TransAlta finds cracked foundations at N.B. wind farm where tower collapsed

The Canadian Press|Oct 29, 2021
New BrunswickSafetyStructural Failure

TransAlta Renewables Inc. says it has found cracks in several foundations of the turbines at a wind farm in New Brunswick where a tower collapsed in September. The company says the discovery of the subsurface cracks means the foundations will likely need repairs, and if replacement is required, costs are estimated at $1.5 million to $2 million per foundation.


Facility southwest of Moncton has more than 50 wind turbines 

TransAlta Renewables Inc. says it has found cracks in several foundations of the turbines at a wind farm in New Brunswick where a tower collapsed in September.

The company says the discovery of the subsurface cracks means the foundations will likely need repairs, and if replacement is required, costs are estimated at $1.5 million to $2 million per foundation.

TransAlta Renewables suspended operations and began an investigation after a tower collapsed earlier this month at its Kent Hill wind farm, 55 kilometres southwest of Moncton, near Prosser Brook.

The suspended operation includes 50 wind turbines at Kent Hills 1 and Kent Hills 2, where the tower collapsed. Five turbines at …

... more [truncated due to possible copyright]

Facility southwest of Moncton has more than 50 wind turbines 

TransAlta Renewables Inc. says it has found cracks in several foundations of the turbines at a wind farm in New Brunswick where a tower collapsed in September.

The company says the discovery of the subsurface cracks means the foundations will likely need repairs, and if replacement is required, costs are estimated at $1.5 million to $2 million per foundation.

TransAlta Renewables suspended operations and began an investigation after a tower collapsed earlier this month at its Kent Hill wind farm, 55 kilometres southwest of Moncton, near Prosser Brook.

The suspended operation includes 50 wind turbines at Kent Hills 1 and Kent Hills 2, where the tower collapsed. Five turbines at Kent Hills 3 continue to operate.

The company says the foundation issues at the Kent Hills 1 and 2 sites are unique to the design of those sites, and there is no indication of any foundation issues at the Kent Hills 3 site or the company's other locations.

It estimates the outage will result in the loss of $3.7 million per month in potential earnings for as long as all 50 turbines are offline, based on average historical wind production.


Source:https://www.cbc.ca/news/canad…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2026 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION