‘Limited damage’ after ship hits foundations of Vattenfall’s Hollandse Kust Zuid wind farm

Windpower Monthly|Craig Richard|Mar 24, 2022
NetherlandsOffshore WindSafety

Damage to an offshore wind farm substation jacket was “limited” after a cargo ship crashed into it in January, according to transmission system operator (TSO) Tennet. The TSO added that the substation jacket at Vattenfall’s 1500MW Hollandse Kust Zuid wind farm in the Dutch North Sea suffered paint damage, a few dents on one of the legs of the platform and damage to one of the four landing platforms for working vessels.


Transmission system operator confirms topside installation can go ahead following an investigation

Damage to an offshore wind farm substation jacket was “limited” after a cargo ship crashed into it in January, according to transmission system operator (TSO) Tennet.

The TSO added that the substation jacket at Vattenfall’s 1500MW Hollandse Kust Zuid wind farm in the Dutch North Sea suffered paint damage (see below), a few dents on one of the legs of the platform and damage to one of the four landing platforms for working vessels.

A rudderless cargo ship became untethered and floated into the wind farm on 31 January, crashing into the substation jacket and a turbine foundation. 

Tennet was unable to carry out the investigation into both the …

... more [truncated due to possible copyright]

Transmission system operator confirms topside installation can go ahead following an investigation

Damage to an offshore wind farm substation jacket was “limited” after a cargo ship crashed into it in January, according to transmission system operator (TSO) Tennet.

The TSO added that the substation jacket at Vattenfall’s 1500MW Hollandse Kust Zuid wind farm in the Dutch North Sea suffered paint damage (see below), a few dents on one of the legs of the platform and damage to one of the four landing platforms for working vessels.

A rudderless cargo ship became untethered and floated into the wind farm on 31 January, crashing into the substation jacket and a turbine foundation. 

Tennet was unable to carry out the investigation into both the damage visible above the water and to the substation’s substructure immediately due to persistent stormy weather in February.

It has now carried out its investigation and believes installation of the second offshore transformer platform – needed for the grid connection to the wind farm – can go ahead as planned. Tennet expects the topside to be installed at the end of March or early April.

It added that the damaged jacket can be replaced at a later stage after the topside installation.

Joris Engelen, Tennet's platform project lead: "When designing and building our jackets, scenarios are taken into account that a ship of limited size may collide with the jacket. 

“After the initial fright of the collision, we set up and implemented an extensive investigation plan in cooperation with the parties involved. 

“The jacket is expected to be in operation for many years. We are therefore relieved that the inspections and the investigations show that we can install the top side of the transformer platform on the jacket safely and as scheduled.”


Source:https://www.windpowermonthly.…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2026 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION