Windham Regional Commission's Report on the proposed Glebe Mountain Windplant to the Vermont Public Service Board

Approximately 125 people attended the hearing, 40 of whom spoke to the issue. Twenty-seven speakers identified themselves as opposed to the project, 13 in favor. One hundred eighty six written comments were received, 146 opposing the project and 40 supporting it.

February 21, 2006

James Volz, Chair
Vermont Public Service Board
112 State Street, Drawer 20
Montpelier, VT  05620-2701

Re: Glebe Mountain Wind Energy, LLC

Dear Chairman Volz,

In accordance with 30 VSA  §248(f), the Windham Regional Commission (WRC) has reviewed materials submitted on December 23, 2005 by Glebe Mountain Wind Energy, LLC regarding its proposed construction of a wind energy facility in the Towns of Londonderry and Windham. The WRC also conducted a public hearing in Londonderry, on January 26.

Attached is the WRC’s summary of its review and of comments received, and recommendations to the Board and to the petitioner.

Electronic copies do not include public comments received, which were many. The hard copies that are sent to the Board and to the parties listed below will include those comments.

Sincerely,


James P. Matteau
Executive Director


cc: Robert Charlebois, Catamount Energy
 Londonderry Selectboard
 Londonderry Planning Commission
 Windham Selectboard
 Windham Planning Commission

Wrc-glebe-hearing-report-final_thumb
Wrc Glebe Hearing Report Final

Download file (51 KB) pdf

FEB 21 2006
http://www.windaction.org/posts/1479-windham-regional-commission-s-report-on-the-proposed-glebe-mountain-windplant-to-the-vermont-public-service-board
back to top