Documents filed under Legal

Seneca Wind: Notice of Application Withdrawal

Seneca_wind_application_withdrawal_notice_thumb In early 2018, Seneca Wind LLC initiated the process before the Ohio Power Siting Board to secure authorization to construct and operate a 70 turbine (up to 200 MW) wind energy facility on 25,000 acres of leased land situated in Seneca County, Ohio. This letter submitted to the Siting Board states that Seneca Wind LLC wishes to withdraw its application from consideration.
9 Aug 2019

Petition for review: USFWS approval of “R-Project” Transmission

Rline-_petition_for_review_thumb This civil suit filed in US District Court against the United State Fish and Wildlife Service challenges the permit granted Nebraska Public Power District to construct the R-Project Transmission Line slated to go through the Sandhills. The petition, which can be downloaded from this page, asserts that the government agency failed to properly assess the environmental impacts of the transmission line, particularly with regard to the Whooping Crane and the American Burying Beetle. The R-Project is a 225-mile transmission line. 
5 Jul 2019

Invenergy v United States Section 1603 cash grant decisions

Californiaridge_v_us_1603_thumb In these two court cases, parent company Invenergy, received cash outlays for two Illinois projects, Bishop Hill and California Ridge. The funds were distributed, but the government later discovered that a portion of the grants were overpaid. A suit was filed by Invenergy in order to prevent Treasury from taking any money back. In these final decisions, one for each project, the court ruled in favor of the Treasury. A portion of one decision is provided below. The full decisions can be accessed by selecting the document icons on this page.
20 Jun 2019

Notice of relinquishment and withdrawal: Black Fork Wind Farm

Black_fork_wind_relinquishment_of_permit_to_construct_2019-05-16_thumb The application for the Black Fork wind energy facility was initially submitted to the Ohio Power Siting Board (OPSB) on March 10, 2011. The project, if constructed would have included up to 91 turbines (up to 200 MW) across 14,500 acres in Richland and Crawford counties, Ohio. There was significant opposition to the project but it was granted a permit by the state. In December 2018, the Ohio Supreme Court ruled in a 5-2 decision that OPSB wrongfully granted the project an extension to the date on which construction was to begin from January 2017 to January 2019. The Court found that the change was an amendment to the permit and required a more extensive review process and would subject the project to more onerous state setback distances. 
16 May 2019

Court: Injunction order halting construction of Crazy Mountain Wind farm

Park_dv-2018-161_thumb Montana District Court Judge Jon A. Oldenburg ruled no construction activity involving the Crazy Mountain wind farm proposed by Pattern Energy can proceed including no alterations to roads until a trial is held to determine if the project will cause irreparable harm to the neighboring property owners. Judge Oldenburg decided that “[u]ntil the ultimate issues are decided by a trier of fact, the balance of equities does not fall in favor of one side or the other."  The full order can be accessed at the document link on this page. Below is an excerpt of the court's ruling justifying the injunction and halting construction of the project.
19 Mar 2019

Summit Ridge Wind Farm: Extension request and comments

Comments_on_summit_ridge_wind_farm_amendment_4_thumb The Summit Ridge Wind Farm was granted a site certificate by the Oregon Energy Facility Siting Council (EFSC or Council) on August 19, 2011. The applicant now seeks a 4th amendment to the certificate that extends the start construction timeline another two years. A host of objections have been raised about the project. This page includes comments by K. Shawn Smallwood PhD outlining environmental concerns with the project’s wildlife surveys and analysis. The Friends of the Columbia Gorge, Oregon Wild, and others present their own comments. The procedural background information and an excerpt of the comments filed with the Council are provided below. The full documents can be downloaded from the links on this page.
22 Feb 2019

PG&E injunction pleading against FERC interference

Pge_injunction_relief_-_ferc-filing2019-01-29_thumb In this court filing, utility-giant PG&E asks the court for an injunction against efforts by FERC to assert jurisdiction over the power contracts (PPAs) held by PG&E. Court documents show PG&E is bound by 387 PPAs with more than 350 companies totaling about $42 billion. The generators whose energy is under contract are at risk if PG&E is allowed to exit the agreements. A portion of PG&E's filing is provided below. The full document can be accessed at the links on this page.
29 Jan 2019

Wharton Wind Farm: cease and desist threat (letters)

L.ryan_cease_and_desist_letter_thumb Seventus LLC and Wharton Wind LLC are seeking to erect an industrial wind energy facility in Wharton County, Texas. A number of county residents organized in an effort to share information regarding the wind energy proposal and to discuss potential harmful impacts once the project is placed in service. Lacricia Ryan, who with her family operate a crop-dusting business in Wharton County, is part of the group looking to educate the community about the project. 
1 Jan 2019

Court Order in Falmouth Appeal: DENIED

Falmouth_greencenter_appeal_decision_-_denied_thumb The Massachusetts Appeals Court upheld a lower court's decision to deny intervention involving action between the town of Falmouth and the Falmouth zoning board of appeals in which judgment had already entered. The judgment declared that two wind turbines operated by the town were a nuisance and ordered that their operation cease and desist. The proposed interveners claimed that they were entitled to intervention as of right because they had compelling interests that were no longer being adequately represented by the town. The lower court ruled, and the appellate court affirmed that the motion be denied since the interveners could not likely establish standing, and that the motion was untimely. A portion of the 10-page order is provided below. The full order can be accessed by clicking the links on this page.
6 Nov 2018

Oral Arguments: In re Application of Black Fork Wind Energy LLC, Case no. 2017-0412

This important legal challenge of the Ohio Power Siting Board decision tests whether the Board ignored state law and the conditions of its own certificate approving construction of the Black Fork wind energy facility when it granted a requested extension of the permit. A detailed description of the case is provided below and at the link appearing on this page. Oral arguments were heard on August 1, 2018 and can be watched at this link. Black Fork is proposed as a 91-turbine facility with a maximum capacity of 200 megawatts. The permit was initially issued in 2012.
1 Aug 2018

WV PSC Order denying acquisition of wind facilities (Hardin Wind Facility and Beech Ridge II)

Wvpsc_denial-wind_farm_purchases_thumb The West Virginia Public Service Commission issued this order denying a petition filed by the Appalachian Power Company (APCo) and Wheeling Power Company seeking consent and approval for APCo to acquire the Hardin wind generation facility (Hardin Wind Facility), that is under development in Hardin County, Ohio, and the Beech Ridge II wind generation facility (Beech Ridge II Wind Facility) that is under development in Greenbrier County, West Virginia. The Beech Ridge II facility is a 50 Mw wind project and the Hardin facility is a 175 Mw wind project. An excerpt of the order is provided below that highlights the reasons for the denial. The full order can be accessed via the links on this page.
30 May 2018

Freeborn Wind LLC Order Denying Permit

Freeborn-wind-order20185-143018-01_thumb Freeborn Wind proposed to construct an up to 84 MW wind energy facility and associated facilities in Freeborn County, Minnesota. The Project is part of an up to 200 MW wind project in Freeborn County, Minnesota, and Worth County, Iowa. In this final order of recommendation, the Administrative Law Judge concluded that Freeborn Wind failed to demonstrate that the proposed Project will meet the requirements of Minn. R. 7030.0040, the applicable Minnesota Noise Standards. Portions of the order are provided below. The full order can be accessed by clicking the document links on this page.
14 May 2018

Ambrose: Courts Uphold Wind Turbine Noise Limits

Letter_to_wind_action_group_-_8dec2017_thumb This important letter by acoustician Stephen Ambrose explains how two separate court decisions, one in Massachusetts and the other in Michigan, together provide clarity on what the minimum protective noise limits should be when siting industrial wind energy facilities. Mr. Ambrose's letter includes links to the two decisions as well as supporting background information. The content of the letter is shown below. The original can be downloaded from this page.
8 Dec 2017

Decision: Tuscola Wind III v Almer Township MI

Tuscola_iii_v_almer_township_order_thumb This important decision by US District Court Judge Thomas L. Ludington addresses two arguments proffered by the wind industry. The first relates to the industry's argument that noise standards for limiting turbine noise emissions that are based on Lmax are not reasonable. The second discusses the argument that restricitve ordinances, in this case an Lmax noise limit, are de facto exclusionay zoning. Judge Ludington takes both claims on and finds the wind company's arguments are without merit. A portion of the decision is provided below. The full decision can be downloaded from this page.
3 Nov 2017

ERT Wiggins v. Ontario: Decision revoking wind turbine permit

Ert_16-036_wiggins_v_ontario_-_decision-2017-08-16_thumb In this important decision by the Ontario Environmental Review Tribune, the Tribune officially revokes Wpd Canada's permit to install eight 137-meter (450 feet) tall wind turbines in close proximity to the Collingwood Regional Airport and a private air field owned by Kevin and Gail Elwood. In its October 2016 decision, the ERT had determined that the appellants met the test that showed there would be harm to human health. The ERT also agreed that irreversible harm to the natural environment, specifically to bats, warranted further investigation. Wpd Canada was granted an opportunity to show that mitigation could resolve the concerns. The ERT in this decision held that the risk to human health and safety was unacceptable. A portion of the decision is provided below (paragraphs 15-20) pertaining to the turbines impairing safe air travel. The full decision of the ERT can be found by clicking the links on this page.
16 Aug 2017

Falmouth Wind Turbines 1 and 2: Court Order to cease and desist operation

Judge_moriarity_decision_june_2017_thumb In this important ruling issued by Massachusetts Superior Court Judge Cornelius J. Moriarty II, the court ordered that the decision of the Falmouth MA Zoning Board of Appeals be affirmed to the extent that the operation of Wind 1 and Wind 2 constitute a nuisance and that the Town of Falmouth cease and desist operation of the wind turbines immediately. The full order can be accessed by clicking the document icon located on this page.  
21 Jun 2017

Greater Sage-Grouse on Steens Mountain: Final Ruling

12-596_order_granting_motion_to_vacate_4-18-17_thumb In this important ruling by the U.S. District Court for the District of Oregon, the court vacated the Secretary of the Interior’s approval of the proposed Steens Mountain wind project which would have sited up to 69 turbines and a 230 kv transmission line in area critical for sage grouse. The order is provided below and can also be accessed by clicking the links on this page. 
18 Apr 2017

Camp Perry Wind Complaint

Campperrycomplaintasfiled-1_thumb Two leading bird conservation groups, American Bird Conservancy (ABC) and Black Swamp Bird Observatory (BSBO), have filed a lawsuit against the Ohio Air National Guard (ANG) over its plans to build and operate a wind turbine at its Camp Perry facility. Located in Port Clinton, Ohio, on the shore of Lake Erie, Camp Perry lies in a major bird migration corridor, close to numerous Bald Eagle nests, and is likely to kill species protected under the Endangered Species Act such as Kirtland's Warbler and Piping Plover. The complaint can be accessed by clicking the links on this page. A portion of the complaint is provided below.
27 Mar 2017

ABC brief supporting disclosure of bird-bat mortality: Blue Creek Wind facility

Brief_thumb This brief, filed before the Ohio Court of Common Pleas in Franklin County, Ohio, responds to Iberdrola's (Avangrid Renewables) action to stop any public disclose of bird/bat mortality data at its Blue Creek wind facility. Iberdrola has argued that the number of birds and bats killed by its turbines is a “trade secret” protected under Ohio law. The introduction and summary of arguments for why Iberdrola's claims are not supported by Ohio law are provided below. The full brief can be accessed by clicking the links on this page. The original complaint can be found here. 
7 Mar 2017

http://www.windaction.org/posts?topic=Legal&type=Document
back to top