Wind farm switch-offs cost bill-payers £1bn over the past five years

The Herald on Sunday|Martin Williams|October 4, 2022
United Kingdom (UK)Energy PolicyTransmission
Payments to energy firms to switch off mainly Scottish wind farm turbines because they produce too much power have cost bill-payers approaching £1bn in just over five years and are expected to soar to £500m a year. ...According to an analysis seen by the Herald on Sunday by National Grid ESO, the company responsible for keeping the lights on, all UK constraint costs including gas, wind and coal generation are predicted to grow from around £1bn to an "eyewatering" £2.3bn by 2026.

Staggering levels of compensation handed to energy firms when they have to reduce their output are set to rise
 
Payments to energy firms to switch off wind farms because they produce too much power have cost energy consumers a total approaching £1 billion in just over five years – and are expected to soar to nearly £500 million a year.
 
It has emerged that households which are seeing a doubling of energy bills since last winter are set to face further pain by the “absurd” constraint payments system which is predicted to dole out record amounts in the next four years.
 
According to an analysis seen by The Herald on Sunday by National Grid ESO, the company responsible for keeping the lights on, all UK constraint costs including gas, wind and coal generation are predicted to grow from around £1bn to an “eyewatering” £2.3bn by 2026.
 
It means that wind-farm compensation payments could reach as much as £500m in a year before energy infrastructure improvements bring the costs down.
 
Because electricity cannot be stored and needs to be generated at the time of demand, compensation is given to ... more [truncated due to possible copyright]
     
Staggering levels of compensation handed to energy firms when they have to reduce their output are set to rise
 
Payments to energy firms to switch off wind farms because they produce too much power have cost energy consumers a total approaching £1 billion in just over five years – and are expected to soar to nearly £500 million a year.
 
It has emerged that households which are seeing a doubling of energy bills since last winter are set to face further pain by the “absurd” constraint payments system which is predicted to dole out record amounts in the next four years.
 
According to an analysis seen by The Herald on Sunday by National Grid ESO, the company responsible for keeping the lights on, all UK constraint costs including gas, wind and coal generation are predicted to grow from around £1bn to an “eyewatering” £2.3bn by 2026.
 
It means that wind-farm compensation payments could reach as much as £500m in a year before energy infrastructure improvements bring the costs down.
 
Because electricity cannot be stored and needs to be generated at the time of demand, compensation is given to energy firms when they have to reduce their output.
 
With wind farms it involves turning off turbines when the network is unable to cope with the power they produce.
 
The payments are made by National Grid ESO but charged to consumers and added to energy bills. The payments over wind power in Scotland, which kicked in during 2010, come when what it generates cannot be exported to England due to insufficient grid infrastructure or if there isn’t the demand.
 
Official National Grid data examined by The Herald shows that wind compensation payments have reached at least £900m since 2017.
 
The payments have risen to £395m in the last two years – £126m more that in the two-year period from 2017. In 2012, and 2013, it is estimated constraint costs were at just £19m.
 
Industry insiders say the cost of the inability to capitalise on wind will be even higher because of a “absolutely preposterous double whammy” where further payments have to be made to energy firms to use gas generators in the south to meet demand for energy when wind turbines in Scotland are switched off.
 
Last year, the Scottish Government said that Scotland is home to 60 per cent of the UK’s offshore wind capacity and 25% of Europe’s wind resource. It is estimated that Scotland is home to just over half of the wind power generation in the UK.
 
Payments are made by National Grid – but charged to consumers
 
Storage facilities
 
There is criticism that the Government is not doing enough to solve the problem by adequately funding a solution to the switch-offs – involving the creation of energy storage technologies.
 
The UK Government has provided an initial £6.7m to 24 projects across the UK to “turbocharge” the development of the storage technology with the aim of “reducing the cost of meeting net zero”. A further £61m will then be awarded to several of the most promising projects – which means many will fall by the wayside.
 
It is estimated that 80% of UK wind energy curtailment in 2020 was on Scottish farms and the soaring compensation payments come despite wind power in Scotland flagging in 2021.
 
A Department for Business, Energy and Industrial Strategy analysis showed renewable power generation for April to June 2021 alone fell 9.6% on the same period the previous year driven by a 14% drop in wind generation because of lower average gusts, which were substantially below the 10-year averages.
 
That resulted in a 36% rise in fossil fuel power generation over the same period to meet increased demand.
 
It has emerged constraint payments including wind are forecast to rise from around £1bn in 2021 to £2.5bn per year by the mid-2020s, according to National Grid, which is also predicting they will reduce once investment in new technology comes online.
 
Yesterday, energy bills soared for around 1.5 million Scottish households after the Government put a freeze on the regulator Ofgem’s price cap on average dual-fuel energy bills.
 
It stepped in after an 80% increase in domestic gas and electricity bills was earmarked for the first half of winter. A typical annual bill will go up from £1,971 to £2,500 but will be further mitigated by cost-of-living payments.
 
But prices will still be twice as high as last winter, and charities have said that will leave many struggling.
 
‘Absurdity’
 
Fair energy prices campaigner Kenny MacAskill, the MP for East Lothian and Alba Party deputy leader who has conducted his own analysis of the constraint payments, described the huge burden to the taxpayer as the “great energy switch-off absurdity”.
 
He said: “At a time when Scots are struggling to meet their energy bills, renewable energy in Scotland is being switched off. Perversely, energy suppliers are paid more for that than for producing energy. As offshore wind comes on stream, the great energy switch-off will only increase. The cost to the public purse will soon become billions.”
 
He said the solution was to store the energy, not switch it off using long duration energy storage (LDES)
 
But he added: “The BEIS has failed to support such schemes. The modest sums required to develop this technology are dwarfed by the costs of curtailment.
 
“There are a range of schemes including in East Lothian that are good to go, for example proposals to develop longerduration energy storage that require
 
At a time when Scots are struggling to meet their energy bills, renewable energy is being switched off. Perversely, suppliers are paid more for that than for producing energy
 
Government investment so that we can develop prototype technology and then scale up from that. Other sites in Scotland, such as Cockenzie and Torness, are ideally placed to take advantage of these opportunities and should be prioritised.
 
“It is time for both the UK and Scottish governments to step up and provide the action and the investment that is needed to make Scotland Europe’s renewable energy powerhouse.”
 
Nick Kitchin, chief executive of Cumulus Energy Storage which is developing the storage and is hoping to introduce manufacturing to Scotland, said the new technology was crucial as Scotland has 25% of Europe’s offshore wind and around 60% of the UK’s onshore wind capacity. “Energy storage, provided means wind farms can continue to generate electricity and receive ROCs [Renewable Energy Certificates] for this production that would otherwise be curtailed.”
 
He felt the UK Government should put more money into projects, saying a lot of them will fall by the wayside in its current schemes.
 
“There is a big opportunity to increase the budget to, say £250m. Instead of six projects, they could have all 24. You could have gigafactories for batteries as they have for electric vehicles.”
 
He said there was a “huge opportunity” for Scotland in manufacturing storage creating hundreds of jobs. “The solution is there, it just needs more money to commercialise it,” he said. “The modest sums required to develop this technology are dwarfed by the costs of curtailment.”
 
Limited capacity
 
Another energy storage firm executive said: “There are going to be casualties with the BEIS projects. There is just not enough support and they are killing opportunities.”
 
Experts say there is a particular issue in Scotland which has large amounts of wind power but limited capacity to export this through interconnectors to England and Wales.
 
This “bottleneck” means that when large amounts of wind power are being generated in Scotland, and demand is relatively low, there is limited scope to export this.
 
A high-voltage submarine power cable between Scotland and England was supposed to help to cut the figure by allowing energy to be exported south of the Border and keeping the turbines on more regularly.
 
But there have been issues. In January 2020, Italian telecom systems firm Prysmian, which manufactured cables for the £1.2bn Western Link project, said that it had failed. It came back into operation on February 7 but it was the third failure in three years.
 
After the outage on the Western Link, which connects Scottish wind farms via Hunterston to England and Wales, the energy regulator Ofgem launched an investigation into National Grid and Glasgow-based ScottishPower, part of the Iberdrola group, over the subsea power cable’s delivery and operation.
 
The joint project, which was billed at the time as the world’s largest subsea interconnecting power cable, was originally due to be completed in late 2015 but electricity did not start flowing through until December 2017. It started at less than full capacity in 2017 after problems during construction. The line has suffered six faults since then, taking it out of action for months at a time.
 
£158m penalty
 
Last year, National Grid and Scottish Power Transmission agreed to pay a £158m penalty package after a two-year the delay. The delays meant it was difficult for renewable energy generators in Scotland to export green electricity to England and Wales from wind farms and led to higher costs to households as alternative sources of energy were used to plug the gap, according to Ofgem.
 
Ofgem said £15m of the fine was to be paid into its redress fund for vulnerable energy customers, which is run by the Energy Saving Trust.
 
The remainder was to go towards reducing system charges, which was due to be passed on to consumers through lower electricity bills.
 
The Western Link runs from Ayrshire to north Wales via a 239-mile subsea route to the Wirral peninsula and a 20-mile stretch underground.
 
It is designed to carry 2.2 gigawatts of electricity, enough to power four million homes. Prysmian Group handed the project to National Grid and ScottishPower late last year and has booked €165 million in provisions for repair costs and “contractual penalties”.

Content truncated due to possible copyright. Use source link for full article.


Source:https://www.heraldscotland.co…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2022 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION