What’s happening with the long-proposed wind farm in Champaign County?

Springfield News|Matt Sanctis|April 19, 2018
OhioGeneral

Attorneys representing the Buckeye Wind and Champaign Wind LLC projects are seeking approval from the Ohio Power Siting Board to extend the certificates for the project from May 28, 2018 to May 28, 2019, according to documents filed with the agency. If the certificates are not extended, it’s possible the developer would have to restart the lengthy application process for the project.


Opponents of a proposed wind farm in Champaign County recently filed documents with the Ohio Power Siting Board opposing an extension of certificates needed to build the project.

Attorneys representing the Buckeye Wind and Champaign Wind LLC projects are seeking approval from the Ohio Power Siting Board to extend the certificates for the project from May 28, 2018 to May 28, 2019, according to documents filed with the agency. If the certificates are not extended, it’s possible the developer would have to restart the lengthy application process for the project.

But a group of Champaign County residents who oppose the wind farms argue that any extension of the certificates would count as changing the initial project and require that the …

... more [truncated due to possible copyright]

Opponents of a proposed wind farm in Champaign County recently filed documents with the Ohio Power Siting Board opposing an extension of certificates needed to build the project.

Attorneys representing the Buckeye Wind and Champaign Wind LLC projects are seeking approval from the Ohio Power Siting Board to extend the certificates for the project from May 28, 2018 to May 28, 2019, according to documents filed with the agency. If the certificates are not extended, it’s possible the developer would have to restart the lengthy application process for the project.

But a group of Champaign County residents who oppose the wind farms argue that any extension of the certificates would count as changing the initial project and require that the approval process start over.

Attorneys for Everpower, the developer of the wind farm, recently argued the extension is necessary because an earlier group of opponents tied the project up in a years-long legal fight. Everpower is in the process of negotiating a sale of the the Champaign County project and others to innogy, a German energy company.

The Champaign County projects were among the earliest approved in the state, before lawmakers imposed tougher requirements for how far turbines in more recent projects should be from neighboring properties.

In documents filed with the OPSB, the residents raise concern over issues like noise produced by the turbines, and argue their interests will be better protected if the developers have to restart the application process. In that case, the tougher setback requirements would apply to the project.

The latest setbacks require that turbines be at least 1,125 feet from an adjacent property line, but some turbines in the Champaign County wind farms would be as close as 541 feet, the residents argue.

“They have a real and substantial interest in attempting to prevent the infliction of additional adverse impacts on their land, residences, communities and lives that the combined facility is projected to create,” opponents said in the latest filing.

“Moreover, the infliction of these adverse impacts would be greatly reduced by the application and enforcement of the current setback requirements … to the combined project.”

The project’s latest opponents also argued they have a right to intervene in the case and rejected the idea that litigation was the sole reason construction has not yet begun on the combined wind farm.

Instead, they argued the developers have sought numerous changes to the project since the certificates were initially issued.

“Given that the bulk of any ‘delay’ in the commencement of construction on these projects is largely due to applicants’ own conduct the local residents maintain that applicants have failed to show good cause for the requested extensions,” opponents argued.

A project schedule filed by the developers shows final designs for the wind farm could be completed as soon as the third quarter of this year. Both phases of the project could be operational by the end of next year if the project moves forward.


Source:https://www.springfieldnewssu…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2024 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION