Under protest, County council approves rezoning bylaws for two Buffalo Plains wind farm turbine locations

Vulcan Advocate|Stephen Tipper|Jul 15, 2022
AlbertaZoning/Planning

Under protest, Vulcan County council approved rezoning land near two wind turbine sites for ABO Wind’s Buffalo Plains 500-megawatt wind farm near Lomond.


Under protest, Vulcan County council approved rezoning land near two wind turbine sites for ABO Wind’s Buffalo Plains 500-megawatt wind farm near Lomond.
 
Reeve Jason Schneider and Couns. Laurie Lyckman, Shane Cockwill and Kelly Nelson each voted in favour, under protest, on the second and third readings of two bylaws, which each rezoned land to rural general from urban fringe. Coun. Christopher Northcott voted against both readings of the two bylaws.
 
Both turbine locations are in Vulcan County’s urban fringe with Lomond. The overall height of each of the wind farm’s 83 turbines will be about 200 metres, with a hub height of 115 metres and, rotor diameter of 170 metres.
 
County council had to approve the rezoning applications …
... more [truncated due to possible copyright]
Under protest, Vulcan County council approved rezoning land near two wind turbine sites for ABO Wind’s Buffalo Plains 500-megawatt wind farm near Lomond.
 
Reeve Jason Schneider and Couns. Laurie Lyckman, Shane Cockwill and Kelly Nelson each voted in favour, under protest, on the second and third readings of two bylaws, which each rezoned land to rural general from urban fringe. Coun. Christopher Northcott voted against both readings of the two bylaws.
 
Both turbine locations are in Vulcan County’s urban fringe with Lomond. The overall height of each of the wind farm’s 83 turbines will be about 200 metres, with a hub height of 115 metres and, rotor diameter of 170 metres.
 
County council had to approve the rezoning applications following a February decision by a provincial body, the Alberta Utilities Commission, to approve the entire wind farm project, including the turbine land locations before council July 13.
 
Last September, Vulcan County’s Municipal Planning Commission (MPC) had already approved almost all the turbine locations, with a separate development permit issued  for each turbine in the project.
 
On June 15, County council carried all three readings of a rezoning bylaw for one turbine location, roughly 1.6 kilometres from McGregor Reservoir, as well as carrying first reading of the other two rezoning bylaws and scheduling a public hearing on the two other rezoning bylaws.
 
With the three turbine locations rezoned, development permit applications for each turbine can now be submitted to Vulcan County’s MPC.
 

Source:https://www.vulcanadvocate.co…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2026 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION