Documents from USA

Invenergy v United States Section 1603 cash grant decisions

Californiaridge_v_us_1603_thumb In these two court cases, parent company Invenergy, received cash outlays for two Illinois projects, Bishop Hill and California Ridge. The funds were distributed, but the government witheld a portion of the grants claiming they were ineligible under the grant program. A suit was filed by Invenergy to recover the full grant amount it claimed it was entitled to and to prevent the government from clawing-back any additional grant money. In these final decisions, one for each project, the court ruled in favor of the Treasury. A portion of one decision is provided below. The full decisions can be accessed by selecting the document icons on this page.
20 Jun 2019

Nextera Burke Wind Denial Order

Ndgf-march_7_2019_letter_thumb The North Dakota PSC denied a permit for Nextera to construct and operate the 200 megawatt (76 turbine) Burke Wind Energy facility proposed for Burke County, ND. An excerpt of the PSC's decision is provided below. The full order denying the permit and letters from the US Fish and Wildlife Service and ND Game and Fish can be downloaded from this page. 
12 Jun 2019

Notice of relinquishment and withdrawal: Black Fork Wind Farm

Black_fork_wind_relinquishment_of_permit_to_construct_2019-05-16_thumb The application for the Black Fork wind energy facility was initially submitted to the Ohio Power Siting Board (OPSB) on March 10, 2011. The project, if constructed would have included up to 91 turbines (up to 200 MW) across 14,500 acres in Richland and Crawford counties, Ohio. There was significant opposition to the project but it was granted a permit by the state. In December 2018, the Ohio Supreme Court ruled in a 5-2 decision that OPSB wrongfully granted the project an extension to the date on which construction was to begin from January 2017 to January 2019. The Court found that the change was an amendment to the permit and required a more extensive review process and would subject the project to more onerous state setback distances. 
16 May 2019

Village of Montfort Appraisal: Impact of Cardinal-Hickory Creek Project

Forensic_appraisal_group_property_impact_-__village_of_montfort_2c_iowa_and_grant_counties_2c_wisconsin_thumb This appraisal examines the impact of the Cardinal-Hickory Creek (CHC) Project on properties in the Village of Montfort in Wisconsin. The CHC is a proposed 345kV high voltage line that will run between 84-105 miles long traveling from Cassville to Middleton in Wisconsin. The project also includes a 22-acre substation. The CHC 345kV will carry energy from the proposed Red Barn wind farm and the Badger Hollow solar farm. The conclusion of impact cited from the report is provided below. The full report can be accessed by clicking the links on this page.  
25 Apr 2019

Court: Injunction order halting construction of Crazy Mountain Wind farm

Park_dv-2018-161_thumb Montana District Court Judge Jon A. Oldenburg ruled no construction activity involving the Crazy Mountain wind farm proposed by Pattern Energy can proceed including no alterations to roads until a trial is held to determine if the project will cause irreparable harm to the neighboring property owners. Judge Oldenburg decided that “[u]ntil the ultimate issues are decided by a trier of fact, the balance of equities does not fall in favor of one side or the other."  The full order can be accessed at the document link on this page. Below is an excerpt of the court's ruling justifying the injunction and halting construction of the project.
19 Mar 2019

US NOAA comments on Vineyard Wind

20190315_nmfs-comments-on-vineyard-wind-deis_thumb This letter by US NOAA Fisheries Northeast Regional Administrator Mike Pentony raises serious concerns regarding the impacts of the 800 MW Vineyard Wind offshore wind facility proposed off the coast of Massachusetts. Concerns center on impacts to New England’s fisheries, marine life, and ocean habitats. The letter was sent to Bureau of Ocean Energy Management and provides comment on the project's Draft Environmental Impact Statement (DEIS). A portion of the letter is provided below. The full letter can be downloaded from the document links on this page. 
15 Mar 2019

US NOAA comments on Vineyard Wind

20190315_nmfs-comments-on-vineyard-wind-deis_thumb This letter by US NOAA Fisheries Northeast Regional Administrator Mike Pentony raises serious concerns regarding the impacts of the 800 MW Vineyard Wind offshore wind facility proposed off the coast of Massachusetts. Concerns center on impacts to New England’s fisheries, marine life, and ocean habitats. The letter was sent to Bureau of Ocean Energy Management and provides comment on the project's Draft Environmental Impact Statement (DEIS). A portion of the letter is provided below. The full letter can be downloaded from the document links on this page. 
15 Mar 2019

San Bernadino County resolution: Bans large-scale renewable energy projects

San_bernadino_co_resolution_on_renewable_energy_2019-2-28_thumb San Bernadino County in California adopted this resolution banning large-scale renewable energy projects. The full resolution and presentation slides explaining the change in policy can be downloaded from this page. Minutes from a May 28, 2018 special meetiing of the supervisors is also available from this page. Below is an excerpt of the resolution. Other supporting documentation leading up to adoption of the resolution can be accessed at the link on this page. 
28 Feb 2019

Summit Ridge Wind Farm: Extension request and comments

Comments_on_summit_ridge_wind_farm_amendment_4_thumb The Summit Ridge Wind Farm was granted a site certificate by the Oregon Energy Facility Siting Council (EFSC or Council) on August 19, 2011. The applicant now seeks a 4th amendment to the certificate that extends the start construction timeline another two years. A host of objections have been raised about the project. This page includes comments by K. Shawn Smallwood PhD outlining environmental concerns with the project’s wildlife surveys and analysis. The Friends of the Columbia Gorge, Oregon Wild, and others present their own comments. The procedural background information and an excerpt of the comments filed with the Council are provided below. The full documents can be downloaded from the links on this page.
22 Feb 2019

Huron County resolution withdrawing support for Emerson Creek Wind Energy Project

Huron-county-res.-19-067_thumb Resolution #19-067 was unanimously passed by the Board of Huron County Commissioners on February 19, 2019. The resolution repeals Resolution 2018-080 relative to the comuty's support of the Application submitted to the Ohio Development Services Agency by Apex Clean Energy for the Emerson Creek Wind Energy Project to be located in Huron County. A portion of the resolution is provided below. The signed resolution can be downloaded from the links on this page.
19 Feb 2019

Galloo Island wind project withdrawal letter

Galloo-island-wind_withdrawal_letter_-_ny_dps_thumb Apex Clean Energy, who proposed to erect 30 turbines and an electric substation on Galloo Island in Lake Ontario off the coast of New York, has officially withdrawn its application from from consideration. The withdrawal letter is provided in full below and can be downloaded throught the document links on this page. 
8 Feb 2019

PG&E injunction pleading against FERC interference

Pge_injunction_relief_-_ferc-filing2019-01-29_thumb In this court filing, utility-giant PG&E asks the court for an injunction against efforts by FERC to assert jurisdiction over the power contracts (PPAs) held by PG&E. Court documents show PG&E is bound by 387 PPAs with more than 350 companies totaling about $42 billion. The generators whose energy is under contract are at risk if PG&E is allowed to exit the agreements. A portion of PG&E's filing is provided below. The full document can be accessed at the links on this page.
29 Jan 2019

PG&E injunction pleading against FERC interference

Pge_injunction_relief_-_ferc-filing2019-01-29_thumb In this court filing, utility-giant PG&E asks the court for an injunction against efforts by FERC to assert jurisdiction over the power contracts (PPAs) held by PG&E. Court documents show PG&E is bound by 387 PPAs with more than 350 companies totaling about $42 billion. The generators whose energy is under contract are at risk if PG&E is allowed to exit the agreements. A portion of PG&E's filing is provided below. The full document can be accessed at the links on this page.
29 Jan 2019

Critique of Campbell County SD proposed wind ordinance

Campbell_temporary_zoning_ordinance_011519_thumb During the summer of 2018, Campbell County Commission discussed a possible need of a wind farm ordinance, Since that time, the county held no hearings or workshops that would provide the public an opportunity to comment on the new law. The only scheduled public hearing is set for February 7th, 2019 where the County will present the ordinance. Attorney David L Ganje has expressed concern that the County is rushing the process and, in doing so, failing to allow for a free exchange ideas about the wind farm ordinance. In August, 2018, Attorney Ganje recommended the commission convene several formal and informal public meetings and hire experts in order to deliver a well-crafted ordinance. 
29 Jan 2019

Audiologist Jerry Punch PhD public comments Seneca Wind

Seneca-wind-jerry-punch-letter-to-opsb_thumb Audiologist Dr. Jerry Punch, a professor emeritus in the Department of Communicative Sciences and Disorders, submitted comments in regard to a wind energy facility before the Ohio Power Siting Board. Dr. Punch's comments focus on the impacts of wind turbines noise on human health. A portion of his comments are provided below. His complete letter can be downloaded at the links on this page.  
15 Jan 2019

Quantifying the demographic cost of human related mortality to a raptor population

Quantifying_demographic_cost_-_journal.pone.0172232_thumb This important research examines the methods for quantifying population-level effects of human activity on raptor mortality. The study was conducted on raptors in California. Despite efforts to protect eagles, many lethal agents remain. According to the report, "prominent among them are electrocution, pesticide exposure, wire collisions, vehicular strikes, lead poisoning, and now, wind turbine blade-strikes." The abstract and conclusion of the paper is provided below. The full paper can be accessed at the document links on this page. 
8 Jan 2019

Quantifying the demographic cost of human related mortality to a raptor population

Quantifying_demographic_cost_-_journal.pone.0172232_thumb This important research examines the methods for quantifying population-level effects of human activity on raptor mortality. The study was conducted on raptors in California. Despite efforts to protect eagles, many lethal agents remain. According to the report, "prominent among them are electrocution, pesticide exposure, wire collisions, vehicular strikes, lead poisoning, and now, wind turbine blade-strikes." The abstract and conclusion of the paper is provided below. The full paper can be accessed at the document links on this page. 
8 Jan 2019

http://www.windaction.org/posts?location=USA&p=3&type=Document
back to top