Library

Avangrid has lost interest in Hopkinton

“If the town in the very near term can examine those changes to the zoning ordinance, we may consider re-engaging with Hopkinton, but the pre-emptive rejection means we will focus on other New York projects in areas with clearer paths to pursue renewable development,” Mr. Copleman wrote.
1 Jun 2018

WV PSC Order denying acquisition of wind facilities (Hardin Wind Facility and Beech Ridge II)

Wvpsc_denial-wind_farm_purchases_thumb The West Virginia Public Service Commission issued this order denying a petition filed by the Appalachian Power Company (APCo) and Wheeling Power Company seeking consent and approval for APCo to acquire the Hardin wind generation facility (Hardin Wind Facility), that is under development in Hardin County, Ohio, and the Beech Ridge II wind generation facility (Beech Ridge II Wind Facility) that is under development in Greenbrier County, West Virginia. The Beech Ridge II facility is a 50 Mw wind project and the Hardin facility is a 175 Mw wind project. An excerpt of the order is provided below that highlights the reasons for the denial. The full order can be accessed via the links on this page.
30 May 2018

Scott Wolf: R.I.‘s ‘Wild West’ of renewable energy

To end the current destructive “Wild West” approach to renewable energy siting in Rhode Island, we believe that the state should immediately place a moratorium on state incentives for utility-scale renewable-energy development ...until the state establishes economic incentives to encourage the siting of utility-scale renewable energy on developed and disturbed locations, such as landfills, brownfields, rooftops, parking lot canopies, and gravel banks, and disincentives to prevent the continued loss of our forests and prime agricultural soils.
30 May 2018

Savoy to decide wind project's fate in July

While the Zoning Board of Appeals made no decision Tuesday night, its chairman and several members hinted that they are leaning against overturning a building inspector's decision to deny the company a crucial permit. ...Minuteman Wind will have one more chance to persuade members of the panel to overturn Building Inspector Phil Delorey's April 5 rejection of its application for a building permit. 
30 May 2018

Wind turbine fire in the Fens

Fen_turbine_fire-cambsfirerescue_image4_thumb The incident involved one of 5 turbines at the Ransonmoor wind farm which is located in the Fens of Cambridgeshire. The project consists of 2 Senvion MM82 and 3 Gamesa G80 wind turbines for a total nameplate capacity is 10.1 MW. The Gamesa turbines were placed in sevrice in 2007; the Senvion turbines followed a year later in 2008. The damaged turbine was built by Gamesa.
30 May 2018

Scituate selects company to conduct wind turbine study

Scituate selectmen voted unanimously Tuesday night to award a contract for conducting an acoustical study of the Scituate Wind turbine to Epsilon Associates as an independent consultant. The Maynard-based company has performed similar testing in Massachusetts, and other states, and has worked with the Massachusetts Department of Environmental Protection (DEP), according to Al Bangert, special projects director.
29 May 2018

Editorial: Will wind energy deliver?

Last week, Massachusetts announced the winner of a new offshore wind contract — which means the Bay State is about to get its first offshore wind farm. The Vineyard Wind project will be located at least a dozen miles south of Martha’s Vineyard and is expected to generate 800 megawatts of energy — enough to power 400,000 homes. Vineyard Wind is aiming for 2021 to be up and operational.
29 May 2018

Turbines sit idle while Ramea power bills increase

When Gould asked Hydro NL when Ramea’s residents can expect their power bills to decrease, the company pointed to the generators as the issue. “They say they have to keep a generator running because when a surge is needed those windmills can’t provide the energy on short notice,” Gould stated. “So therefore we’re still burning diesel fuel, so the charges will remain as they are.” 
28 May 2018

http://www.windaction.org/posts?p=4
back to top