Armow wind appeal dismissed

Blackburn News|Janice MacKay|Apr 23, 2014
OntarioLegal

The renewable energy approval puts the burden of proof on the appellants to prove serious harm to health from the project, and the tribunal found they did not prove it to a level of scientific certainty. That's despite testimony from several property owners who say they experience health problems.


The Armow Wind Farm in Kincardine has survived an Environmental Review Tribunal.

The Tribunal has dismissed an appeal from the Kroeplin family, who are members of Huron-Kinloss Against Lakeside Turbines.

The wind project will consist of 92 turbines.

The appeal claimed the project would cause serious harm to human health, and claimed the rights to the security of the person would be violated.

The renewable energy approval puts the burden of proof on the appellants to prove serious harm to health from the project, and the tribunal found they did not prove it to a level of scientific certainty.

That's despite testimony from several property owners who say they experience health problems when they are living near turbines, and the …

... more [truncated due to possible copyright]

The Armow Wind Farm in Kincardine has survived an Environmental Review Tribunal.

The Tribunal has dismissed an appeal from the Kroeplin family, who are members of Huron-Kinloss Against Lakeside Turbines.

The wind project will consist of 92 turbines.

The appeal claimed the project would cause serious harm to human health, and claimed the rights to the security of the person would be violated.

The renewable energy approval puts the burden of proof on the appellants to prove serious harm to health from the project, and the tribunal found they did not prove it to a level of scientific certainty.

That's despite testimony from several property owners who say they experience health problems when they are living near turbines, and the health issues disappear when they move out of their home.

An acoustical expert told the hearing the turbines would very likely exceed the ministry of environment’s own noise limits. He also pointed out several problems in the wind company’s calculations.


Source:http://blackburnnews.com/midw…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2026 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION