Articles filed under Structural Failure from USA

Finally: GE engineer shares reasons for multiple turbine failures

“Two of the incidents involved blades coming apart during the operation of the turbine in high wind speeds, but resulting from different contributing factors,” said Hall. “The other two incidents of the first four appear to be related to how our control systems responded to a sequence of events in the field. “It does not appear that a single, systemic issue. 
17 Sep 2019

Morning storm left a Copenhagen Wind Farm Turbine short a blade

Sandi Briner, senior vice president of communications for EDF Renewables, the parent company for the wind farm, confirmed in a written statement that a “fault alarm” on the turbine notified wind technicians in the site area that there was a problem at about 8:50 a.m. A team went to the site, confirmed the damage and secured the access road leading to “turbine 30,” as the impacted turbine is designated.
5 Sep 2019

GE probes third turbine collapse at US wind farms this year

GE Renewable Energy has identified and addressed the root causes of the two turbine failures earlier this year. The May incident is understood to be down to an issue experienced during a turbine reboot addressed with a software update. The earlier collapse at the Casa Mesa Wind Energy Center is being attributed to a fuse-related blade issue while the turbine was running in overspeed mode during high winds.
10 Jul 2019

'Third GE wind turbine collapse would be sign something's wrong': insurer

“We probably see one or two of these a year out of a fleet of many thousands of turbines,” covered by GCube, McLachlan told Recharge. “It’s not that common. In a very bad year you might get three. “Two that close together, from the same manufacturer ... you would begin to wonder. And certainly one more GE [incident], three, that would tell me there’s something not right there.
3 Jun 2019

Crews respond to wind turbine fire in Huron County

Firefighters and deputies were called after a wind turbine caught fire near the village of Elkton. Jeff Smith, an Elkton village official, said the fire, which broke out on April 1,  is 300 feet in the air and crews cannot reach it to extinguish the blaze. The turbine is part of the Harvest II wind energy facility placed in service in November 2012 by Exelon and is one of 33 Vestas V-100 (1.8 MW) turbines erected in Oliver, Chandler and McKinley townships.
1 Apr 2019