Sitting still: Malfunction shuts down wind turbines

Like birds poised for light, the blades of many windturbines at Diamond Vista Wind Farm in northern MarionCounty have not been turning for a while.

A transformer malfunction shut down eight of the farm’s 12circuits on Oct. 6. Four circuits at the west end of the windfarm are still functioning.

Technicians from the company that manufactured thetransformer were called to check it out and at irst thought it would need to be transported back to the plant in Mexico forrepairs.

That would have caused a shutdown of four months or so. However, they were able to get it ixed and, barringunforeseen developments, the turbines are expected to be inoperation next week.

David Mueller, liaison between landowners and Enel GreenPower, said the transformer was under warranty, thecompany had insurance, and landowners experienced no lossof revenue.

“Everybody is covered,” he said.

Mueller said the company reported excellent production ofelectricity this past year.

“Even with a month’s delay, production exceeds theprevious year,” he said.

Like birds poised for light, the blades of many wind turbines at Diamond Vista Wind Farm in northern Marion County have not been turning for a while.

A transformer malfunction shut down eight of the farm’s 12 circuits on Oct. 6. Four circuits at the west end of the wind farm are still functioning.

Technicians from the company that manufactured the transformer were called to check it out and at irst thought it would need to be transported back to the plant in Mexico for repairs.

That would have caused a shutdown of four months or so. However, they were able to get it ixed and, barring unforeseen developments, the turbines are expected to be in operation next week.

David Mueller, liaison between landowners and Enel Green Power, said the transformer was under warranty, the company had insurance, and landowners experienced no loss of revenue.

“Everybody is covered,” he said. 

Mueller said the company reported excellent production of electricity this past year.

“Even with a month’s delay, production exceeds the previous year,” he said.