OPSB calls for comments on proposed rules, denies Defiance County solar project

Ohio Power Siting Board|January 19, 2023
OhioZoning/PlanningPhotovoltaic Solar

The OPSB denied the application filed by Cepheus Energy Project, LLC to construct a 68 megawatt (MW) solar-powered electric generating facility in Delaware Township and Sherwood Village, Defiance County. The OPSB found that, based on the unanimous opposition to the project by local governments whose constituents are impacted by the project, the proposed project would fail to serve the “public interest, convenience, and necessity” as required by Ohio law.


The Ohio Power Siting Board (OPSB) today issued draft modifications to its rules for public comment. The OPSB requests that interested persons submit comments by Jan. 30, 2023 and submit reply comments by Feb. 6, 2023.
OPSB HOME

COLUMBUS, OHIO – The Ohio Power Siting Board (OPSB) today issued draft modifications to its rules for public comment. The OPSB requests that interested persons submit comments by Jan. 30, 2023 and submit reply comments by Feb. 6, 2023.

Specifically, the OPSB staff recommends changes to certain definitions in Ohio Administrative Code 4906-1- 01, the site/route information that is required of applicants in Ohio Administrative Code 4906‑3-05, and the facility setback requirements in Ohio Administrative Code 4906-4-09.

I…

... more [truncated due to possible copyright]

The Ohio Power Siting Board (OPSB) today issued draft modifications to its rules for public comment. The OPSB requests that interested persons submit comments by Jan. 30, 2023 and submit reply comments by Feb. 6, 2023.
OPSB HOME

COLUMBUS, OHIO – The Ohio Power Siting Board (OPSB) today issued draft modifications to its rules for public comment. The OPSB requests that interested persons submit comments by Jan. 30, 2023 and submit reply comments by Feb. 6, 2023.

Specifically, the OPSB staff recommends changes to certain definitions in Ohio Administrative Code 4906-1- 01, the site/route information that is required of applicants in Ohio Administrative Code 4906‑3-05, and the facility setback requirements in Ohio Administrative Code 4906-4-09.

In separate business, the OPSB denied the application filed by Cepheus Energy Project, LLC to construct a 68 megawatt (MW) solar-powered electric generating facility in Delaware Township and Sherwood Village, Defiance County. The OPSB found that, based on the unanimous opposition to the project by local governments whose constituents are impacted by the project, the proposed project would fail to serve the “public interest, convenience, and necessity” as required by Ohio law. The OPSB noted that all three local governments in the Cepheus Energy Project area – the Village of Sherwood, the Defiance County Board of Commissioners, and the Delaware Township Trustees – opposed the project and that the public comments filed in the case, which largely disfavor the project, reinforce the local government opposition.

Additional information about today’s OPSB decisions is available at www.OPSB.ohio.gov. Copies of today’s orders and entries will be available in case numbers 21-0293-EL-BGN (Cepheus Solar) and 21‑0902‑GE-BRO (OPSB rulemaking). A recorded webcast of today’s OPSB meeting is available on the Public Utilities Commission of Ohio’s YouTube channel at www.youtube.com/user/PUCOhio.


Source:https://opsb.ohio.gov/news/op…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2023 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION