IKEA/APEX wind farm non-payment causes liens filed against local farmers

Edgar County Watchdogs|June 23, 2015
IllinoisGeneral

IKEA (the furniture company) and APEX (a wind energy company) failed to make payments to Ambassador Steel Fabrication, LLS from Auburn, Indiana for work completed at the Hoopeston wind farm. The lien document pages can be accessed by clicking the links on this page.


VERMILION CO., IL. – IKEA (the furniture company) and APEX (a wind energy company) failed to make payments to Ambassador Steel Fabrication, LLS from Auburn, Indiana for work completed at the Hoopeston wind farm. The failure of IKEA and APEX to make their payments in a timely manner is now causing issues for farmers and other land owners who leased their properties for the project.

The list of names can be found on the documents recorded at the Vermilion County Recorder’s office in Document # 14-09577. This document is a “NOTICE OF SUBCONTRACTORS CLAIM and ILLINOIS MECHANIC’S LIEN CLAIM-LEASEHOLD IMPROVEMENT” For details, see the lien documents HERE and HERE.

The lien is for $1.4 million dollars.

Until IKEA/APEX settles this issue and …

... more [truncated due to possible copyright]

VERMILION CO., IL. – IKEA (the furniture company) and APEX (a wind energy company) failed to make payments to Ambassador Steel Fabrication, LLS from Auburn, Indiana for work completed at the Hoopeston wind farm. The failure of IKEA and APEX to make their payments in a timely manner is now causing issues for farmers and other land owners who leased their properties for the project.

The list of names can be found on the documents recorded at the Vermilion County Recorder’s office in Document # 14-09577. This document is a “NOTICE OF SUBCONTRACTORS CLAIM and ILLINOIS MECHANIC’S LIEN CLAIM-LEASEHOLD IMPROVEMENT” For details, see the lien documents HERE and HERE.

The lien is for $1.4 million dollars.

Until IKEA/APEX settles this issue and the lien is released, leaseholders may have difficulty completing real estate or financial transactions.

UPDATE: In late May 2015, 39 additional Mechanic’s Liens were issued against Hoopeston Wind LLC, in favor of NCSG Crane and Heavy Haul Service in the amount $2,444,703.76 for each of the 39 liens.

Attachments

Lien Documents

January 21, 2015


Source:http://edgarcountywatchdogs.c…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2024 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION