Eversource reports another big financial hit from its foray into offshore wind

The Boston Globe|Jon Chesto |Jul 31, 2026
USAMassachusettsOffshore Wind

Eversource faced a significant financial setback, recording a $164 million charge due to construction delays in the Revolution Wind project, influenced by Trump administration's stop-work orders. Despite selling its stake in the project, Eversource remains liable for cost overruns, with future liabilities estimated at an additional $194 million. The project, nearing completion, is set to power 350,000 homes and has begun delivering energy to the New England grid.


The Trump administration’s battle against offshore wind is costing Eversource shareholders millions again: This time, the price tag totals $164 million.

The Boston-based utility company reported that figure on Thursday as a one-time charge against its latest earnings, a charge forced by delays in construction for the Revolution Wind energy project going up in federal waters southwest of Martha’s Vineyard.

In particular, Eversource points to two stop-work orders that the Trump administration imposed as part of its effort to curtail offshore wind energy development, one in August of last year and another in December.

Eversource sold its 50 percent stake in Revolution Wind nearly two years ago to an affiliate of private equity firm Global …

... more [truncated due to possible copyright]

The Trump administration’s battle against offshore wind is costing Eversource shareholders millions again: This time, the price tag totals $164 million.

The Boston-based utility company reported that figure on Thursday as a one-time charge against its latest earnings, a charge forced by delays in construction for the Revolution Wind energy project going up in federal waters southwest of Martha’s Vineyard.

In particular, Eversource points to two stop-work orders that the Trump administration imposed as part of its effort to curtail offshore wind energy development, one in August of last year and another in December.

Eversource sold its 50 percent stake in Revolution Wind nearly two years ago to an affiliate of private equity firm Global Infrastructure Partners, as part of its effort to completely exit the troubled offshore wind sector. However, the terms of the sale required Eversource and its former partner in Revolution Wind, Danish developer Ørsted, to share in any construction cost overruns.

The first post-sale bill became clear to Eversource shareholders last October, when the company recorded a $75 million charge against earnings, primarily because of the extra costs incurred with Revolution Wind. The August stop-work order was one of the factors. The actual overrun was much higher, but a tax benefit related to the sale of Eversource’s wind investments greatly mitigated it.

This time, the tax-related mitigation is much smaller. Eversource estimates its liability to GIP will go up by another $194 million over time, or $164 million after taxes.

In a conference call with analysts on Friday, Eversource chief executive Joe Nolan offered encouraging words about Revolution Wind’s progress. The end, he said, is in sight.

“We’re going to bring this in and I’m very, very proud of the work that was done,” Nolan said. “And obviously, we couldn’t control the shutdowns, but we just wanted to capture that and make sure that we are upfront about charges.”

The multibillion-dollar project should be done by the end of the year. Nolan said it’s 97 percent complete. “We’re on the 5-yard line to get over the goal,” he added.

A spokeswoman for Ørsted said Revolution started delivering energy to the New England grid in March, and has regularly ramped up its capacity since that date. The 704-megawatt project is expected to generate enough power with its 65 giant wind turbines for 350,000 homes when complete, with contracts to deliver power to Connecticut and Rhode Island. A similarly sized wind farm in the waters south of the Vineyard, the Vineyard Wind 1 project owned by CIP and Iberdrola, is essentially complete as well — though its costs also went up as a result of a federal stop-work order.

Nolan had good news to share on the earnings call about another project, a series of transmission upgrades in Maine and New Hampshire. Grid overseer ISO New England just announced that it favors a $2.2 billion proposal submitted by Eversource and Iberdrola’s Avangrid to build more power-line capacity in Northern New England, in large part to improve access to on-shore wind energy resources in Maine. (ISO New England is expected to make a final decision in September.)

Eversource’s $700 million portion of the power-line project will go up in properties or rights of way that the company owns in New Hampshire. While ratepayers will ultimately pay for these costs, ISO New England argues that the transmission upgrades will provide savings for residents and businesses that exceed the project costs.


Source:https://www.bostonglobe.com/2…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2026 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION