Articles filed under Legal

Icebreaker developer appeals ruling after project approval

The developer of the US’ first freshwater wind farm in the Great Lakes has appealed against over-restrictive operating restrictions on the approval it received last month. After a long permitting journey to satisfy 14 federal, state and local agencies, the 20.7MW Icebreaker in Lake Erie was unanimously approved by the Ohio Power Siting Board (OPSB) in May.
24 Jun 2020

Icebreaker Wind appeals OPSB’s ruling

The Lake Erie Energy Development Corp. (LEEDCo) has asked the board to reconsider its decision so that the plans to build and operate the six-turbine demonstration project eight miles off Cleveland’s shoreline can move forward.
23 Jun 2020

Nebraska Public Power District says R-Project route won’t change after federal judge vacates permit

The Denver judge said Fish and Wildlife’s order granting the permit didn’t review possible routes to avoid O’Fallon’s Bluff, despite saying in its final environmental impact statement that running electrical lines over it would have “a long-term, high-intensity indirect (visual, auditory and atmospheric) effect.” Thousands of wagons on the Oregon-California Trail crossed the bluff from 1843 to 1866, cutting deep dips that remain today. It parallels Interstate 80 to the south between Sutherland and Hershey.
19 Jun 2020

Birdwatcher's vow: I will take wind farm fight to high court

Hamish Cumming will continue his fight in the Victorian Court of Appeal on June 15 as he seeks to have the $1.5 billion Golden Plains wind farm, planned for Rokewood northwest of Geelong, revised to about 130 turbines. Mr Cumming said buffer zones around brolga breeding and flocking areas near the Golden Plains wind farm had been applied incorrectly by developer Westwind.
27 May 2020

Judge strikes plan to put wind turbines on Bethlehem Authority land

A Carbon County judge has sided with two property owners who appealed the construction of 37 wind turbines on Bethlehem Authority-owned property, arguing the structures would be too loud and ruin their property values. The judge also ruled that a special exception the turbine company, Atlantic Wind LLC, was seeking should be vacated because Atlantic Wind failed to show the project will comply with Penn Forest Township zoning codes.
29 Apr 2020

Carbon judge rules against Atlantic Wind turbines

In a 61-page opinion Judge Steven R. Serfass wrote, “Atlantic Wind has failed to demonstrate that the sound produced by the proposed wind turbines will not exceed 45 A-weighted decibels and that there will be only one principal use on the proposed project area. Atlantic Wind has failed to meet its burden of persuasion that the proposed wind turbine project will comply with all the objective requirements for special exception to the granted under the Penn Forest Township Zoning Ordinance.”
24 Apr 2020

Fishermen seek delay in Gulf of Maine offshore wind planning

In deeper waters of the gulf, wind power will be achieved only with the use of floating turbines. The extensive anchoring and cabling that would be required means “lease areas will become de facto closures to fishing,” the Responsible Offshore Development Alliance wrote in an April 14 letter the governors of Maine, New Hampshire and Massachusetts, and the federal Bureau of Ocean Energy Management.
16 Apr 2020

http://www.windaction.org/posts?topic=Legal&type=Article
back to top