Sources: Vineyard Wind Decision Delayed Until December 2020

Final approval for the Vineyard Wind Project will likely not happen for at least another 18 months, according to information received from multiple sources by The Public’s Radio. This means the country’s first large scale offshore wind farm won’t begin construction in time to take advantage of a lucrative federal tax credit that expires at the end of the year. 
19 Aug 2019

Sources: Vineyard Wind Decision Delayed Until December 2020

Final approval for the Vineyard Wind Project will likely not happen for at least another 18 months, according to information received from multiple sources by The Public’s Radio. This means the country’s first large scale offshore wind farm won’t begin construction in time to take advantage of a lucrative federal tax credit that expires at the end of the year. 
19 Aug 2019

Report and recommendations for minimizing and mitigating environmental and commercial impacts of offshore wind facilities

Report_of_the_commission_on_environmental_standards_-_final_thumb The attached report by the Connecticut Commission on Environmental Standards provides recommendations to offshore wind developers in mitigating potential risks to the area's wildlife, fishing industry, and water navigation systems. The Commission urges developers to conduct assessments on potential impact areas and provide funding to offset economic and environmental losses.
13 Aug 2019

Feds delay environmental statement for offshore wind project

Connie Gillette, chief of public affairs for the Bureau of Ocean Energy Management, said Friday the agency took the action after receiving comments “from stakeholders and cooperating agencies” requesting a more robust cumulative analysis that would include projects that have been awarded power purchase agreements, but may not have submitted construction and operations plans.
10 Aug 2019

Feds delay environmental statement for offshore wind project

Connie Gillette, chief of public affairs for the Bureau of Ocean Energy Management, said Friday the agency took the action after receiving comments “from stakeholders and cooperating agencies” requesting a more robust cumulative analysis that would include projects that have been awarded power purchase agreements, but may not have submitted construction and operations plans.
10 Aug 2019

Trump stands up for New Bedford fishing community

The Trump administration was unsatisfied with the studies done on how much the wind industry would impact the fishing industry and has ordered an extended review: "An Interior Department review explored how Vineyard Wind may affect other industries and resources, including marine life. But the National Marine Fisheries Service raised concerns it looked too narrowly at potential cumulative effects on fishing, prompting the supplemental review."
9 Aug 2019

Trump stands up for New Bedford fishing community

The Trump administration was unsatisfied with the studies done on how much the wind industry would impact the fishing industry and has ordered an extended review: "An Interior Department review explored how Vineyard Wind may affect other industries and resources, including marine life. But the National Marine Fisheries Service raised concerns it looked too narrowly at potential cumulative effects on fishing, prompting the supplemental review."
9 Aug 2019

Vineyard Wind Races Against the Clock

Beyond the immediate concerns with permitting, Vineyard Wind faces a tangle of logistical challenges and potential investor turmoil if the project continues to see delays. Anthony Logan, an industry expert with the renewables research firm Wood Mackenzie Power, has spent the past six years forecasting the wind energy field. He said that while Vineyard Wind, barring major disaster, remains poised to become the first industrial-scale offshore wind-farm in the U.S., the financial success of the project is dependent on qualifying for a federal tax incentive for wind energy projects, known as the investment tax credit (ITC).
9 Aug 2019

Vineyard Wind Races Against the Clock

Beyond the immediate concerns with permitting, Vineyard Wind faces a tangle of logistical challenges and potential investor turmoil if the project continues to see delays. Anthony Logan, an industry expert with the renewables research firm Wood Mackenzie Power, has spent the past six years forecasting the wind energy field. He said that while Vineyard Wind, barring major disaster, remains poised to become the first industrial-scale offshore wind-farm in the U.S., the financial success of the project is dependent on qualifying for a federal tax incentive for wind energy projects, known as the investment tax credit (ITC).
9 Aug 2019

Federal agencies, Vineyard Wind at odds over wind farm setup

All three federal agencies that weighed in on Vineyard Wind’s construction and operations plan have coalesced around the east-to-west orientation of the 84 wind turbines. The three agencies are supporting a distance of at least 1 mile between the turbines, which is a marked contrast to the company’s diagonal layout plan with less space between, according to the Times review of 349 public comments on the draft environmental impact statement.
2 Aug 2019

Federal agencies, Vineyard Wind at odds over wind farm setup

All three federal agencies that weighed in on Vineyard Wind’s construction and operations plan have coalesced around the east-to-west orientation of the 84 wind turbines. The three agencies are supporting a distance of at least 1 mile between the turbines, which is a marked contrast to the company’s diagonal layout plan with less space between, according to the Times review of 349 public comments on the draft environmental impact statement.
2 Aug 2019

Vineyard Wind receives gubernatorial boost

One section of the proposed cable route passes through the Muskeget Channel about a mile from Chappaquiddick, and therefore falls under the auspices of the Edgartown conservation commission. In a 5-1 vote, the commission denied Vineyard Wind a permit to lay cable in the channel. Vineyard Wind has since appealed to the Massachusetts Department of Environmental Protection. 
31 Jul 2019

Vineyard Wind receives gubernatorial boost

One section of the proposed cable route passes through the Muskeget Channel about a mile from Chappaquiddick, and therefore falls under the auspices of the Edgartown conservation commission. In a 5-1 vote, the commission denied Vineyard Wind a permit to lay cable in the channel. Vineyard Wind has since appealed to the Massachusetts Department of Environmental Protection. 
31 Jul 2019

R.I. delegation raises concerns with speed of offshore wind review

Vineyard Wind already agreed to a nearly $17 million mitigation package in Rhode Island. But it doesn’t look like that will be enough. The fishing industry still has many issues. For example, the Long Island Commercial Fishing Association is worried about the effect these giant towers could have on boat radar, and the impediments that transmission cables could cause.
30 Jul 2019