Pretty Prairie wind farm lawsuit dismissed, allowing it to be appealed

The Hutchinson News|John Green|September 14, 2020
KansasLegal

Pretty Prairie Wind LLC, a subsidiary formed by NextEra Energy to develop an 82-turbine wind farm in the southeast quadrant of the county, filed the suit in July 2019 after it failed to obtain a conditional use permit to build the project.


The Pretty Prairie Wind lawsuit was dismissed by a Reno County judge on Monday after attorneys for the developer filed a motion asking to dismiss all claims in the suit except on an issue the district court already ruled on.

The action effectively allows the corporation to appeal to a higher court an earlier ruling by District Judge Tim Chambers on a motion for summary judgment. It has 10 days to file a notice of appeal.

Pretty Prairie Wind LLC, a subsidiary formed by NextEra Energy to develop an 82-turbine wind farm in the southeast quadrant of the county, filed the suit in July 2019 after it failed to obtain a conditional use permit to build the project.

That after landowners in the development area who opposed the project …

... more [truncated due to possible copyright]

The Pretty Prairie Wind lawsuit was dismissed by a Reno County judge on Monday after attorneys for the developer filed a motion asking to dismiss all claims in the suit except on an issue the district court already ruled on.

The action effectively allows the corporation to appeal to a higher court an earlier ruling by District Judge Tim Chambers on a motion for summary judgment. It has 10 days to file a notice of appeal.

Pretty Prairie Wind LLC, a subsidiary formed by NextEra Energy to develop an 82-turbine wind farm in the southeast quadrant of the county, filed the suit in July 2019 after it failed to obtain a conditional use permit to build the project.

That after landowners in the development area who opposed the project successfully filed a protest petition which forced a unanimous county commission vote to grant the permit, but the vote was split 2-1 in favor of the permit.

The developer contends forms on which petitions were gathered by a “circulator” had to be notarized by a sworn notary public, and since they weren’t, that they were not legally valid.

In a July 9 ruling on the issue, Chambers found a sentence at the bottom of the form stating that the circulator attested to the validity of the signatures “under penalty of perjury” was legally sufficient.

Pretty Prairie Wind then filed a motion asking to appeal on that issue immediately, which Chambers denied, stating the case should go forward on the remaining issues in the suit.

“Plaintiffs have determined that they do not wish to proceed with the remaining claims in this action and ask that the remaining claims be dismissed...except for the claim contained in Count 1 ... that the Protest Petitions were invalid for failure of the signatures of the ‘circulators’ to be notarized.”

Attorneys previously said an appeal in the case will likely take a year.  


Source:https://www.hutchnews.com/new…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2024 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION