In 2005, the Texas Legislature adopted Senate Bill 20 which directed the Public Utility Commission of Texas ('PUCT') to select the most productive wind zones in the State and devise a transmission plan to deliver wind energy from these remote areas to the State's urban centers. Five Competitive Renewable Energy Zones ('CREZs') were identified in West Texas and the Panhandle for the construction of new wind energy generation. In 2008, the PUCT ordered the construction of new transmission to support up to 18,456 megawatts of wind energy capacity at an estimated cost of $4.93 billion, or approximately $4.00 per month per residential customer once construction was completed. The costs were to be reflected as rate increases. In its order from March 2009, the Public Utility Commission of Texas (PUCT), named thirteen companies to build the new electric transmission lines.