UCI wind turbine broken in initial test

Winchester News-Gazette|Bill Richmond and Cynthia Aukerman|February 18, 2010
IndianaStructural Failure

The Union City, Ind., wind turbine Tuesday experienced a failure of one of the rotor blade's tip brake mechanisms during commissioning and testing of the unit ...the failure will prevent the wind turbine from operating and producing electricity until the defective parts are repaired or replaced.


The Union City, Ind., wind turbine Tuesday experienced a failure of one of the rotor blade's tip brake mechanisms during commissioning and testing of the unit. According to city officials, no one was harmed by the failure, and the turbine has been locked down into safe mode.

Information provided Wednesday by the turbine manufacturer, Nordic Windpower, said the failure will prevent the wind turbine from operating and producing electricity until the defective parts are repaired or replaced. Nordic has guaranteed the defect will be properly remedied at their cost. A Nordic spokesman said once the failure is remedied, the turbine will perform as promised.

Union City, Ind. Mayor Bryan Conklin said the blades will be replaced, rather than …

... more [truncated due to possible copyright]

The Union City, Ind., wind turbine Tuesday experienced a failure of one of the rotor blade's tip brake mechanisms during commissioning and testing of the unit. According to city officials, no one was harmed by the failure, and the turbine has been locked down into safe mode.

Information provided Wednesday by the turbine manufacturer, Nordic Windpower, said the failure will prevent the wind turbine from operating and producing electricity until the defective parts are repaired or replaced. Nordic has guaranteed the defect will be properly remedied at their cost. A Nordic spokesman said once the failure is remedied, the turbine will perform as promised.

Union City, Ind. Mayor Bryan Conklin said the blades will be replaced, rather than attempting to make repairs on the end of the blade. The replacement is expected to take 30 days.

Nordic has said it will reimburse the City of Union City for all lost energy production revenue between now and when the turbine is fully operational. The wind speeds will be monitored to determine the extent of the lost energy revenue.


Source:http://www.winchesternewsgaze…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2024 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION