The problem seems to be a relay switch which has been repeatedly switching off for reasons unknown, said Mr. Crosby who has overseen the town's wind turbine project. ...The situation is complicated by the bankruptcy earlier this year of AAER, the Canadian firm that supplied the wind turbine to Portsmouth and provided the warranty protection.


PORTSMOUTH - It blew a steady 20 m.p.h. from the west Friday but the blades on Portsmouth's wind turbine didn't budge.

"Yes," replied Gary Crosby, Portsmouth's town planner, when asked whether the turbine is broken. "We're going through a bit of a rough patch but hope to have it resolved soon."

The problem seems to be a relay switch which has been repeatedly switching off for reasons unknown, said Mr. Crosby who has overseen the town's wind turbine project.

"For awhile I was able to go over there myself and physically switch it back on," he said, but as of the middle of last week, even that didn't work. "Now I can't reset it at all," he said Friday.

The situation is complicated by the bankruptcy earlier this year of AAER, the …

... more [truncated due to possible copyright]

PORTSMOUTH - It blew a steady 20 m.p.h. from the west Friday but the blades on Portsmouth's wind turbine didn't budge.

"Yes," replied Gary Crosby, Portsmouth's town planner, when asked whether the turbine is broken. "We're going through a bit of a rough patch but hope to have it resolved soon."

The problem seems to be a relay switch which has been repeatedly switching off for reasons unknown, said Mr. Crosby who has overseen the town's wind turbine project.

"For awhile I was able to go over there myself and physically switch it back on," he said, but as of the middle of last week, even that didn't work. "Now I can't reset it at all," he said Friday.

The situation is complicated by the bankruptcy earlier this year of AAER, the Canadian firm that supplied the wind turbine to Portsmouth and provided the warranty protection.

When AAER was still afloat, technicians there could monitor the turbine remotely and make any needed adjustments, usually without even visiting the site.

But Mr. Crosby said those duties have temporarily fallen to him while the new service provider, Lumus Construction of Woburn, Mass., gets up to speed. The Town Council voted September 15 to hire Lumus at an annual rate of $33,000 with additional fees for extra work

But before it can work on the turbine, Lumus must first be licensed by Wind Tech International, the company that built the turbine. Mr. Crosby said that that process is under way but he's not sure when it will be done.

That left Mr. Crosby to run over to the turbine every time it shut down, which had been happening as frequently as every six to eight hours.

"I can see it from my house, between a couple of trees and I was going over constantly days, weekends, holidays." He could hit the reset buttons from within the control room at the base of the tower - but as of Friday that process no longer worked.

"It's wearing on me to lose days with good breezes. I would love to see it turning ... But overall this has been a very good machine, very reliable," Mr. Crosby said. In fact, as recently as the 18th of October, the turbine's output was "22 percent ahead of monthly projections so we have a cushion."


Source:http://eastbayri.com/detail/1…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2024 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION