Ørsted books EUR 1.6 billion impairment from increased costs, Sunrise Wind delays in US

Offshore Wind Biz|Adnan Memija|Jan 21, 2025
New YorkTaxes & SubsidiesOffshore Wind

Ørsted has reported impairment losses of DKK 12.1 billion (approximately EUR 1.62 billion) for the fourth quarter of 2024, citing rising costs for its offshore wind business in the US, mostly related to the development of the 924 MW Sunrise Wind project off the coast of New York. The Danish offshore wind developer said that the financial strain was caused by several factors, including rising interest rates, a decline in the value of its seabed leases in the US, and increased costs associated with the construction of the Sunrise Wind offshore wind farm.


Ørsted has reported impairment losses of DKK 12.1 billion (approximately EUR 1.62 billion) for the fourth quarter of 2024, citing rising costs for its offshore wind business in the US, mostly related to the development of the 924 MW Sunrise Wind project off the coast of New York.

The Danish offshore wind developer said that the financial strain was caused by several factors, including rising interest rates, a decline in the value of its seabed leases in the US, and increased costs associated with the construction of the Sunrise Wind offshore wind farm.

“The Sunrise Wind project is progressing on a tight construction schedule and is navigating challenges related to supply chain and construction,” according to the developer.

The expected …

... more [truncated due to possible copyright]

Ørsted has reported impairment losses of DKK 12.1 billion (approximately EUR 1.62 billion) for the fourth quarter of 2024, citing rising costs for its offshore wind business in the US, mostly related to the development of the 924 MW Sunrise Wind project off the coast of New York.

The Danish offshore wind developer said that the financial strain was caused by several factors, including rising interest rates, a decline in the value of its seabed leases in the US, and increased costs associated with the construction of the Sunrise Wind offshore wind farm.

“The Sunrise Wind project is progressing on a tight construction schedule and is navigating challenges related to supply chain and construction,” according to the developer.

The expected commissioning of the project has been delayed into the second half of 2027. Ørsted said that the costs for the project have increased, especially related to the monopile foundations.

The delayed commissioning and higher expected project costs will lead to an impairment of DKK 4.3 billion in the fourth quarter of 2024.

In July 2024, Ørsted acquired Eversource’s stake in Sunrise Wind, New York’s new offshore wind farm, which is also in the construction phase as Revolution Wind, with offshore work scheduled to start this year.

“Our dedicated efforts to strengthen execution and navigate supply chain challenges will continue. We’re working diligently and in close collaboration with our suppliers to manage the remaining risks impacting the construction of Sunrise Wind. Delivering the project within the updated schedule and cost is an absolute top priority for Ørsted,” said Mads Nipper, Group President and CEO of Ørsted.

The charge from the decreased value of seabed leases off the coasts of New Jersey, Maryland, and Delaware will amount to DKK 3.5 billion.

Additionally, during the fourth quarter of 2024, the development of the long-dated US interest rates led to a 75-basis-point increase in the weighted average cost of capital, the company said. This increase adversely impacted the value-in-use for the US portfolio, primarily the offshore wind projects, leading to an impairment of DKK 4.3 billion, according to the Danish firm.

The cost hits put the operating profit for 2024 at DKK 24.8 billion, which the company says is in line with guidance.

“The impairments announced today, and especially the continued construction challenges, are very disappointing. We are, however, encouraged by the performance of our operations, and we’re confirming our full-year EBITDA guidance, supported by the increasing power production from our growing global fleet of renewable energy assets,” said Nipper.

“We remain committed to the US market in the long term with its potential for renewables to meet the growing electricity demand and create thousands of industrial jobs across the US.”

Regarding other news coming from the US, President Donald Trump recently issued an Executive Order pausing offshore wind leasing on the US Outer Continental Shelf (OCS) and mandating a review of the federal government’s leasing and permitting practices for wind projects. The Order also stops all relevant agencies from issuing approvals, either new or renewed, for both onshore and offshore wind projects until the review is completed.


Source:https://www.offshorewind.biz/…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2026 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION