Iowa Supreme Court backs wind expansion; MidAmerican can continue a project approved in 2009

Des Moines Register|Ryan J. Foley|June 9, 2012
IowaGeneral

The decision means MidAmerican can continue its ongoing expansion approved by regulators in 2009, which allowed the firm to add 1001 megawatts and allow the company to pass certain costs to customers in a rate increase ...It also means that MidAmerican does not have to buy wind power from NextEra, which the Florida company had proposed as an alternative.


The Iowa Supreme Court on Friday upheld a regulatory decision that allowed a huge expansion of wind energy by the state's largest utility, rejecting a challenge from a rival company who claimed it was unnecessary and unfair to other energy producers.

The court voted 5-0 to uphold a 2009 decision by the Iowa Utilities Board that gave Des Moines-based MidAmerican Energy Co. the ability to nearly double its wind power generation and guaranteed the firm could raise customers' rates in the future to recover much of the cost of expansion. The court rejected a challenge by Florida-based NextEra Energy Resources, a producer that sells electricity in the wholesale market.

"We're just very pleased with the ruling and pleased that we are …

... more [truncated due to possible copyright]

The Iowa Supreme Court on Friday upheld a regulatory decision that allowed a huge expansion of wind energy by the state's largest utility, rejecting a challenge from a rival company who claimed it was unnecessary and unfair to other energy producers.

The court voted 5-0 to uphold a 2009 decision by the Iowa Utilities Board that gave Des Moines-based MidAmerican Energy Co. the ability to nearly double its wind power generation and guaranteed the firm could raise customers' rates in the future to recover much of the cost of expansion. The court rejected a challenge by Florida-based NextEra Energy Resources, a producer that sells electricity in the wholesale market.

"We're just very pleased with the ruling and pleased that we are continuing our efforts to add more wind generation in Iowa," MidAmerican spokeswoman Ann Thelen said.

The case pitted two major players in the growing wind energy sector against each other in one of the states with the highest production.

NextEra is the largest wind energy producer in North America, owning 65 wind facilities, including some in Iowa. MidAmerican owns more wind generation capacity than any other rate-regulated utility in the U.S., with 30 percent of its capacity set to come from wind by the end of this year.

The decision means MidAmerican can continue its ongoing expansion approved by regulators in 2009, which allowed the firm to add 1001 megawatts of wind energy by 2013 and spelled out "advanced ratemaking principles" allowing the company to pass certain costs to customers in a rate increase once the project is complete. It also means that MidAmerican does not have to buy wind power from NextEra, which the Florida company had proposed as an alternative.

Under the project, Mid-American spent $985 million last year creating and expanding wind farms in central and western Iowa. The company plans additional wind projects in five Iowa counties this year that will cost hundreds of millions of dollars more.

MidAmerican is asking regulators to increase customer rates by up to $114.7 million over the next two years, which would increase the average monthly residential bill by $3.63. Thelen said those increases are not tied specifically to the expansion and reflect the rising cost of environmental regulations and transporting coal.

NextEra argued the Iowa Utilities Board should not have approved the project because MidAmerican did not demonstrate the need for extra capacity, did not properly consider other alternatives as required by state law and should have funded it through shareholders, not ratepayers.

NextEra claimed the expansion was unfair because MidAmerican will be allowed to sell excess wind power that is subsidized by its customers on the wholesale market. NextEra argued that it and other producers who compete with MidAmerican would be disadvantaged since they do not have a similar funding source.

Justice David Wiggins conceded that MidAmerican did not have a need for extra capacity until 2019, but found "substantial evidence" the plan would reduce carbon emissions, help maintain reasonable prices for customers and promote economic development and renewable energy in Iowa.

In a majority ruling, he rejected NextEra's argument that allowing MidAmerican to compete in the wholesale market discriminates against independent energy producers. Wiggins said any impact the expansion will have on the wind market would be slight, and outweighed by the benefits to MidAmerican customers.

Justice Edward Mansfield concurred with the court's outcome but not its reasoning. He said the court should have given more deference to utility regulators, and avoided commenting on whether the project was desirable since justices are not energy experts.

NextEra spokesman Steve Stengel said the company has no comment on the ruling.

Ronald Polle, an attorney for the Office of Consumer Advocate, which represents the public in regulatory proceedings involving utilities, said he was pleased the board's decision will stand. He said wind energy benefits customers because it is a low-cost and environmentally friendly fuel.

"We thought it was in the best long-term interest of customers," he said. "What wind does is ... it smooths the volatility of fuel costs. It ultimately results in lower costs over the life of the plant.

"And it helps MidAmerican comply with environmental regulations in a cost-effective manner."


Source:http://www.desmoinesregister.…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2024 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION