Line will carry wind power

Wyomine Star-Tribune|Dustin Bleizeffer|June 22, 2008
WyomingGeneral

Electrical power producers are in line to build 850 megawatts of new electrical generation in Wyoming -- and most of it will be wind energy, according to the Wyoming Infrastructure Authority. ...Steve Waddington, executive director of the Wyoming Infrastructure Authority, said 12 different "bidders" successfully passed a financial credit check and are qualified to compete for transmission capacity on the proposed power line. "It's not exclusively wind developers that are qualified to bid, but it is predominantly so," Waddington said. "The project looks pretty promising."


Electrical power producers are in line to build 850 megawatts of new electrical generation in Wyoming -- and most of it will be wind energy, according to the Wyoming Infrastructure Authority.

One megawatt can power about 750 homes.

A monthlong open auction will begin at the end of the month for transmission space on the proposed Wyoming-Colorado Intertie, a 345-kilovolt power line that will deliver power from eastern Wyoming to the Colorado Front Range.

Steve Waddington, executive director of the Wyoming Infrastructure Authority, said 12 different "bidders" successfully passed a financial credit check and are qualified to compete for transmission capacity on the proposed power line.

"It's not exclusively wind developers that are …

... more [truncated due to possible copyright]

Electrical power producers are in line to build 850 megawatts of new electrical generation in Wyoming -- and most of it will be wind energy, according to the Wyoming Infrastructure Authority.

One megawatt can power about 750 homes.

A monthlong open auction will begin at the end of the month for transmission space on the proposed Wyoming-Colorado Intertie, a 345-kilovolt power line that will deliver power from eastern Wyoming to the Colorado Front Range.

Steve Waddington, executive director of the Wyoming Infrastructure Authority, said 12 different "bidders" successfully passed a financial credit check and are qualified to compete for transmission capacity on the proposed power line.

"It's not exclusively wind developers that are qualified to bid, but it is predominantly so," Waddington said. "The project looks pretty promising."

Feasibility, technical and corridor studies for the power line have been completed. The first phase of the project includes a 345-kilovolt line from north of the Laramie River Station coal-fired power plant at Wheatland to the Pawnee substation in Colorado. Additional 230-kilovolt segments may be strung to the Laramie River Station and Dave Johnston coal-fired power plants later, according to the Infrastructure Authority.

The project is expected to unleash a massive wind resource in Wyoming. By 2013, it could access up to 900 megawatts of class 6 and class 7 wind resources in the eastern part of the state for delivery to Colorado, where utilities are rushing to meet state-mandated deadlines for boosting renewable energy.

The Wyoming-Colorado Intertie project is a "development partnership" among the Wyoming Infrastructure Authority, TransElect and the Western Area Power Administration.

 


Source:http://www.casperstartribune.…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2024 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION