Thruway Authority sues maker of wind turbines that don't work

The Buffalo News|Jonathan D. Epstein |December 27, 2018
New YorkGeneral

The turbines were installed in 2013-2014 as part of a renewable energy program designed to generate enough power to save the authority as much as $420,000 a year on energy bills. The authority spent $500,000 on design and up to $4.8 million on installation. But the machines went offline between October 2017 and January 2018 because of mechanical issues. The suit alleges negligence, professional malpractice, breach of warranty and breach of contract.


Four years after spending $5 million to install wind turbines at four highway exits, the New York State Thruway Authority is now suing the company, contractor and consultants who installed them because the machines haven't worked since last year.

The authority on Thursday filed a lawsuit against Vergnet Group S.A., Prudent Engineering LLP, Ravi Engineering & Land Surveying PC, Kandey Company Inc. and CHA Consulting Inc., citing the failure of four turbines along the Thruway in Chautauqua and Erie counties. The machines are located on authority property at exits 61, 59, 58 and 57A.

The turbines were installed in 2013-2014 as part of a renewable energy program designed to generate enough power to save the authority as much as $420,000 …

... more [truncated due to possible copyright]

Four years after spending $5 million to install wind turbines at four highway exits, the New York State Thruway Authority is now suing the company, contractor and consultants who installed them because the machines haven't worked since last year.

The authority on Thursday filed a lawsuit against Vergnet Group S.A., Prudent Engineering LLP, Ravi Engineering & Land Surveying PC, Kandey Company Inc. and CHA Consulting Inc., citing the failure of four turbines along the Thruway in Chautauqua and Erie counties. The machines are located on authority property at exits 61, 59, 58 and 57A.

The turbines were installed in 2013-2014 as part of a renewable energy program designed to generate enough power to save the authority as much as $420,000 a year on energy bills. The authority spent $500,000 on design and up to $4.8 million on installation. But the machines went offline between October 2017 and January 2018 because of mechanical issues.

The suit alleges negligence, professional malpractice, breach of warranty and breach of contract. The authority seeks to recoup $8.1 million from the installation and operation of the two-blade machines, plus interest, costs and collection fees. The state Attorney General's Office is handling the litigation for the authority.

None of the companies could be reached for comment Thursday except for Ravi, which declined to comment.

According to the lawsuit, West Seneca-based Kandey was selected to install the turbines through a competitive bidding process, and hired Vergnet, a French company that manufactured the machines. But Vergnet was placed in receivership more than a year ago because of severe cash-flow problems, and was taken over by a consortium of five companies led by asset management firm Arum International.

Albany-based CHA Consulting – formerly Clough Harbor & Associates LLP – provided preliminary engineering services, final design services and construction support for the project, while East Syracuse-based Prudent Engineering provided construction inspection services for the installation. Prudent also served as a subconsultant to Ravi Engineering for program management, monitoring and maintenance services.

A fifth turbine, which was installed near Exit 60 at the Westfield Maintenance Facility, was manufactured by a different company, Northern Power Systems of Vermont, and is still operating. It is not part of the lawsuit.


Source:https://buffalonews.com/2018/…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2024 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION