logo
Editorial

An Unending Production Tax Credit?

Lisa Linowes|August 20, 2014
USATaxes & Subsidies

Last month when GE's Chief Financial Officer, Jeff Bornstein, complained that rules defining 'begin construction' were still too vague and holding up delivery of 400 to 500 turbines. "We expect that clarification to come from the Treasury ...We’ve seen that clarification and we think it is helpful.”


Despite eking out a 1-year extension of the wind production tax credit (PTC) last year, only 836 MW of new wind was installed in the first six months of this year, the second lowest since 2008 (in 2013, a single two megawatt turbine was erected in Q1/Q2).

Yet surprisingly, with the PTC nominally expired, the industry is advertising 14,600+ MW of new wind under development, including 2,000 MWs added to the pipeline this year, after the PTC expired!

Why the slump? But more importantly, why is there new wind growth without the PTC?

IRS interpretation

In the final hours of the 112th Congress, amid fears of fiscal calamity, House Republicans were pressed to accept, without debate or amendment, Senate language that extended the wind PTC for 1-year[1]. The extension included a significant change. New renewable projects need only 'begin construction' by January 1, 2014, instead of being 'placed-in-service' by that date.

The law was silent on what it meant to 'begin construction', thus requiring the Internal Revenue Service (IRS) to issue guidance on Congress' intent.

For the most part, the IRS relied on rules developed by the Treasury to administer Section 1603 cash grants which also used the 'begin construction' phrase[2]. Applicants must begin 'physical work of a significant nature' or incur at least 5% of the project's capital cost (the safe harbor rule) by a specific date. No  hard deadline was set for placing projects in service but the IRS stated it would strictly scrutinize projects to ensure they maintained a continuous construction program, particularly for projects online after 2015[3].

Section 1603 grants fueled a wind bubble that more than doubled US wind capacity from 2009-12[4]. By contrast, big wind stalled in 2013-14 adding just 1920 MW in the 18 months ending June 2014.

A predictable slow-down

It's no surprise that wind development slowed to a crawl after 2012. Developers, racing to meet 1603 deadlines, flushed the industry's project pipeline. Most of 2013 was spent building the pipeline to an estimated 14,600 MW.

But important differences between the grant program and the production tax credit contributed to the slow-down.

Under the grant program, developers could submit applications to the Treasury detailing initial work completed and receive confirmation on whether they met the physical work test, or, for applicants relying on the 5% safe harbor, whether qualifying costs had been paid or incurred. After that, the Treasury had little discretion provided projects were in service by the legal deadline.

Tax credits, on the other hand, are granted only after annual tax returns are filed for the year in which the project is completed, which means a project must be producing electricity before PTC-eligibility can be confirmed. An IRS audit to validate eligibility may not happen until years after that. Banks and tax investors were unwilling to risk capital on projects that might be denied the PTC.

Going too far

The IRS issued two notices (here and here) in 2013 explaining how it would evaluate PTC eligibility. The industry appeared satisfied[5] until last month when GE's Chief Financial Officer, Jeff Bornstein, complained that rules defining 'begin construction' were still too vague and holding up delivery of 400 to 500 turbines.

"We expect that clarification to come from the Treasury in the next week or two," he said. "We’ve seen that clarification and we think it is helpful.”

And sure enough, GE got exactly what it wanted.

The IRS has delivered its third guidance document and it's troubling.

For example, for projects hoping to satisfy the physical work test, there is no threshold or minimum amount (or cost) of work required to satisfy the test. Work need only begin before January 1, 2014. Apparently, a single worker equipped with a hand shovel digging in the vicinity of a proposed wind turbine foundation is enough to pass the test. And if that one worker keeps at it for one year or ten, the IRS may find the project satisfies the continuous construction requirement.

Developers who begin construction of a facility in 2013, can choose to transfer equipment and other components to an entirely different site, complete construction and claim the PTC for the new site. Work performed or expenses paid/incurred prior to January 1, 2014 will be considered in determining whether the new project meets the begin construction tests. Under this interpretation, large wind developers can bank turbines for use nationwide prior to 2014 and allocate them by project in later years.

Finally, according to the guidance, if a developer incurs less than five percent of the total cost of a project at the time it is placed in service, as long as he pays or incurs at least three percent of the total cost before January 1, 2014, the safe harbor rule may be met and the PTC can be claimed for a portion of the project.

Conclusion

In reading the IRS' latest guidance, AWEA's claim of 14,600 MW of wind under development with 2000 MW of new wind added to the pipeline after the PTC expired is not far-fetched. The fact the GE reported on the IRS' latest guidance before it was released suggests the turbine giant had a hand in crafting the document, which raises other concerns.

The Senate's $85 billion tax extender package that adds one more year to the PTC is deadlocked over Harry Reid's refusal to allow amendments. Things might change in the lame duck, but animosity against the wind PTC runs high among House and some Senate Republicans. Given this latest tactic to drag out the PTC indefinitely, we hope Congress will take notice. Twenty-two years is long enough for the temporary PTC. It's time for it to end, once and for all.

__________________________________________
[1] American Taxpayer Relief Act of 2013 (ATRA 2013) also known as the Fiscal Cliff.
[2] The cash grant program required that eligible renewable energy projects begin construction in 2009, 2010, or 2011 and be placed in service by January 1, 2013.
[3] The IRS may determine construction has not begun on a facility before January 2014 if it cannot confirm continuous construction.
[4] Ninety-percent, or more, of the record 13,000+ MW installed in 2012, can be attributed to Section 1603, not the PTC.
[5] Hearing before the House Subcommittee on Energy Policy, Health Care and Entitlements.
 


Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2024 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION