This hurts us' | Enel suspends Colombia wind farm build as years of protests take toll
ReCharge News|Andrew Lee |May 25, 2023
Global renewables giant Enel has halted work indefinitely on a wind farm in Colombia after years of protests by indigenous people and said it may try to sell the project. Continual blockades organised by the Wayuu people and their supporters have since 2021 stymied Enel Colombia’s efforts to build the 205MW Windpeshi wind farm in La Guajira. Hopes rose just weeks ago of an agreement that would allow the project to continue, but Enel Green Power Colombia and Central America manager Eugenio Calderón said on Wednesday that work has stopped.
Global renewables giant Enel has halted work indefinitely on a wind farm in Colombia after years of protests by indigenous people and said it may try to sell the project. Continual blockades organised by the Wayuu people and their supporters have since 2021 stymied Enel Colombia’s efforts to build the 205MW Windpeshi wind farm in La Guajira. Hopes rose just weeks ago of an agreement that would allow the project to continue, but Enel Green Power Colombia and Central America manager Eugenio Calderón said on Wednesday that work has stopped.
Global renewables giant says half of working days lost at Windpeshi project in La Guajira
Global renewables giant Enel has halted work indefinitely on a wind farm in Colombia after years of protests by indigenous people and said it may try to sell the project.
Continual blockades organised by the Wayuu people and their supporters have since 2021 stymied Enel Colombia’s efforts to build the 205MW Windpeshi wind farm in La Guajira.
Hopes rose just weeks ago of an agreement that would allow the project to continue, but Enel Green Power Colombia and Central America manager Eugenio Calderón said on Wednesday that work has stopped.
“This decision, which not only hurts us as a company, but as citizens who are committed to the energy transition …
... more [truncated due to possible copyright]Global renewables giant says half of working days lost at Windpeshi project in La Guajira
Global renewables giant Enel has halted work indefinitely on a wind farm in Colombia after years of protests by indigenous people and said it may try to sell the project.
Continual blockades organised by the Wayuu people and their supporters have since 2021 stymied Enel Colombia’s efforts to build the 205MW Windpeshi wind farm in La Guajira.
Hopes rose just weeks ago of an agreement that would allow the project to continue, but Enel Green Power Colombia and Central America manager Eugenio Calderón said on Wednesday that work has stopped.
“This decision, which not only hurts us as a company, but as citizens who are committed to the energy transition with great enthusiasm and responsibility, was made after carrying out rigorous analysis and feasibility studies, which concluded that it is not possible for the company to continue with the construction of Windpeshi," Calderón said.
"Projects have to be sustainable not only from a social point of view but also from an economic point of view, and their success depends on joint work between companies, institutions and communities. We will continue to engage with communities and stakeholders to address the implications of this decision."
Italy-based Enel, one of the world's largest wind and solar operators, said protests stopped work at Windpeshi on almost 50% of working days in 2021 and 2022, and the stoppages had risen to 60% in 2023. The company will now “examine project sale options”.
As the global renewables build-out gathers pace, wind and solar plants are more often becoming the target of protests over their impact on indigenous communities and the environment.
Norway earlier this year saw high-profile demonstrations over the effect of large-scale wind power on native reindeer herders, with global climate icon Greta Thunberg famously joining protestors.