Documents filed under General

US BLM: Crescent Peak Wind denial letter

Blm_denial_letter_-_crescent_peak_wind_nov_19_2018_thumb The US Department of the Interior's Bureau of Land Management (BLM) issued this official letter denying Eolus North American's application for a right-of-way to construct and operate a wind energy facility with up to 106 wind turbines spanning approximately 32,000 acres of public lands in southern Nevada. The letter describes in detail the reasons for the denial. The summation of the letter is provided below. The full letter can be downloaded from this page. 
19 Nov 2018

Ganje Memo on Decommissioning

Ganje-decommissioning-recommendation-memo_thumb Attorney David Ganje of South Dakota submitted a memo to the state's Legislative Research Council (LRC) that responds to the LRC's recent memo on wind energy. In particular, Attorney Ganje challenges the LRC for not emphasizing the importance of project decommissioning. The introductory letter accompanying the memo is provided below. The full memo can be downloaded from this page. The LCR memo can be accessed here. 
27 Aug 2018

Invenergy 'Neighbor' Agreement - Iowa

360156642-invenergy-neighbor-agreement_thumb The document attached to this page is a "Wind Farm Neighbor Easement" agreement signed between wind project developer, Invenergy, and property owners with land adjacent to the Ida Grove Wind Project, a 300-megawatt project cconsistng of 120-GE 2.3-MW and 14-GE 1.79-MW turbines. The project was proposed by Invenergy and now owned by MidAmerican Energy Company (MEC) in Iowa. The project was placed in service at the end of 2016. Paragraphs from the agreement are excerpted and presented below. The full document can be accessed by clicking the document icon on this page.
7 Oct 2017

Upland Prairie wind memorandum of lease

Apex-lease-memorandum-clay-county-ia_thumb The document attached to this page is a memorandum of lease signed between Apex Clean Energy Inc and landowners in Clay County Iowa. The lease paves the way for the Upland Prairie wind facility to be constructed in Clay county and neighboring Dickinson County. The project, which will consist of 121 turbines (300 MW total), is now owned and under construction by Cedar Rapids-based Alliant Energy, one of Iowa's largest utilities. TO access the full lease document click the document link. on this page.
1 Jul 2017

Wind Energy’s Dirty Word: Decommissioning

Stripling95-wind_energys_dirty_word-decommissioning_thumb William Stripling’s note, which appeared in Vol 95 - Issue 1 of the Texas Law Review, examines the general failure of current law to ensure decommissioning of America’s wind farms. He discusses the history and current landscape of domestic wind-energy generation, before focusing on the best practices in wind-farm decommissioning, aesthetic and environmental harms posed by abandoned wind farms, and the challenges and costs of removing wind turbines. He then surveys the state of current law regarding decommissioning across U.S. jurisdictions, before finally discussing common pitfalls of current decommissioning law and suggesting how these pitfalls are best avoided. The conclusion of the paper is provided below. The full paper can be downloaded at the links provided on this page.
1 Jan 2017

Powering the Plunder: What Morocco and Siemens are hiding at COP22, Marrakech

Poweringplunder_eng_web_thumb A non-governmental body has called for Siemens and Enel to cancel wind projects in the disputed territory of Western Sahara. Western Sahara Resource Watch (WSRW) has said that schemes agreed by Siemens, Enel Green Power and the Moroccan government are set to take place in Western Sahara; and contribute to Morocco’s illegal occupation of the area. The Sahwari people claim ownership of the region, which was a colonial power of Spain and has been formally claimed by Morocco since 1957. Spain relinquished power in 1975. This document prepared by WSRW explains the dispute.
11 Nov 2016

US Wind production and capacity factors 2011-2015

Eia-windprojectgenerationstate-2015-2011-summary_thumb The U.S. Energy Information Administration provides monthly and annual production data for over 10,000 power plants including wind-powered facilities. Windaction.org has been tracking this data closely since 2011 with a specific focus on wind power plants. The below table lists the annual aggregate capacity factors for each state that EIA has reported wind production for projects with at least one full-year of production. A breakdown of the production data by state and individual projects in each of the years 2011 - 2015 can be accessed by downloading the documents attached to this page. Editor's note: Windaction.org, endeavors to present the most current and accurate information available. If readers identify a problem with any of the data, please contact us at info@windaction.org. In an effort to ensure accuracy, the attached data files may be updated from time-to-time. (Data files updated on April 2, 2016)
21 Mar 2016

Horizon Wind Thunder Bay denial

011-8937_refusal-thunderbay_thumb Horizon Wind Inc. first proposed the controversial wind project in 2007 that would place 16 wind turbines at various locations in the south Neebing area of Thunder Bay. The project was first approved by the city council but with objections to some turbine locations. Legal actions by Horizon eventually paved the way for the project but not without continued objections by the residents. Due to delays, the feed-in-tariff contract signed with Ontario was canceled in 2014. The project is now officially off the books in Ontario. This denial document, issued on October 29, 2015, explains why.
29 Oct 2015

BLM has limited assurance that wind and solar projects are adequately bonded: GAO Report

Gao-decommissioning-highlights_thumb The GAO conducted a file review of 45 wind and solar development project rights-of-way with a bond as of April 15, 2014; analyzed data from BLM data systems; reviewed relevant federal laws, regulations, and BLM policies and procedures; and interviewed agency officials. GAO found about one-third of the wind and solar rights-of-way were underbonded by as much as $15 million in total. Also, BLM did not clearly document how it made its bond decisions, contrary to government standards that call for documentation of significant events. The highlights of the GAO report are provided below. The full report can be accessed by clicking the links on this page.
23 Jun 2015

Gamesa US Harmony Wind project cancelled

20156-111228-01_thumb The Minnesota Public Utilities Commission (Commission) issued EcoHarmony West Wind LLC Site Permit on February 3, 2010 to construct a  58-turbine, 116-megawatts project. On April 22, 2013, the Site Permit was amended to allow an additional two years to commence construction and obtain a power purchase agreement (or other enforceable mechanism). Failing to do so, Gamesa filed notice that it would not be pursuing the project.  The content of Gamesa's notice is provided below. Both Gamesa's letter and the May 8, 2015 letter by the Commission inquiring about the project's status can be accessed by clicking the links on this page.
8 Jun 2015

Paynesville Wind Cancelled

Paynesville_wind_letter-mpuc-apr152015_thumb Geronimo Wind Energy's proposed  Paynesville Wind farm was issued a site permit and a Certificate of Need (CN) from the Minnesota Public Utilities Commission on January 26, 2011. The project would consist of 63 wind turbines totaling 95 megawatts to be located on approximately 15,000 acres in Stearns County, Minnesota. Paynesville Wind has been unable to secure a buyer for its energy. This letter was issued by the company this month. The content of the letter is provided below. The original can be accessed by clicking the links on this page. 
6 Jun 2015

Letter: Indefinite suspension of Great Bay Wind Energy Center investment

Great-bay-wind-letter-to-county_thumb Pioneer Green Energy has been promoting a 25-turbine wind energy facility (599-feet tall each) to be sited in Somerset County, Maryland, across the Chesapeake Bay from the Pax River naval base in an area surrounded by dozens of active bald eagle nests. Significant objections to the project were raised by the Navy and local residents. The Maryland State Senate and Assembly voted overwhelmingly to delay the project until more information could be determined about the impacts on military radar. Objections were also raised by members of Maryland's Congressional delegation. On March 20, 2015, Pioneer Green notified the Somerset County Commissioners that the project was being placed on indefinite suspension. The letter is provided below and can be accessed by clicking the links on this page.
20 Mar 2015

Environmental issues associated with wind energy: A review

Environmental-issues-and-wind-energy-dai-etal_thumb Abstract Recognized as one of the most mature renewable energy technologies, wind energy has been developing rapidly in recent years. Many countries have shown interest in utilizing wind power, but they are concerned about the environmental impacts of the wind farms. The continuous growth of the wind energy industry in many parts of the world, especially in some developing countries and ecologically vulnerable regions, necessitates a comprehensive understanding of wind farm induced environmental impacts. The environmental issues caused by wind farms were reviewed in this paper by summarizing existing studies. Available mitigation measures to minimize these adverse environmental impacts were discussed in this document. The conclusion of the report is provided below. The full paper can be accessed at the links on this page.
1 Mar 2015

Investigative Report of Steve Black - U.S. Fish and Wildlife Service

Steve_black_public_thumb The Inspector General of the Department of Interior released this report involving an investigation of Steven Black, a senior official who is now retired from the US Fish and Wildlife Service. Mr. Black had apparent close ties with the renewable energy industry and was accused of pressuring subordinates to ignore environmental concerns in favor of supporting the construction of wind energy and other renewable projects. The summary of the investigation is provided below. The full report can be accessed by clicking the link(s) on this page. 
7 Nov 2014

Oklahoma Corporation Commission inquiry on wind power issues

2014-232_20noi_20filed_208-12-14_thumb The Oklahoma Corporation Commission voted to open a notice of inquiry into wind farms. Two technical conferences to further refine questions are scheduled for Sept. 11 and Oct. 15. A hearing before the commission is set for Dec. 2. The text of the notice is provided below. The full document can be accessed by clicking the links on this page.
12 Aug 2014

http://www.windaction.org/posts?topic=General&type=Document
back to top