More Gorge wind dealing: Avangrid Renewables adds 400MW project to its pipeline

Portland Business Journal|Pete Danko |November 16, 2017
OregonGeneral

Avanagrid Renewables, which already has nearly 1,300 megawatts of operating wind power in the region and is building a big project that will sell its output to Apple, has acquired a permitted but unbuilt project in the Columbia River Gorge.


Avanagrid Renewables, which already has nearly 1,300 megawatts of operating wind power in the region and is building a big project that will sell its output to Apple, has acquired a permitted but unbuilt project in the Columbia River Gorge.

But don’t count on the 400-megawatt Golden Hills Wind Farm breaking ground soon.

With the acquisition from Orion Renewable Energy Group, Avangrid Renewables is asking state regulators to extend the deadline for beginning construction on the Sherman County project from June 2018 to June 2020.

Laura Beane, president and CEO of Avangrid Renewables, said that like any potential project, Golden Hills won’t be built unless and until the Portland-based company has a power purchase agreement in hand.

The …

... more [truncated due to possible copyright]

Avanagrid Renewables, which already has nearly 1,300 megawatts of operating wind power in the region and is building a big project that will sell its output to Apple, has acquired a permitted but unbuilt project in the Columbia River Gorge.

But don’t count on the 400-megawatt Golden Hills Wind Farm breaking ground soon.

With the acquisition from Orion Renewable Energy Group, Avangrid Renewables is asking state regulators to extend the deadline for beginning construction on the Sherman County project from June 2018 to June 2020.

Laura Beane, president and CEO of Avangrid Renewables, said that like any potential project, Golden Hills won’t be built unless and until the Portland-based company has a power purchase agreement in hand.

The immediate future of wind development is in some doubt as the House and Senate consider tax measures that could trim incentives. But Beane said she thinks in the long term, demand from utilities and corporations looking to green their profiles will mean projects are likely to be built in the Northwest.

“Having a pipeline of projects that you can develop is key,” Beane said. “You’re basically setting up options.”

Other major developers seem to have a similar mindset. This year has seen three other significant moves in the Gorge:

Pattern Energy Group bought Summit Ridge Wind, a Wasco county project;

Capital Power Corporation filed for a site certificate for the Nolin Hills Wind Power Project in Umatilla County;

and NextEra Energy Resources, the nation's largest generator of renewable energy, acquired the Wheatridge Energy Wind Energy Facility in Morrow and Umatilla counties.

Golden Hills’ history demonstrates the speculative nature of wind project development in the region. It got a site certificate from Oregon regulators in 2009, has changed hands once before, and has seen its construction-start deadline pushed out twice already.


Source:https://www.bizjournals.com/p…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2024 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION