Vestas turbine blade breaks at Norwegian wind farm

reNEWS|Mar 18, 2025
NorwaySafetyStructural Failure

The wind farm in Osen and Flatanger was closed after a turbine blade partially fell to the ground, energy company Aneo said. ...“We sent a team out to carry out a visual inspection and it was clear that one blade has sustained a lot of damage and partially fallen to the ground.


Aneo closes 130MW Sormarkfjellet site after incident

A Vestas turbine blade has broken at the 130MW Sormarkfjellet wind farm in Norway.

The wind farm in Osen and Flatanger was closed after a turbine blade partially fell to the ground, energy company Aneo said.

An Aneo spokesperson said: “On Saturday afternoon a number of alarms went off in the control room.

“We sent a team out to carry out a visual inspection and it was clear that one blade has sustained a lot of damage and partially fallen to the ground.

“Because of the weather conditions we do not want to send out more employees to further investigate so we have closed the wind farm to the public and all employees.

“No turbines are operating at the moment and we will provide more …

... more [truncated due to possible copyright]

Aneo closes 130MW Sormarkfjellet site after incident

A Vestas turbine blade has broken at the 130MW Sormarkfjellet wind farm in Norway.

The wind farm in Osen and Flatanger was closed after a turbine blade partially fell to the ground, energy company Aneo said.

An Aneo spokesperson said: “On Saturday afternoon a number of alarms went off in the control room.

“We sent a team out to carry out a visual inspection and it was clear that one blade has sustained a lot of damage and partially fallen to the ground.

“Because of the weather conditions we do not want to send out more employees to further investigate so we have closed the wind farm to the public and all employees.

“No turbines are operating at the moment and we will provide more information when we have it.

“When the weather allows we will carry out further visual inspections using drones; we don’t have a timeline on when this will happen but it will hopefully be soon.”

Vestas has been approached for comment on the incident.

Back in late January, another turbine at the site was damaged in a storm. The Aneo spokesperson said that this turbine is still not operating and there is currently no timeline for carrying out repairs.

The wind farm is equipped with Vestas V117 turbines and started operations in 2021. It has an installed power of 130MW and yearly production of 440GWh.

This is the equivalent to the annual energy consumption of 29,300 households.


Source:https://www.renews.biz/99432/…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2026 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION