Documents

Somerset County, Maine: Resolution on Industrial Wind Energy Development

Somerset_county_wind_resolution_thumb At the September 6, 2017 meeting of the Somerset County Maine Commissioners, the Board adopted Resolution 17 – 164 that publicly opposes any additional industrial Wind Development in Somerset County. The agenda for the meeting can be found here. The full resolution, as adopted, is provided below and can be accessed at the links on this page. 
6 Sep 2017

ERT Wiggins v. Ontario: Decision revoking wind turbine permit

Ert_16-036_wiggins_v_ontario_-_decision-2017-08-16_thumb In this important decision by the Ontario Environmental Review Tribune, the Tribune officially revokes Wpd Canada's permit to install eight 137-meter (450 feet) tall wind turbines in close proximity to the Collingwood Regional Airport and a private air field owned by Kevin and Gail Elwood. In its October 2016 decision, the ERT had determined that the appellants met the test that showed there would be harm to human health. The ERT also agreed that irreversible harm to the natural environment, specifically to bats, warranted further investigation. Wpd Canada was granted an opportunity to show that mitigation could resolve the concerns. The ERT in this decision held that the risk to human health and safety was unacceptable. A portion of the decision is provided below (paragraphs 15-20) pertaining to the turbines impairing safe air travel. The full decision of the ERT can be found by clicking the links on this page.
16 Aug 2017

Status: Aramini-Krogh project to evaluate Health Canada Wind Turbine Noise and Health Study

Stats_canada_health_canada_raw_data_project_update_july_2017_thumb In November 2014, Health Canada released the results of its $2.1 million “Wind Turbine Noise and Health Study.” Despite public anouncements from Health Canada that the raw data originating from the Study would be made available, the data continues to be inaccessible making it impossible to validate the conclusions drawn by Health Canada researchers. For example, HC found high levels of annoyance but concluded no association to turbine noise.
30 Jul 2017

Apex: Galloo Island Wind - USFWS Comments

Usfws-comments-apex-galloo_island_wind_proposal_thumb This letter by the US Fish and Wildlife Service, was submitted to the State of New York in reference to a pending proposal to build a wind turbine project in the very sensitive land area on and around Galloo Island. The letter can be accessed by clicking on the links included on this page. The letter was submitted by Clifford P. Schneider with an accompanying letter by Mr. Schneider explaining the federal agency's concerns with the project application.
12 Jul 2017

Falmouth Wind Turbines 1 and 2: Court Order to cease and desist operation

Judge_moriarity_decision_june_2017_thumb In this important ruling issued by Massachusetts Superior Court Judge Cornelius J. Moriarty II, the court ordered that the decision of the Falmouth MA Zoning Board of Appeals be affirmed to the extent that the operation of Wind 1 and Wind 2 constitute a nuisance and that the Town of Falmouth cease and desist operation of the wind turbines immediately. The full order can be accessed by clicking the document icon located on this page.  
21 Jun 2017

A new methodology for investigating ILFN complaints

Subjectarea10_cooper_1013_3659_thumb This important study has identified flaws in the current compliance testing for wind turbine noise and further outlined the methods necessary for identifying and measuring the low-frequency, pulsation that isoften times reported by those impacted by the turbines. Specifically, the "presence of amplitude modulation in the low frequency region, that modulates at an infrasound rate, at or near the threshold of hearing" has been identified and may support the symptoms reported by Dr. Nina Pierpont in her work, Wind Turbine Syndrome. The introduction and conclusion of the paper is provided below. The full paper can be accessed by clicking the links on this page. 
18 Jun 2017

Greater Sage-Grouse on Steens Mountain: Final Ruling

12-596_order_granting_motion_to_vacate_4-18-17_thumb In this important ruling by the U.S. District Court for the District of Oregon, the court vacated the Secretary of the Interior’s approval of the proposed Steens Mountain wind project which would have sited up to 69 turbines and a 230 kv transmission line in area critical for sage grouse. The order is provided below and can also be accessed by clicking the links on this page. 
18 Apr 2017

Mammalian mesocarnivore visitation at tortoise burrows in a wind farm

Mammalian-mesocarnivore-visitation-10.1002_40jwmg.21262_thumb For wind proponents who insist that wildlife can co-exist around operating wind turbines, this study explains how the behavior of animals resident within a wind project site changed their behavior and avoided the project area. In particular, the researchers identified the loss of habitat due to the access roads and noise/vibrations of the turbines. A portion of the document is provided below. The full paper can be accessed by clicking the document icon on this page. In addition, supplemental data from the study is also attached to this page.
12 Apr 2017

Altered cortical and subcortical connectivity due to infrasound administered near the hearing threshold – Evidence from fMRI

Journal.pone.0174420-infrasound_thumb The findings of this study  demonstrate that infrasound near the hearing threshold may induce changes of neural activity across several brain regions, some of which are known to be involved in auditory processing, while others are regarded as keyplayers in emotional and autonomic control. In other words, sound that is not audible can still trigger a response in the human brain.
12 Apr 2017

The Maine Tourism Association and visual impact of turbines: Testimony

Mainetourism-testimony47967_thumb The Maine Tourism Association provided this testimony in support of Maine bill LD 901, a bill that calls for a I5-mile buffer zone and visual impact assessment on expedited wind energy development in order to protect some of the most popular tourist desitinations in the State. Maine tourism supports 16% of the state's employment and brings in $8.8 billion in total sales annually.  
2 Apr 2017

Camp Perry Wind Complaint

Campperrycomplaintasfiled-1_thumb Two leading bird conservation groups, American Bird Conservancy (ABC) and Black Swamp Bird Observatory (BSBO), have filed a lawsuit against the Ohio Air National Guard (ANG) over its plans to build and operate a wind turbine at its Camp Perry facility. Located in Port Clinton, Ohio, on the shore of Lake Erie, Camp Perry lies in a major bird migration corridor, close to numerous Bald Eagle nests, and is likely to kill species protected under the Endangered Species Act such as Kirtland's Warbler and Piping Plover. The complaint can be accessed by clicking the links on this page. A portion of the complaint is provided below.
27 Mar 2017

Rand: Critique of Noise Impact Report for NextEra's Golden West Wind Energy Center

Rand_review_epsilon-4177-goldenwest-170321_thumb NextEra's Golden West Wind Energy Center sited in El Paso County, Colorado was required under the County permit to conduct a noise impact study after the project was placed in service in October 2015. Acoustician Robert Rand was asked by residents living near the turbines to review the noise impact study as prepared by NextEra consultant, Epsilon Associates. Mr. Rand's report, included here, identified several material errors with Epsilon's report and also found that the project appears to be operating outside the noise limits permitted by the County and the State. The Golden West Wind Energy Center consists 145 1.72-megawatt GE turbines for a total installed capacity of 249.4-megawatts Mr. Rand's executive summary is provided below. The full report can be accessed by clicking the document icon on this page. 
23 Mar 2017

GVEA: Financial cost of interconnecting Delta Wind Farm

Gvea-letter-3-15-2017_thumb Alaska's Golden Valley Electric Co-Op denies a proposal by DWF to connect a new 13.5 megawatt ("MW") wind facility arguing, among other things, that the cost of interconnection would be higher than the benefits of the project.A letter with supporting evidence was submitted to the Regulatory Commission of Alaska. A portion of the letter appears below. The full document can be accessed by clicking the links on this page. 
15 Mar 2017

Comments by the Academic Editors Regarding: “Evaluation of Quality of Life of Those Living near a Wind Farm“:

Ijerph-14-00141-v2-mroczek_thumb These papers document an important debate between wind-friendly academics who argue that those living near wind turbines benefit from the experience and those who insist such conclusions are backed by inappropriate study methodologies and broad assertions that cloud actual findings. In this circumstance, Dr Daniel Shepherd a PhD in psychoacoustics and head of research at AUT University in Auckland, New Zealand, challenges the methods and conclusions of Mroczek et al.’s “Evaluation of Quality of Life of Those Living near a Wind Farm“ published in the International Journal of Environmental Research and Public Health, 2015, 12, 6066–6083. The academic editors of the Journal, after granting Mroczek the opportunity to respond, agree with Shepherd's main criticisms. In total, there are four papers documenting this debate; three are attached to this page. These include Shepherd's critique, Mroczek's response and the position of the Journal's academic editors. Portions of the response by the Journal's editors are also provided below.
8 Mar 2017

ABC brief supporting disclosure of bird-bat mortality: Blue Creek Wind facility

Brief_thumb This brief, filed before the Ohio Court of Common Pleas in Franklin County, Ohio, responds to Iberdrola's (Avangrid Renewables) action to stop any public disclose of bird/bat mortality data at its Blue Creek wind facility. Iberdrola has argued that the number of birds and bats killed by its turbines is a “trade secret” protected under Ohio law. The introduction and summary of arguments for why Iberdrola's claims are not supported by Ohio law are provided below. The full brief can be accessed by clicking the links on this page. The original complaint can be found here. 
7 Mar 2017

Vestas wind turbine collapse in Lemnhult, Sweden

Ro2017_01-slutrapport-lemnhult_thumb On December 24, 2015, a Vestas wind turbine collapsed in Lemnhult, Sweden. More than a year later, the Swedish Accident Investigation Authority has launched its report. The full report, in Swedish, can be accessed by clicking the links on this page. An English summary which is also provded in the report is posted below. Images of the collapsed Vestas V112 turbine can be found here.
22 Feb 2017

Penn Forest Township prevails against Atlantic Wind (Iberdrola)

Atlanticwindvspennforesttwp-opinion_thumb Atlantic Wind (aka Iberdrola) filed a complaint on September 26, 2016 (amended on November 7, 2016) before the Pennsylvania Carbon County Court of Common Pleas arguing that the venue to hear its Bethlehem Watershed wind turbine proposal was unsafe and that the location  should be changed and an independent hearing officer appointed. Atlantic Wind alleged that threats of violence by the public impacted the company's ability to receive a fair hearing before the Township zoning board. Atlantic Wind also requested an injunction barring the zoning board from holding further hearings until the court could rule. In this ruling the Court of Common Pleas ruled against Atlantic Wind. The full order can be accessed by clicking the links on this page. A portion of the order is provided below.  
17 Feb 2017

Denial of Flat Rock Wind upheld by Appeals Court: Decision

Flatrockwind-rushcountyin-appealorder_thumb An application prepared by Apex Clean Energy to construct and operate the Flat Rock wind facility was submitted to the Rush County Board of Zoning Appeals (the “BZA”) on March 15, 2015. The 180 MW project consisted of 95-3 MW turbines with approximately 66 turbines located in Rush County and the remaining turbines to be sited in Henry County. The Rush County BZA ultimately approved the application with the condition that the setback distance between the wind turbines and non-participating properties be 2,300 feet. The County's ordinance established a setback distance of 1,000 feet. Apex filed a petition before the Rush County Superior Court for judicial review of the BZA’s decision. On May 27, 2016, a judge issued findings of fact and conclusions of law that upheld the BZA’s approval with the 2,300-foot setback provision. Apex appealed the decision to the Indiana Court of Appeals. The decision by the Appeals Count was in favor of Rush County. The full decision can be accessed by clicking the links on the page. A portion of the decision is provided below.
14 Feb 2017

http://www.windaction.org/posts?type=Document
back to top