Library from Ontario

Clearview Wind turbines licence revoked

There may not be eight wind turbines spinning in Clearview Township after all. In a decision released Wednesday, the Environmental Review Tribunal revoked the renewable energy approval for the project, saying the danger to human life and safety was too great.
17 Aug 2017

ERT Wiggins v. Ontario: Decision revoking wind turbine permit

Ert_16-036_wiggins_v_ontario_-_decision-2017-08-16_thumb In this important decision by the Ontario Environmental Review Tribune, the Tribune officially revokes Wpd Canada's permit to install eight 137-meter (450 feet) tall wind turbines in close proximity to the Collingwood Regional Airport and a private air field owned by Kevin and Gail Elwood. In its October 2016 decision, the ERT had determined that the appellants met the test that showed there would be harm to human health. The ERT also agreed that irreversible harm to the natural environment, specifically to bats, warranted further investigation. Wpd Canada was granted an opportunity to show that mitigation could resolve the concerns. The ERT in this decision held that the risk to human health and safety was unacceptable. A portion of the decision is provided below (paragraphs 15-20) pertaining to the turbines impairing safe air travel. The full decision of the ERT can be found by clicking the links on this page.
16 Aug 2017

Council gives green light to controversial wind turbine project on Amherst Island

The president of the Association to Protect Amherst Island says she’s disappointed with what she calls a lack of transparency on the township’s part. “The township has not established very clearly what the boundary of the roads are. So owners are concerned that the property is going to be used without their consent,” said Michelle Lelay of the Association to Protect Amherst Island.
11 Aug 2017

Family angered by wind executive's response; Preliminary results indicate turbidity of water is well above acceptable level

Jessica Brooks couldn't believe it when she learned through media reports that an official with the North Kent Wind project stated there was no evidence of any issue found, so far, with her family's well water. ...there was so much sediment built up, it took several minutes to flush the system as the water came in dribbles and sputtered at times.
9 Aug 2017

Ontario schools to enter mediation over turbine issue

The turbine has sat idle since November 2016, when its transformer stopped working. ...school district officials argued the energy company defaulted on the contract and demanded the company uphold the current contract by fixing the turbine without the assurance of a contract extension.
9 Aug 2017

Plant closure underscores Liberal energy blunders

McCarter found 30,000 of those jobs were in construction, lasting only one to three years, and the government had failed to take into account studies in other jurisdictions showing that for each job created through renewable energy, two to four were lost in other sectors of the economy, because of higher electricity prices.
20 Jul 2017

$1B worth of energy wasted last year: engineers

Acchione said the province is wasting the power through a practice called “curtailment.” It means that when the province’s hydro generators produce power consumers don’t need, and it can’t be exported, they have to dump it. ...“The numbers...show that Ontario’s cleanest source of power is literally going down the drain because we’re producing too much of it.”
30 Jun 2017

http://www.windaction.org/posts?location=Ontario
back to top