logo
Article

Bird discovery threatens closure of 50MW project

Windpower Monthly|Michael McGovern|Oct 16, 2013
EuropeImpact on Birds

A Spanish court has ruled null and void local authority permits granted to a 50MW wind plant, partly owned by Italian utility Enel, that has been in operation for three years. Avian group SEO Birdlife brought the case to court. It discovered the regional government of Castile and León had concealed official environmental reports highlighting the importance of a local bird species, the urogallo, in the vicinity of the Peña del Gato wind project.


SPAIN: A Spanish court has ruled null and void local authority permits granted to a 50MW wind plant, partly owned by Italian utility Enel, that has been in operation for three years.

Avian group SEO Birdlife brought the case to court. It discovered the regional government of Castile and León had concealed official environmental reports highlighting the importance of a local bird species, the urogallo, in the vicinity of the Peña del Gato wind project.

The plant is located in the Omaña and Cepeda districts, close to the world's southernmost population of the urogallo.

SEO Birdlife is considering whether to call for a precautionary closure of the Peña del Gato, pending the verdict of the developer's appeal, which can take several …

... more [truncated due to possible copyright]

SPAIN: A Spanish court has ruled null and void local authority permits granted to a 50MW wind plant, partly owned by Italian utility Enel, that has been in operation for three years.

Avian group SEO Birdlife brought the case to court. It discovered the regional government of Castile and León had concealed official environmental reports highlighting the importance of a local bird species, the urogallo, in the vicinity of the Peña del Gato wind project.

The plant is located in the Omaña and Cepeda districts, close to the world's southernmost population of the urogallo.

SEO Birdlife is considering whether to call for a precautionary closure of the Peña del Gato, pending the verdict of the developer's appeal, which can take several years.

The ruling is the second threatened closure of an operational wind plant in Spain. An appeal is still pending against a court ruling to dismantle 25 of 33 turbines at developer Acciona's 49.5MW Serra de Tallat plant in Catalonia.


Source:http://www.windpowermonthly.c…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2026 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION