Articles from Massachusetts

Cape Wind appeals permit extension rejection; Wind farm officials say nothing has changed

In its request for an extension of the transmission line approval, Cape Wind said none of the circumstances that led to the original approval has changed. The company said “it is quite feasible” it may be able to begin construction of the wind farm by the extension date of May 1, 2017, but conceded that if there are further delays it may need more extensions.
5 Apr 2016

Market Policies, Emissions Goals on Collision Course in New England

Backers of gas generation countered that renewables are benefiting from government-backed subsidies and long-term contracts that threaten to reintroduce government-mandated integrated resource planning. ...state policies are giving renewables undue advantage and undermining conventional generators’ investments in the market.
21 Mar 2016

Ruling on turbine complaints expected within two weeks

Attorney Kevin J. Joyce of Boston, representing the residents, filed a motion requesting a temporary restraining order against Future Generation Wind putting the turbines into operation. In his motion, Mr. Joyce stated that the turbines are “undisputedly in violation” of the board of health’s regulations. The motion further stated that preventing operation of the turbines would be in the best interest of public health, safety, and welfare.
11 Mar 2016

Time to show wind developers the door

Maine was originally part of Massachusetts, and we act like we are still, but I would admonish Maine residents to rise up and show the wind developers the door. Let them try constructing these useless monstrosities in the Berkshires and see how far they get. I have yet to delineate the total crony corruption that has enabled this industrial wind disaster but here are a few nuggets to chew on.
11 Mar 2016

Wind energy is a public health problem

Wind turbine projects have previously been rejected in Wellfleet, Eastham, Orleans, Harwich, Dennis, Brewster, Barnstable and Bourne. Health concerns have been a major issue. A Superior Court judge, hearing neighbor’ complaints that wind turbine noise constituted an intolerable “nuisance” that was causing “irreparable harm,” issued an injunction to curtail operations. The “Falmouth experience” is not unique.
7 Mar 2016

No Decision Rendered By Zoning Board On Falmouth Wind Turbine Permit

Following a decision-making flow chart prepared by Falmouth special counsel Mark Bobrowski, board members weighed the existing turbine’s consistency with the 2010 town bylaw that was in place when Wind 1 was erected. ...board chairman Kimberly A. Bielan argued that neighbors testified in the hearing that curtailment would not lessen the impact of the turbine on their daily lives.
6 Mar 2016

Falmouth wind turbine permit headed for denial

The special-permit application is just one legal issue surrounding the turbines. Nine lawsuits are now pending in Barnstable Superior Court about their operation, said Westboro attorney Christopher Senie, who represents some of the neighbors. The special-permit denial may help quell some of those suits as well as deal with the continuing operation of Wind 2, he said. 
6 Mar 2016

Falmouth turbine permit headed for denial

The majority of board members found fault with the application on more than one front, including the zoning requirement that the turbine known as Wind 1 will not have "adverse effects" on either the neighborhood or the town. Throughout the permit hearing, which stretched over a half dozen meetings and several months, neighbors of the turbine presented evidence on multiple fronts, including personal testimony, in an attempt to show the negative effects of the turbine.
5 Mar 2016

Residents sue town over wind turbines

A group of Bourne residents has brought a lawsuit against town officials and Future Generation Wind LLC relative to the construction of four giant wind turbines at the Bourne-Plymouth town line. The case was heard in Barnstable Superior Court on Friday, March 4. The judge in the case rejected the neighbors' request for a temporary injunction, which would have halted work on the project.
4 Mar 2016

Falmouth turbine zoning decision looms large

A six-year battle over the town's wind turbines faces a critical turning point Saturday when the Falmouth Zoning Board of Appeals will deliberate a special-permit application to keep one of the devices operational. The board has scheduled a public meeting to deliberate the application and is expected to vote on it, although a delay is possible. But whenever the board's decision comes, whether it marks the beginning of the end for the fight or simply sparks another round of litigation remains to be seen.
4 Mar 2016

Fishermen Give Cold Shoulder to Offshore Wind Developer

A representative from Denmark’s largest energy company had a cold reception in Chilmark this week as commercial fishermen and others discussed a proposed wind farm south of the Vineyard. Andy Revill, a fishermen’s liaison for Dong Energy, traveled from the U.K. to meet with fishermen. ...But fishermen who gathered at the Chimark town hall on Tuesday said that would almost surely interfere with gillnetters in the area.
12 Feb 2016

http://www.windaction.org/posts?location=Massachusetts&p=18&type=Article
back to top