Northeast Utilities plans additional transmission to meet capacity needs

Platts|Lisa Wood|Nov 1, 2013
ConnecticutMaineMassachusettsNew HampshireRhode IslandVermontTransmission

"We think that it is likely there will be significant additional transmission investment needed to maintain reliability and improve access to these clean, intermittent power sources," Lee Olivier, executive vice president and chief operating officer, said in an earnings call Friday. "But it is too early to estimate how much that additional investment will be and exactly when it will occur."


Northeast Utilities expects to build additional transmission to fill capacity needs created by retiring coal-fired and nuclear plants in New England, the utility said Friday.

NU, the region's largest utility, already has a $4 billion pipeline of transmission projects planned through 2017. The utility foresees the need for more transmission in the six-state region to make up for capacity shortfalls and to accommodate new wind power installations.

"We think that it is likely there will be significant additional transmission investment needed to maintain reliability and improve access to these clean, intermittent power sources," Lee Olivier, executive vice president and chief operating officer, said in an earnings call Friday. "But it …

... more [truncated due to possible copyright]

Northeast Utilities expects to build additional transmission to fill capacity needs created by retiring coal-fired and nuclear plants in New England, the utility said Friday.

NU, the region's largest utility, already has a $4 billion pipeline of transmission projects planned through 2017. The utility foresees the need for more transmission in the six-state region to make up for capacity shortfalls and to accommodate new wind power installations.

"We think that it is likely there will be significant additional transmission investment needed to maintain reliability and improve access to these clean, intermittent power sources," Lee Olivier, executive vice president and chief operating officer, said in an earnings call Friday. "But it is too early to estimate how much that additional investment will be and exactly when it will occur."

Recent announcements amount to 2,700 MW of retiring generation, about 10% of the region's peak capacity, he said. These include the planned 2017 retirement of the 1,497-MW Brayton Point and the 2014 closing of the 604-MW Vermont Yankee. Olivier also factored in 500 MW of demand response that was withdrawn from the next ISO New England capacity auction.

In all, the utility has identified up to 8,000 MW of New England plants that may shut down.

Wind power built in Maine also contributes to the need for transmission, according to Olivier, since the power must be moved south to Connecticut and Boston, the region's load centers.

"So you're looking at two issues," he said. "One, you're looking at a capacity shortfall in the 2018 time frame. Second, you're looking at more transmission to get renewable energy to the marketplace."

One of the utility's largest and most controversial transmission projects, the 1,200-MW Northern Pass, continues to move forward. A draft environmental impact statement is expected from the US Department of Energy next summer


Source:http://www.platts.com/latest-…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2026 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION