Library filed under Legal

Kahuku wind farm plan challenged again

The other contention is that the project developer failed to acquire control of the state-owned site for the wind farm within a PUC deadline. Collins said the developer missed a 120-day deadline because it didn't receive a permit for incidental Hawaiian hoary bat deaths until six months after the PUC approval. "You don't have an incidental take permit, you don't have site control, " he said.
12 Sep 2019

Innogy relinquishes state certificates; leases remain

“Buckeye Wind LLC and Champaign Wind LLC have relinquished the Certificates of Environmental Compatibility and Public Need issued for the Buckeye Wind project as construction activities have not commenced as required under the certificates,” according to a statement issued by Viola Baumann of Innogy – the Germany-based parent company of Buckeye Wind.
11 Sep 2019

Buckeye Wind I and II withdrawal notices

Ohio-buckeye_wind_withdrawal_1_opsb-a1001001a19i06b72929j00832_thumb Buckeye Wind LLC and Champaign Wind LLC, who collectively sought and received approval to construct the Buckeye I and Buckeye II wind energy facilities, have now withdrawn their applications and surrendered their certificates of environmental compatibility and public need. The notices of withdrawal are available at the document links on this page. 
6 Sep 2019

First ruling in Henry County wind farm case now in judge's hands. He will rule on submitted motion to dismiss

Rick Porter, the attorney for the 15 neighbors, said he had “yet to deal with a 50-page motion to dismiss.” “It seems they're trying to litigate the entire matter in a motion to dismiss,” he said, adding that it was “before we even have a chance to bring in witnesses” in a trial. He said his clients were “citizens hiring an attorney battling a mega-company with an unlimited budget.”
23 Aug 2019

Seneca Wind: Notice of Application Withdrawal

Seneca_wind_application_withdrawal_notice_thumb In early 2018, Seneca Wind LLC initiated the process before the Ohio Power Siting Board to secure authorization to construct and operate a 70 turbine (up to 200 MW) wind energy facility on 25,000 acres of leased land situated in Seneca County, Ohio. This letter submitted to the Siting Board states that Seneca Wind LLC wishes to withdraw its application from consideration.
9 Aug 2019

Judge upholds Coventry’s denial of green development project (solar)

Despite the fact the project was denied, DePasquale began prepping the two properties for the installation of solar arrays anyway. In early June, the Department of Planning & Development issued a cease-and-desist order for DePasquale’s unauthorized solar installation. A week later, on June 10, the town issued a finalized order, requiring that DePasquale remove all pilings and cease all work on the property except for seeding, loaming, and related landscape clean-up activities.
8 Aug 2019

Court battle continues for proposed wind farm

Fifteen Marion County landowners are continuing their fight against Expedition Wind, by asking the court not to grant a motion to dismiss the civil action lawsuit filed in mid-May. The lawsuit, according to the legal document filed July 26, stated that it’s too early to dismiss because the expected findings, which will come from discovery, have yet to be entered before the Eighth Judicial District in Marion County.
7 Aug 2019

Australian watchdog sues four wind farm operators over 2016 blackout

The sharp drop in power from the wind farms overloaded demand for power on a transmission line from a neighboring state, which then tripped that link off, cutting the state off from back-up electricity supply. “These alleged failures contributed to the black system event and meant that AEMO (the Australian Energy Market Operator) was not fully informed when responding to system wide failure in South Australia."
7 Aug 2019

Windfarm operators taken to court over South Australian blackout

The Australian Energy Regulatoralleges subsidiaries of the four companies – AGL Energy, Neoen SA, Pacific Hydro and Tilt Renewables – failed to ensure their windfarms complied with a generator performance standard requirement and had automatic protection systems to ensure continuity of supply. The regulator’s chair, Paula Conboy, said the alleged failures meant the Australian Energy Market Operator was not fully informed when responding to the system-wide failure.
7 Aug 2019

Oregon Supreme Court ruling could nix permits for big energy projects

An Oregon Supreme Court ruling could bring an end to permits for two big energy projects in Eastern Oregon and eight more statewide. The Oregon Energy Facility Siting Council in October 2017 adopted a swifter, less public method to amend permits, or site certificates, for wind farms, thermal power plants and other large energy facilities. While the traditional “type A” review process involved public notices and hearings, the new “type B” process cut out the public involvement, including allowing interested parties to request a contested case proceeding. Type B also required staff to issue decisions as soon as possible.
3 Aug 2019

Oregon Supreme Court Invalidates Energy Council's Rules for Modifying Power Plants

Today the Oregon Supreme Court held in favor of a coalition of nine conservation organizations, invalidating rules adopted in 2017 by the Oregon Energy Facility Siting Council (EFSC) that had dramatically reduced transparency and discouraged public participation in permitting decisions for large power plants throughout Oregon. Today’s legal victory is also expected to terminate the previously issued permits for two controversial power projects, the Summit Ridge Wind Farm proposed in Wasco County, along the Deschutes river, and the Perennial Wind Chaser Station, a natural gas power plant proposed in Umatilla County.
1 Aug 2019

Ontario minister, wind companies charged under Environmental Protection Act

Burke’s lawyer, Eric Gillespie, says roughly 80 families have been impacted by the contamination, which he alleges occurred when deposits of black shale in the soil were disturbed during construction of the project. “When you put up very large wind turbines that are 100 metres high, they require very large foundations,” he said. “Once they started developing these projects it became clear they were interfering with the drinking water supplies for many of the residents.”
27 Jul 2019

Ontario ministry, minister & wind companies charged for failing to prevent tainted well water

An Ontario Justice of the Peace has determined on July 12 that there are reasonable and probable grounds to lay charges under the Environmental Protection Act (EPA) against Jeff Yurek, Ontario’s minister of the environment, the Environment Ministry and the three industrial wind companies — Pattern Energy Group, Samsung Renewable Energy Inc. and Engie Canada Inc.  
27 Jul 2019

Bourne homeowners file suit over turbines

According to the suit, Chin, a registered real estate broker, had Rosemary Victoria sell the house to Mojica and Grendon, but neither informed the couple that the turbines would likely be built, a violation of state regulations that require the disclosure of information that would influence prospective buyers. “Angela S. Chin and Rosemary Victoria violated this regulation by not disclosing to the plaintiffs that four, massive, wind turbines would soon be constructed on the adjacent lot,” Henchy wrote.
25 Jul 2019

Wind farm case dismissed; construction not begun

Only a week after 70 opponents of a wind farm filed a lawsuit against Marion County Planning Commission over approving a conditional use permit, they dismissed the case. The plaintiffs dismissed the suit July 17 before the planning commission filed an answer.
25 Jul 2019

Neighbors file lawsuit to stop Henry County wind farm

The suit asks that the special-use permit granted by the Henry County Board last December be declared void because, among other things, the county allegedly failed to hold a public hearing with notice of the particular location of the property. It also alleges Avangrid failed to identify a specific turbine model, the exact number of turbines and the final locations of turbines.
16 Jul 2019

http://www.windaction.org/posts?topic=Legal
back to top