logo
Article

Permitting appeals board staff recommends OK for Bingham wind power project

Bangor Daily News|Darren Fishell|February 25, 2015
MaineGeneral

The Board of Environmental Protection, an appointed citizen oversight panel, will consider the Bingham Wind permit appeal at a March 5 meeting and hear oral arguments before taking up a draft order that would uphold the permit for the 62-turbine wind farm.


PORTLAND, Maine — Staff of the state’s environmental permitting appeals board have recommended upholding a permit for a proposed western Maine wind farm that would be Maine’s largest wind power project to date.

The Board of Environmental Protection, an appointed citizen oversight panel, will consider the Bingham Wind permit appeal at a March 5 meeting and hear oral arguments before taking up a draft order that would uphold the permit for the 62-turbine wind farm.

The Maine Department of Environmental Protection gave a permit to the $398 million project in September. It is led by subsidiaries of the former First Wind, now part of solar energy giant SunEdison after a $2.4 billion sale that closed in January.

The anti-wind-power group …

... more [truncated due to possible copyright]

PORTLAND, Maine — Staff of the state’s environmental permitting appeals board have recommended upholding a permit for a proposed western Maine wind farm that would be Maine’s largest wind power project to date.

The Board of Environmental Protection, an appointed citizen oversight panel, will consider the Bingham Wind permit appeal at a March 5 meeting and hear oral arguments before taking up a draft order that would uphold the permit for the 62-turbine wind farm.

The Maine Department of Environmental Protection gave a permit to the $398 million project in September. It is led by subsidiaries of the former First Wind, now part of solar energy giant SunEdison after a $2.4 billion sale that closed in January.

The anti-wind-power group Friends of Maine Mountains filed an appeal of the project permits to the BEP in October, arguing in part that the company did not have adequate financing to provide for the project’s decommissioning.

BEP staff wrote in the draft order that the company was right in its estimates of those costs and that its plan meets the requirement that project decommissioning be fully funded before construction begins.

Rand Stowell, a member of the board of directors for Friends of Maine Mountains, said in a prepared statement that he was not surprised by the decision.

“Even though it is a rare occurrence, we hope that the BEP will overturn the decision,” Stowell said. “But if they won’t overturn it, at the very least we would like to see some stricter conditions placed on the permit.”

He said the group will argue that there should be tougher requirements for decommissioning turbines.

Since the group started its appeals, the structure and finances of the company changed substantially.

Last year, the company’s joint venture with power utility Emera was in jeopardy, bouncing between state utility regulators and the Maine Supreme Judicial Court amid a challenge from the smaller utility, Houlton Water Co. Houlton Water raised concerns about the investment of the parent company of utility Emera Maine in power generation projects in the state.

Utilities were required to get rid of their generation capacity through the restructuring of Maine’s electricity markets in 2000.

As part of buying First Wind, SunEdison also bought out Emera’s stake in the joint venture, effectively putting a halt to state regulators consideration of that case.

Some of the same questions have emerged in a separate case, however, involving a wind project by a sister company of Central Maine Power Co., near Fletcher Mountain in Somerset County.

The Bingham project would have turbines located on property in Bingham, Abbot, Parkman, Mayfield Township and Kingsbury Plantation. It has reached agreements to make for 20 years annual payments of $106,900 to Bingham, $20,000 to Moscow, Abbot and Parkman, and $176,000 to Kingsbury Plantation.

 


Source:http://bangordailynews.com/20…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2024 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION