Destruction of a mountain: Bingham Wind site work

These images demonstrate the size and scale of land preparation required to construct turbine projects using machines standing nearly 500-feet in height. First Wind is constructing its 57-turbine wind facility in Somerset County, Maine. The project, at 185 MW, will be the largest in Maine and in New England. The turbines will have a tower height of 94 Meters and rotor diameter for the three blades of 112 or 113 meters placing the total height with the blade fully extended at 150 meters (492 feet) or more. SunEdison will be using 47 Vestas’ V112-3.3 MW turbine for the project together with components previously ordered from Vestas. Reporting on the actual number and capacity of the turbines has varied due to First Wind changing turbine models but it appears that ten of the turbines will be Vestas V112-3.0 MW.


Source: http://www.windtaskforce.or...

AUG 31 2015
http://www.windaction.org/posts/43301-destruction-of-a-mountain-bingham-wind-site-work