Wind farm costs to rise under new rules - IWEA

Irish Independent|John Mulligan |December 13, 2019
IrelandGeneral

The Irish Wind Energy Association has criticised proposed new rules for onshore wind farm development, claiming it will be "more difficult and more expensive" to construct projects under the plans. The rules would see new standards for noise, mandatory community consultations, a minimum setback distance of 500 metres from any residential property in the vicinity of a new development, and other measures.


The Irish Wind Energy Association has criticised proposed new rules for onshore wind farm development, claiming it will be "more difficult and more expensive" to construct projects under the plans.

The rules would see new standards for noise, mandatory community consultations, a minimum setback distance of 500 metres from any residential property in the vicinity of a new development, and other measures.

The proposals are now open to public consultation.

Housing Minister Eoghan Murphy said the proposals were "aimed at striking a better balance between addressing the needs to local communities and maintaining Ireland's ability to deliver on its renewable energy ambitions".

Richard Bruton, the Minister for Communications, Climate …

... more [truncated due to possible copyright]

The Irish Wind Energy Association has criticised proposed new rules for onshore wind farm development, claiming it will be "more difficult and more expensive" to construct projects under the plans.

The rules would see new standards for noise, mandatory community consultations, a minimum setback distance of 500 metres from any residential property in the vicinity of a new development, and other measures.

The proposals are now open to public consultation.

Housing Minister Eoghan Murphy said the proposals were "aimed at striking a better balance between addressing the needs to local communities and maintaining Ireland's ability to deliver on its renewable energy ambitions".

Richard Bruton, the Minister for Communications, Climate Action and Environment, said that by 2030, 70pc of Ireland's electricity was expected to be generated from renewable sources.

"These guidelines are crucial to delivering the step up that is required and will give clarity to project leaders," Mr Bruton said.

Among the other proposals are that communities where wind farms are developed must be permitted to take part-ownership in projects, benefit from another type of dividend, or a combination of the two.

"Although we have not yet had time to study the new draft guidelines in detail, it is immediately clear that they will make it more difficult and more expensive to develop renewable energy in Ireland, and will significantly undermine the Government's own Climate Action Plan," said David Connolly, CEO of the Irish Wind Energy Association (IWEA).

The IWEA said analysis prepared for it by Everoze on the new noise limits showed they would lead to an average 11.4pc increase in the price of wind-generated electricity.

It claimed this would see the cost of installing the 4GW of onshore wind required in the Climate Action Plan rising by about €2.7bn over the next 25 years.


Source:https://www.independent.ie/bu…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2024 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION