Library from Ontario

Developer has 9 more months to complete study

EDP Renewables Ken Little says the study will continue "until all components are complete per the REA requirements. ...Still, the ministry has since conducted its own recordings of the Brinston-area turbines after an official complaint submitted by nearby residents Leslie Disheau and Glen Baldwin last month.
9 Aug 2014

A sunny Ontario experiment gone wrong

In its latest 18-month outlook, the IESO forecasts that 99.5 per cent of Ontario’s 12,947 MW of installed nuclear capacity will be available during summer consumption peaks. But it predicts only 13.7 per cent of the 1,824 MW of installed wind capacity will be available. Solar is even less reliable. So, when wind and solar actually do produce power, it’s usually dumped.
5 Aug 2014

Big Thunder wind park contract cancelled

“The Big Thunder Wind Park project was significantly delayed due to force majeure events,” added Bernard. “Under a FIT contract, either party to the contract has the right to terminate the contract if force majeure events delay a project past 24 months. The OPA terminated the Big Thunder Park project for this reason”.
27 Jul 2014

Contract scrapped

A spokeswoman for the Nor’Wester Mountain Escarpment Protection Committee says she’s ecstatic that Horizon Wind Inc.’s planned turbine farm in Thunder Bay might be dead in the water. ...It's not necessarily the end of the project, she cautioned. "It wouldn't come as a surprise if there is an appeal," she said, adding she thinks treaty rights must come first and be protected and will ultimately prevail.
25 Jul 2014

Appeal delays Grand Bend wind farm

Preliminary work for the wind farm will likely start later this year, but major construction won’t begin until the appeals are settled. “Our company policy is not to do much during an appeal process,”
9 Jul 2014

Wind turbine sound studies to cost more than originally planned

Council initially enacted a wind turbine development bylaw in 2009 and then updated it last fall to address concerns expressed by residents. The updated version changed the setback distance of a turbine to the nearest residence from 750 metres to 1,000 metres (one kilometre) and also included a maximum sound tolerance of 36 decibels for any turbine operating within the county.
20 Jun 2014

Samsung Deal Dead

Mayor Milne says it appears the wind turbine project is dead, but you never know if council will bring it up for discussion again in the future. According to the township's bylaw they need a two-thirds vote to reconsider any decision of council.
20 Jun 2014

Turbines spin without approval in West Lincoln

"The ministry has told the company not to operate while the amendment application is under review," said Kim Groombridge, MOE district supervisor for Niagara. "They are operating out of compliance." The project was delayed after it was discovered that several of the turbines were built closer than the 95-metre property line setback.
19 Jun 2014

Shelburne left in the dark by wind project

The Town of Shelburne has received little in the way of co-operation from the project’s proponents. And, as was evidenced during a regular scheduled council meeting on Monday, the municipal government is fed up with the lack of attention. The town has yet to receive project drawings, traffic mitigation plans, or an outline of potential measures to ensure the environment’s protection
17 Jun 2014

McGuinty government changed green energy rules to benefit Liberal-linked firms, court filing charges

A U.S. wind power developer that is seeking $653-million in damages under a NAFTA challenge accuses the government of Ontario of manipulating Green Energy Act rules to benefit the interests of Liberal-connected firms. ...The court filing, recently made public in the case that pits Mesa Power, a Texas-based developer owned by U.S. financier T. Boone Pickens, against the government, alleges Ontario replaced “transparent” criteria for the selection of energy projects with “political favoritism, cronyism and local preference.”
9 Jun 2014

http://www.windaction.org/posts?location=Ontario&p=19
back to top