Wind farm opponents lose Wyoming Supreme Court appeal

Casper Star-Tribune| Nicole Pollack |Apr 19, 2023
WyomingLegalZoning/Planning

The decision upheld an earlier district court loss for a pair of lawsuits representing almost 50 local landowners opposed to the roughly 500-megawatt Rail Tie Wind Project. Each was filed shortly after county lawmakers granted the permit. Both challenges argued that the permitting process was incomplete and that county commissioners erred by still approving a special-use permit for the project.


Albany County’s board of commissioners was justified in authorizing a 120-turbine wind farm to proceed during the summer of 2021, the Wyoming Supreme Court ruled Monday.

The decision upheld an earlier district court loss for a pair of lawsuits representing almost 50 local landowners opposed to the roughly 500-megawatt Rail Tie Wind Project. Each was filed shortly after county lawmakers granted the permit.

Both challenges argued that the permitting process was incomplete and that county commissioners erred by still approving a special-use permit for the project.

The Wyoming Supreme Court — like the district court — found that the commissioners fulfilled everything the law required of them. It said in Monday’s ruling that the permit …

... more [truncated due to possible copyright]

Albany County’s board of commissioners was justified in authorizing a 120-turbine wind farm to proceed during the summer of 2021, the Wyoming Supreme Court ruled Monday.

The decision upheld an earlier district court loss for a pair of lawsuits representing almost 50 local landowners opposed to the roughly 500-megawatt Rail Tie Wind Project. Each was filed shortly after county lawmakers granted the permit.

Both challenges argued that the permitting process was incomplete and that county commissioners erred by still approving a special-use permit for the project.

The Wyoming Supreme Court — like the district court — found that the commissioners fulfilled everything the law required of them. It said in Monday’s ruling that the permit approval “was not arbitrary and capricious and was not a taking of private property.”

Pete Gosar, an Albany County commissioner, said the verdict came as a relief. “You try to follow your processes as best you can, and you hope you have it,” he said. Wyoming’s highest court affirmed that the commission did.


Source:https://trib.com/business/ene…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2026 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION