logo
Article

BPA plan would share costs of wind-power shutdown

Seattle Times|Hal Bernton|April 18, 2013
OregonWashingtonUSAGeneral

The Bonneville Power Administration (BPA) this week released a new proposal to share the "oversupply costs" that pile up when there is not enough demand for all the electricity produced by hydroelectric dams and wind-power producers. During these oversupply periods, when wind-power producers may be asked to shut down, the plan would compensate them for lost revenue, according to Doug Johnson, a BPA spokesman.


The Bonneville Power Administration proposes to share the costs of shutting down wind turbines when energy production exceeds demand.

The Bonneville Power Administration (BPA) this week released a new proposal to share the "oversupply costs" that pile up when there is not enough demand for all the electricity produced by hydroelectric dams and wind-power producers.

During these oversupply periods, when wind-power producers may be asked to shut down, the plan would compensate them for lost revenue, according to Doug Johnson, a BPA spokesman.

This year, the BPA forecast a 50 percent chance there will be an oversupply of power. If that happens, the cost of the plan could be about $10 million, or up to $50 million if extreme conditions …

... more [truncated due to possible copyright]
The Bonneville Power Administration proposes to share the costs of shutting down wind turbines when energy production exceeds demand.

The Bonneville Power Administration (BPA) this week released a new proposal to share the "oversupply costs" that pile up when there is not enough demand for all the electricity produced by hydroelectric dams and wind-power producers.

During these oversupply periods, when wind-power producers may be asked to shut down, the plan would compensate them for lost revenue, according to Doug Johnson, a BPA spokesman.

This year, the BPA forecast a 50 percent chance there will be an oversupply of power. If that happens, the cost of the plan could be about $10 million, or up to $50 million if extreme conditions occur during the peak spring runoff period.

The BPA operates regional transmission lines used by wind-power producers, and also sells hydroelectric power from federal dams on the Columbia and Snake rivers.

Under the new proposal, Seattle City Light, Tacoma Power and other utilities that use BPA transmission lines would share in the costs of compensating wind-power producers. The plan calls for those producers, as they use the transmission lines, to share some of the costs, which could reduce their net compensation, according to Johnson.

Two years ago, the BPA offered no compensation to wind-power producers who were ordered to shut down when there was not enough demand.

They depend on the BPA to transmit their power, and the Federal Energy Regulatory Commission eventually ruled that the agency's actions unfairly discriminated against them.

In a statement released to The Seattle Times, Iberdrola Renewables, a major Northwest wind-power developer, said the BPA's proposal "is not there yet," and needs more work to find "a fair and lawful solution for the region."

The struggle to come up with a cost-sharing formula reflects broader strains in the regional power system as the BPA seeks to integrate wind power.

In recent years, the supply of wind power has dramatically expanded, spurred by federal tax incentives and state requirements to buy renewable electricity.

Scott Thomsen, a Seattle City Light spokesman, said the BPA provides about 40 percent of the utility's power. He said any added BPA costs from compensating wind-power producers would be passed on to ratepayers.

Since the costs would be shared among transmission-line users, Johnson expects the effects on ratepayers within the BPA region would be modest. He did not speculate on what they might be.

The new proposal, which would cover the period from March 31, 2012, through Sept. 20, 2015, still requires approval by the Federal Energy Regulatory Commission.

Hal Bernton: 206-464-2581 or hbernton@seattletimes.com


Source:http://seattletimes.com/html/…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2024 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION