Library from Massachusetts

Fishermen, wind farm developers at odds

The Responsible Offshore Development Alliance called for the creation of six travel lanes, each one four nautical miles in width, through the entire lease area off the coast of the two states. The offshore wind developers in November had proposed no special travel lanes, choosing instead to let fishermen navigate through turbines set one nautical mile apart traveling north and south and seven-tenths of a nautical mile going diagonally.
7 Jan 2020

5 offshore wind firms agree to standard configuration

The agreement is significant because many Massachusetts politicians, including US Rep. Joe Kennedy III and Sen. Ed Markey, have accused the Bureau of Ocean Energy Management and the Trump administration of playing politics with the process. But the agreement by the five wind farm developers suggests they, and particularly Vineyard Wind, recognized a need to address the consistency of their project designs.
19 Nov 2019

Vineyard wind pushes IRS for subsidy extension on delayed offshore project

“Since the business case is being impacted by external delays, we are requesting an extension from the IRS for the originally planned ITCs of the project,” Torgerson told analysts. “We’re petitioning the IRS to get an extension of that ITC at the 24 percent level…through the 2022 timeframe.” The delay means Vineyard may be able to upgrade to longer rotor blades for its 9.5-megawatt MHI Vestas turbines, Torgerson said — jumping from a 164-meter rotor diameter up to 174 meters. Longer blades mean more electricity can be generated.
1 Nov 2019

Mayflower’s lowest-price offshore wind option selected

Few details about the price or the onshore investment were revealed, but Mayflower said in its original bid that the price would be “the lowest cost offshore wind energy ever in the US.” Mayflower is a joint venture of Shell New Energies and EDP Renewables. ...It appears Mayflower was far and away the easy choice. The state’s press release said the company offered a lower price and greater economic development opportunities than the other two bidders – Vineyard Wind, the company that won the first offshore wind procurement, and Bay State Energy, which lost for the second time.
30 Oct 2019

Vineyard Wind, Edgartown Commission reach settlement

The commission this summer denied the project's plans to bury two transmission cables in Nantucket Sound and Muskeget Channel areas within Edgartown, and the project appealed to the state Department of Environmental Protection (DEP). After the department issued an order of conditions favoring the project, the commission appealed and the settlement was reached before that appeal was fully heard by another wing of the DEP.
2 Oct 2019

Trump aide offers no guidance on Vineyard Wind

“It’s going to take some time, longer than we expected for this project,” said Bennett, who was asked about the agency’s timetable by Attorney General Maura Healey’s chief of staff, Mike Firestone. Bennett was at the Sheraton Boston Hotel taking part in an offshore wind panel at an eastern region meeting of the National Association of Attorneys General.
27 Sep 2019

Next Step For Turbines: Issuing RFQ

This RFQ is part of the town’s effort to relocate and operate its two Vestas 1.65-megawatt, V-82 wind turbines with 80-meter-tall towers from the wastewater treatment plant site on Blacksmith Shop Road to an alternative location outside Falmouth. In June, Mr. Suso said he expected to issue an RFP regarding the wind turbines within 30 days. The matter proved more complicated than expected.
13 Sep 2019

Edgartown, Vineyard Wind double-down

Edgartown conservation agent Jane Varkonda told The Times Edgartown didn’t receive the August 5 superseding order of conditions from the commonwealth in a timely manner. Varkonda said she learned by happenstance the decision had been made during a conversation with a state official. Upon learning Edgartown was without the decision, the official sent it.
28 Aug 2019

Troubling questions, concerns raised about off-shore wind farms

Overwhelming, too, for Al Eagles, a lobsterman from Newport, who questioned why the federal government is allowing projects to go forward when so little is known about their effects. “To me, everything you said up here was all unknowns,” Eagles said to Hare. “We could be devastating entire species out there. By the time we realize it, it would be too late.” Lanny Dellinger, also a Newport lobsterman and chair of a board that advises Rhode Island coastal regulators on fishing issues related to offshore wind, said the entire fishing industry is under threat. 
22 Aug 2019

Wind turbines and radar mix poorly

Glander went on to write that the Coast Guard may make the same recommendation for Vineyard Wind that it did for the Block Island Wind Farm, a research analysis indicating whether the turbines “produce radar reflections, blind spots, shadow areas, or other effects that could adversely impact safety of navigation.” If there are negative impacts to marine radar, Glander wrote, Vineyard Wind should recommend how to remedy them. If such remedies are necessary, he wrote they should be “funded by Vineyard Wind.”
22 Aug 2019

2 views on Vineyard Wind delay

It is furthermore unclear how Secretary Bernhardt could issue a decision on the DEIS, when critical impact categories such as fishing vessel transit, disruption payments, baseline ecological information, radar interference and others are yet to be settled. 
19 Aug 2019

Sources: Vineyard Wind Decision Delayed Until December 2020

Final approval for the Vineyard Wind Project will likely not happen for at least another 18 months, according to information received from multiple sources by The Public’s Radio. This means the country’s first large scale offshore wind farm won’t begin construction in time to take advantage of a lucrative federal tax credit that expires at the end of the year. 
19 Aug 2019

http://www.windaction.org/posts?location=Massachusetts
back to top