Maine regulators nix CMP land deal for wind farm

Bangor Daily News|Darren Fishell|July 29, 2015
MaineEnergy Policy

Utilities regulators turned down Central Maine Power Co.’s request to negotiate a land purchase for an affiliated wind power developer, arguing such an arrangement could open the possibility of improperly favorable treatment.


PORTLAND, Maine — Utilities regulators turned down Central Maine Power Co.’s request to negotiate a land purchase for an affiliated wind power developer, arguing such an arrangement could open the possibility of improperly favorable treatment.

Tuesday’s unanimous decision of the three-person Maine Public Utilities Commission came before the panel allowed a financial relationship between Nova Scotia utility Emera and the generation company Algonquin Power & Utilities Corp. to continue pending a challenge in Maine’s top court.

The commission’s decision in the CMP case falls in line with the recommendation of its staff, who argued earlier this month that Atlantic Wind should find someone other than CMP to acquire the right-of-way it will need for its West Range Wind project, previously Fletcher Wind, in Somerset County.

“Atlantic Wind can hire the same subcontractors that CMP would have hired,” commission chairman Mark Vannoy said Wednesday.

The case narrowly addressed that transaction as the Maine Supreme Judicial Court is set to address the standards that regulators should use to determine whether financial relationships between regulated utilities and power generators stand to violate state law separating the two.

That law created competitive markets for power suppliers, with the idea that competition would reduce electricity prices in the region.

The PUC in May decided to postpone its investigation of the relationship between CMP and Atlantic Wind, both subsidiaries of Spanish power company Iberdrola, as it awaits a ruling from the court on related issues.

That ruling will come in response to municipal utility Houlton Water Co.’s second challenge to PUC decisions that allowed Emera, the parent company of utility Emera Maine, to invest in Algonquin Power and the wind power company First Wind.

Amid those legal challenges, Emera unwound its $333 million partnership with First Wind as part of First Wind’s sale to solar energy giant SunEdison. But Emera retained its interests in Algonquin, which has power generation assets that are connected to the northern Maine transmission system of Maine Public Service. Algonquin also has an energy services subsidiary that sells power into the regional ISO New England grid.

The high court’s decision could affect the ability or rules for Atlantic Wind or any companies affiliated with either Emera or CMP to develop power generation projects in the state.

The West Range Wind project would be Atlantic Wind’s first planned project in the state, although it also has leased thousands of acres in Washington County.


Source:https://bangordailynews.com/2…

Share this post
Follow Us
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2022 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION