling Ridge Energy Project to BPA’s electricity transmission system, based on BPA’s analysis under the National Environmental Policy Act (“NEPA”). This detailed brief filed on behalf of the groups provides an informative description of the circumstances surrounding BPA's decision and how the petitioners argue the NEPA provisions were incorrectly applied. A portion of the brief is provided below. The full document as filed with the U.S. Ninth Circuit Court of Appeals can be accessed by clicking the link on this page. 
3 Apr 2016

Request for declaratory judgment: Whitewater Wind LLC

Complaint-filed-whitewater-wind-nextera_thumb This complaint, filed by residents of Fayette County, Indiana, seeks a declaratory judgment by the Fayette Circuit Court that both the Decommissioning Plan and its addendum between the county and NextEra Energy Resources in reference to the proposed Whitewater Wind facility, be declared invalid and void, for failing to comply with the county’s zoning ordinance. The complaint also seeks “costs of this action” and other relief. Paragraphs 9-13 of the complaint are presented below. The full complaint can be accessed by clicking the document on this page.
15 Mar 2016

Apex Clean Energy: Tort claim against Rush County, IN

Apex-notice_of_tort_claim_3-4-16_thumb As of March 4, 2016, Apex filed a Notice of Tort Claim Pursuant to Indiana Code 34-13-3 (Indiana Tort Claims Against Governmental Entities and Public Employees Act). To summarize the notice, Apex claims that the commissioner’s official action on September 8th, 2015 to cease and desist all negotiations with Apex and to arbitrarily and capriciously reject the wind energy project will cause Apex to sustain economic losses. A portion of the tort claim is provided below. The full document can be accessed by clicking the links on this page. 
4 Mar 2016

http://www.windaction.org/posts?topic=Legal&type=Document
back to top