Library filed under Zoning/Planning from Massachusetts

Savoy to decide wind project's fate in July

While the Zoning Board of Appeals made no decision Tuesday night, its chairman and several members hinted that they are leaning against overturning a building inspector's decision to deny the company a crucial permit. ...Minuteman Wind will have one more chance to persuade members of the panel to overturn Building Inspector Phil Delorey's April 5 rejection of its application for a building permit. 
30 May 2018

Savoy wind turbine plan sparks Hawley concerns

“It [the project] will require the fragmenting of one of the largest blocks of undisturbed forest in western Massachusetts,” he said. “This project is about money — not about saving the environment.” “And then there’s the well-documented noise issues,” he said. “I’m convinced about 200 acres of our land will become undevelopable for residential use in the future.”
19 Dec 2016

Falmouth Zoning Board of Appeals Ruling

308985283-falmouth-zoning-board-of-appeals-ruling_thumb In this detailed ruling issued by the Falmouth Zoning Board of Adjustment in reference to Wind 1, one of two Vestas 1,65 MW turbines sited at the town's water treatment center, the board listed 38 separate finding on whether a permit should be issued that would allow the turbine to continue operating. The turbine was shut down following a court ruling that found the turbine was erected the town without first securing a permit. Some of the 38 findings are provided below. The full document can be accessed by clicking the links on this page.  
15 Apr 2016

No Decision Rendered By Zoning Board On Falmouth Wind Turbine Permit

Following a decision-making flow chart prepared by Falmouth special counsel Mark Bobrowski, board members weighed the existing turbine’s consistency with the 2010 town bylaw that was in place when Wind 1 was erected. ...board chairman Kimberly A. Bielan argued that neighbors testified in the hearing that curtailment would not lessen the impact of the turbine on their daily lives.
6 Mar 2016

Falmouth wind turbine permit headed for denial

The special-permit application is just one legal issue surrounding the turbines. Nine lawsuits are now pending in Barnstable Superior Court about their operation, said Westboro attorney Christopher Senie, who represents some of the neighbors. The special-permit denial may help quell some of those suits as well as deal with the continuing operation of Wind 2, he said. 
6 Mar 2016

Falmouth Wind Turbine: Deemed ineligible for permit

302178715-decision-making-spreadsheet_thumb On the morning of March 5, 2016, the Falmouth Zoning Board of Appeals (ZBA) deliberated over whether the Town's application for a special permit to retain Wind 1 should be approved. Wind 1 is the first of two Vestas V82 1.65 MW turbines erected at the community's wastewater treatment facility. The turbines created significant controversy following noise complaints by nearby residents beginning in 2010 when the turbines were first turned on. In a February 2015 ruling, the Massachusetts appeals court found that the Town of Falmouth failed to meet the requirements under the local bylaws when it erected Wind 1 without first obtaining a permit. The ZBA hearing was to determine whether a newly filed application met the requirements for a permit to be issued retroactively. Wind I has been idle since September 2015. The attached documents represent the arguments by the town's attorney (in favor of issuing a permit), the residents (on why a permit should not be issued), and a spreadsheet itemizing the decisions that need to be made the the ZBA. The below summary by Mark Cool explains how the Board ruled on each of the decisions. 
5 Mar 2016

Falmouth turbine permit headed for denial

The majority of board members found fault with the application on more than one front, including the zoning requirement that the turbine known as Wind 1 will not have "adverse effects" on either the neighborhood or the town. Throughout the permit hearing, which stretched over a half dozen meetings and several months, neighbors of the turbine presented evidence on multiple fronts, including personal testimony, in an attempt to show the negative effects of the turbine.
5 Mar 2016

Falmouth turbine zoning decision looms large

A six-year battle over the town's wind turbines faces a critical turning point Saturday when the Falmouth Zoning Board of Appeals will deliberate a special-permit application to keep one of the devices operational. The board has scheduled a public meeting to deliberate the application and is expected to vote on it, although a delay is possible. But whenever the board's decision comes, whether it marks the beginning of the end for the fight or simply sparks another round of litigation remains to be seen.
4 Mar 2016

Turbine special permit hearing closes

Representatives for the town and a dozen neighbors of its first wind turbine, known as Wind 1, gave closing remarks Thursday, January 28, regarding a special permit application for the turbine. The turbine is currently shut down in accordance with a cease-and-desist order issued by the board in the fall.
2 Feb 2016

http://www.windaction.org/posts?location=Massachusetts&topic=Zoning%2FPlanning
back to top