Vestas focuses on bolting in 3MW turbine collapse probe

Recharge News|Andrew Lee|Jan 6, 2016
SwedenSafetyStructural Failure
Today it said preliminary findings suggest “that the turbine collapse was caused by a failure in the bolted flange between tower sections one and two”. Examination by an external metallurgical laboratory does not indicate a bolt quality issue, said Vestas, and “the ongoing investigation is focused on the bolt pre-tensioning procedure”.

Vestas says a failure of bolting between tower sections is the likely cause of the collapse of one of its 3MW turbines in Sweden.
 
The wind OEM has been investigating since the V112-3.0 MW came down on Christmas Eve at the Lemnhult Wind Farm operated by Stena Renewable – the first such incident involving a Vestas MW-class machine.
 
Today it said preliminary findings suggest “that the turbine collapse was caused by a failure in the bolted flange between tower sections one and two”.
 
Examination by an external metallurgical laboratory does not indicate a bolt quality issue, said Vestas, and “the ongoing investigation is focused on the bolt pre-tensioning procedure”.
 
No one was injured in the collapse, which saw the other 31 turbines at …
... more [truncated due to possible copyright]
Vestas says a failure of bolting between tower sections is the likely cause of the collapse of one of its 3MW turbines in Sweden.
 
The wind OEM has been investigating since the V112-3.0 MW came down on Christmas Eve at the Lemnhult Wind Farm operated by Stena Renewable – the first such incident involving a Vestas MW-class machine.
 
Today it said preliminary findings suggest “that the turbine collapse was caused by a failure in the bolted flange between tower sections one and two”.
 
Examination by an external metallurgical laboratory does not indicate a bolt quality issue, said Vestas, and “the ongoing investigation is focused on the bolt pre-tensioning procedure”.
 
No one was injured in the collapse, which saw the other 31 turbines at Lemnhult taken out of service as a precaution.
 
The Danish manufacturer said: “Vestas has installed more than 55,000 turbines globally, and incidents involving turbines’ structural integrity are very rare.
 
“We have not experienced a MW-class turbine collapsing before. We will provide additional information when it becomes available.”

Source:https://www.rechargenews.com/…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2026 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION