Library from Massachusetts

Report: Moving disputed Falmouth turbine would cost $3M

One of the two wind turbines under a court order never to operate at their current spot may spin again on the wastewater treatment plant property, a little less than a half mile north from where it now stands. Accomplishing the move, however, would cost the town just over $3 million and isn’t likely to appease critics of the turbine’s current location.
16 Oct 2018

What’s next for Falmouth turbines?

Weston and Sampson, engineers hired by the town to look at logistics and costs related to dismantlement and removal of the turbines, are scheduled to present their findings to selectmen Monday at 8 p.m., during the board’s regular meeting in Town Hall.
15 Oct 2018

Vineyard Wind, Barnstable officials sign agreement on cable project

 Barnstable and Vineyard Wind officials have signed a host community agreement that includes $16 million in payments to the town in return for the offshore wind energy developer landing a high-voltage electric power transmission cable at William H. Covell Memorial Beach rather than via a disputed route through Lewis Bay in West Yarmouth. But a final decision on the transmission cable route, the landing location and other details is still to be determined. 
4 Oct 2018

Yarmouth shellfishermen to participate in offshore wind cable hearings

The proximity of the men’s grant areas means their oysters, which total about 3,250,000, could be smothered by sand and silt that’s stirred up when Vineyard Wind lays the cable, the letter contends. Although Vineyard Wind officials have met with the shellfishermen multiple times and proposed solutions that include installing silt curtains while work is conducted, there’s no evidence those solutions will work, according to the letter.
2 Oct 2018

Vineyard Wind execs buoyed by report

A September report from Bank of America Merrill Lynch indicated that the federal Bureau of Ocean Energy Management would approve projects like Vineyard Wind in a timely manner, Beane said. The report said timing of permitting affects whether offshore wind developers can take advantage of federal investment tax credits that are expected to expire in 2024.
1 Oct 2018

Falmouth neighbors want wind turbines taken down

Funfar’s lawyer James Rosenblum argued that Wind 2 is the same make and model as Wind 1, and neither was ever issued a special permit from the zoning board. The lack of a special permit had never been legally challenged in court for Wind 2, as it had for Wind 1, “but that doesn’t mean Wind 2 is a legal structure,” Rosenblum said. “The structure had a legal building permit but doesn’t have a legal special permit and never did,” he said.
22 Sep 2018

Building Commissioner says Wind 2 not abandoned

In his response, Mr. Palmer said this regulation does not apply to Wind 2 because of when it was installed. The letter indicates Wind 2 was issued a permit and became operational in February 2012. “The building permit and the date of initial operation are both beyond the six year enforcement provision of G.L. c. 40A, s. 7 for structures erected in reliance upon a building permit,” Mr. Palmer wrote.
22 Sep 2018

State finds flaws In turbine noise study

In reviewing the study, the Massachusetts Department of Environmental Protection found that noise samples were collected at the wrong time of day and that not all the turbines were spinning when the sampling was done. The state also pointed out that some necessary information was missing from the analysis and that the report provided conflicting information relative to the turbines’ exact locations on the site.
6 Sep 2018

Petition mobilizes opponents of proposed Yarmouth power line

Press_release_petitions_presented_to_gov._and_yamouth_bos_08__28_2018_thumb Thousands of visitors and residents have signed a petition opposing an effort by offshore energy company Vineyard Wind to bring a high-wattage transmission cable through Lewis Bay and onshore in Yarmouth. ...A copy was given to Gov. Charlie Baker last week and to the Yarmouth selectmen at their meeting Tuesday, where Chairman Norman Holcomb told residents the board was open to hearing concerns.
29 Aug 2018

Falmouth resident shares lasting turbine troubles

Wind 1 and Wind 2, the two 1.65-megawatt turbines the Town of Falmouth installed on industrial-zoned land between 2009 and 2010, no longer turn or generate electricity. However, Falmouth residents Neil P. Andersen and Elizabeth L. Andersen said they still feel the aftereffects from the turbines and from their legal fight against them.
28 Aug 2018

Neighbors of Plymouth turbines bring health concerns to Bourne board

In a plea for help, a small group of residents came in front of the Bourne Board of Health on Aug. 8 after a Superior Court judge ruled that Bourne officials didn’t have the authority to regulate the construction of the turbines because they were outside of the town’s jurisdiction. ...however, the judge had written that a “Board of Health has broad powers to regulate and prevent nuisances that affect the public health,” adding that it remained to be seen whether the operation of the turbines would be a nuisance affecting the health of Bourne residents.
20 Aug 2018

Conflicted DEP fails to address wind hazards

The DEP can no longer help enforce its own regulations because of its involvement in wind turbine contracts. The Project Regulatory Agreement does not take into consideration public health and safety it has become immoral with despicable inhuman conduct bordering on criminal. We know today the DEP has been aware residents have been living in a toxic environment around the wind turbines.
13 Aug 2018

Buzzards Bay residents raise issue with turbines

Buzzards Bay residents plagued night-and-day by four Future Generation wind turbines operating on Mann cranberry bog in South Plymouth have returned to the Bourne Board of Health seeking intervention and relief. The board, however, says its jurisdiction does not extend across the town line. The board has been legally advised not to consider out-of-town matters already adjudicated by the Barnstable Superior Court.
10 Aug 2018

http://www.windaction.org/posts?location=Massachusetts
back to top