Hundreds of opponents of a massive wind farm on Lewis excluded themselves from giving evidence at a public inquiry because they requested confidentiality in their objections, it emerged last night. Thousands of people lodged protests against the controversial Eisgein development on Lewis. But many did not realise that ticking a confidentiality box means that they cannot make representations to an inquiry.


Hundreds of opponents of a massive wind farm on Lewis excluded themselves from giving evidence at a public inquiry because they requested confidentiality in their objections, it emerged last night.

Thousands of people lodged protests against the controversial Eisgein development on Lewis. But many did not realise that ticking a confidentiality box means that they cannot make representations to an inquiry.

Their contact details to the energy consents department in Edinburgh cannot legally be passed onto the appeals section, a Scottish Government spokesman confirmed. This means they would not be invited to make representations.

An earlier blunder in failing to notify potential witnesses delayed the preliminary inquiry meeting into …

... more [truncated due to possible copyright]

Hundreds of opponents of a massive wind farm on Lewis excluded themselves from giving evidence at a public inquiry because they requested confidentiality in their objections, it emerged last night.

Thousands of people lodged protests against the controversial Eisgein development on Lewis. But many did not realise that ticking a confidentiality box means that they cannot make representations to an inquiry.

Their contact details to the energy consents department in Edinburgh cannot legally be passed onto the appeals section, a Scottish Government spokesman confirmed. This means they would not be invited to make representations.

An earlier blunder in failing to notify potential witnesses delayed the preliminary inquiry meeting into the 53-turbine Muaitheabhal wind farm on the privately-owned Eisgein Estate.

The pre-inquiry meeting has been rescheduled for Friday in Stornoway.

A spokesman for the Scottish Government said objectors could still ask to lift their confidentiality request. He explained that representers should notify the Scottish Government planning consent department to make the change.


Source:http://news.scotsman.com/poli…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2024 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION