KenGen's Sh6.9b wind power project in Meru delayed over land row

Daily Nation|Agnes Aboo|April 5, 2017
AfricaGeneral

Power generating firm KenGen has delayed the construction of a 400-megawatt wind-power plant in Meru County until land rows rocking the project are resolved. ,,,The area has been in a conflict of interest from many stakeholders since the power company identified it for the mega project.


KENYA -- Power generating firm KenGen has delayed the construction of a 400-megawatt wind-power plant in Meru County until land rows rocking the project are resolved.

The first phase of the Meru Wind Farm Project, which is expected to cost Sh6.9 billion, was scheduled to be completed in December 2017.

The project will sit on an 18,700–acre piece of land in Tigania East Sub-County.

According to KenGen’s managing director Albert Mugo, the construction has been delayed due to land disputes.

“As you see in the papers, we await land adjudication so that we can deal with the bona-fide land owners,” Mr Mugo said through a text message.

Sh6m for demarcation

To speed up the demarcation of the disputed land, a budget of Sh6 million was …

... more [truncated due to possible copyright]

KENYA -- Power generating firm KenGen has delayed the construction of a 400-megawatt wind-power plant in Meru County until land rows rocking the project are resolved.

The first phase of the Meru Wind Farm Project, which is expected to cost Sh6.9 billion, was scheduled to be completed in December 2017.

The project will sit on an 18,700–acre piece of land in Tigania East Sub-County.

According to KenGen’s managing director Albert Mugo, the construction has been delayed due to land disputes.

“As you see in the papers, we await land adjudication so that we can deal with the bona-fide land owners,” Mr Mugo said through a text message.

Sh6m for demarcation

To speed up the demarcation of the disputed land, a budget of Sh6 million was approved by the national government.

The process was expected to be completed within two months to allow the firm to construct the plant this year. However, this has faced a big blow after Meru Governor Peter Munya put an injunction to stop the process.

“Those purporting to be committee members have not been gazetted. Whatever they are doing in the land is illegal. If we allow them to continue with the illegal process, the poor will be deprived of their land,” he said.

The governor said he will only allow the process to go on once an all-inclusive land committee is constituted.

Mr Munya said the bona-fide land owners should be given a two week notice before meeting to choose a committee that will oversee the subdivision of land.

Conflict of interest

The area has been in a conflict of interest from many stakeholders since the power company identified it for the mega project.

The area, which is located few metres from the Isiolo International Airport, is also seen as an avenue for the Lamu Port-South Sudan-Ethiopia-Transport (LAPSSET) Corridor project.

According to the District Lands and Adjudication Settlements Officer (DILASO) Kephers Obingo, the demarcation process will be done before the KenGen wind power station is set up.

“We need cooperation from all those involved to ensure the exercise runs smoothly. Genuine land owners will get documents immediately after the demarcation,” Mr Obingo.

The wind mill project will occupy the sections of Ngaremara and Gambela locations.


Source:http://www.nation.co.ke/busin…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2024 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION