Library filed under General from Wyoming

A new chapter for a controversial wind farm, as sPower buys Pioneer Wind Park from Wasatch Wind

The NLRA has challenged the turbines at the Wyoming Supreme Court, the Federal Energy Regulatory Commission and in federal court. It lost in all three venues but succeeded in slowing Pioneer with a flood of legal briefs. The next showdown will come at the Wyoming Industrial Siting Council, the state regulatory board that permits large-scale developments. On Monday, the commission will consider sPower's request to reduce its reclamation bond for the facility after initial plans were downsized. 
30 Aug 2015

Wyoming board gives key OK for Carbon County wind farm

Power Company of Wyoming has also applied to the U.S. Fish and Wildlife Service for an eagle take permit, which would allow the company to kill a designated number of raptors each year ...In its application to the state, the company said it intends to provide $1.68 billion in its own funding to build the project. The remaining $3.11 billion will be financed through debt.  
8 Aug 2014

Storrow: DKRW, Two Elk, Wasatch and a broken DEQ

Wasatch Wind’s 80 megawatt Pioneer Park wind farm near Glenrock is the youngest of the Big Three, having first been announced in 2010. We don’t know the project’s exact price tag, but we can be sure it is no less than $190 million because that is the minimum threshold needed for the Department of Environmental Quality’s Industrial Siting Council to consider a project application.
14 Jul 2014

Firm seeks to harness Wyoming's wind energy for California

Wyoming residents enjoy the cheapest electricity prices in the nation, thanks to low-cost power from coal-fired plants near vast surface mines in the Powder River Basin. California, which has all but phased out coal power and has the nation's most aggressive renewable energy laws, has close to the highest prices, according to U.S. Energy Department data.
8 Feb 2014

Rocky Mountain Power applies for rules change amid dispute

Utilities are required by a law from 1978 to accept electricity generated by renewable-power projects of less than 100 megawatts. But the law comes with a hitch. Utilities are required to purchase the power only if doing so doesn’t lead to a rate increase for consumers. Current limitations in transmission capacity mean Rocky Mountain Power cannot offer Wasatch a higher price without triggering a rate increase,
3 Feb 2014

Chokecherry permit process inches along

The Chokecherry-Sierra Madre Wind Energy Project south of Rawlins is slowly moving through a bureaucratic maze of environmental impact and assessment studies. Although the U.S. Fish and Wildlife Service, and the Bureau of Land Management (BLM) have tentative timelines to complete their respective analysis, it is uncertain when construction will begin.
31 Jan 2014

Wasatch Wind wins key ruling for Glenrock wind project, but questions remain

Wind developers previously had to be in commercial production to qualify for the credit. The IRS issued new guidelines in the summer, saying companies only had to show work had begun. The new guidelines are untested in court, said Lay, a lawyer. “I have no doubt they [the developer] will claim to have met these requirements. Whether that claim stands up to the scrutiny of the IRS and its overseers in the Congress is another question."
27 Dec 2013

Wasatch Wind gets more time to start building wind farm near Glenrock

At a permit hearing on July 18, 2011, members of the Industrial Siting Council told the company that Edison Mission financing wasn't enough, Esch said. The council wanted to see additional sources of money. The council gave the company two years to show it had additional resources to fund the project. That deadline - July 18 - is approaching, and the company asked for a new deadline of May 2014.
26 Jun 2013

Few Wyoming wind projects making progress

Companies with projects and interest in Wyoming are slowly developing their projects, eyes on the day when they'll be able to transmit their product to customers in other states. But those projects, for the most part, are years from completion. Some may be a decade away from full service.
28 May 2013

Wasatch back with the wind

Specifically, the company is asking for a 10-month extension of the July 18, 2013, deadline to meet Special Condition #19 requiring the company to provide evidence of sufficient financial resources to construct, maintain, operate, decommission and reclaim the facility. ...The Industrial Siting Council will meet at 10 a.m. on Monday June 24, 2013, to consider the company's request for the extension.
9 May 2013

New date set for Chokecherry state permit

PCW originally planned to file the application on Jan. 21, but decided to wait to apply to see what would happen with Senate File 49, which, if passed, would have required projects requesting a permit from the ISC to spend 25 percent of anticipated project funds during the first two years of the project.
20 Mar 2013

Massive Wyoming wind farm developer to seek state permit

The company held its application because of concerns over now-dead legislation which could have affected construction on the project. The bill in question, Senate File 49, would have required companies with large enough projects to spend at least 25 percent of the anticipated cost in the first two years after approval.
19 Feb 2013

Citizens' group loses Wyo. wind farm challenge

"While disappointed with the court's ruling, the Northern Laramie Range Alliance believes the outcome is not surprising: As far as we have been able to determine, the ISC has never declined to issue an industrial siting permit in its 40 years of existence," the statement said. The alliance's news release also noted that Edison is in bankruptcy.
18 Dec 2012

Environmental groups criticize Wind energy project

The Laramie-based Biodiversity Conservation Alliance is considering legal action because of its concerns that the Chokecherry Sierra Madre Wind Energy Project would devastate local sage grouse and golden eagle populations. The project, calls for the construction of 1,000 wind turbines on 219,707 acres of land in Carbon County.
15 Oct 2012

Salazar approves Chokecherry wind energy project

The site, which encompasses approximately 2,000 acres of public and private land, will be home to 1,000 wind turbines and produce 2,500 megawatts of electricity. Once completed the Chokecherry and Sierra Madre Wind Energy project will be the largest wind farm in the country.
12 Oct 2012

http://www.windaction.org/posts?location=Wyoming&p=2&topic=General
back to top