Library from South Dakota

Wagner men claim local wind turbines violate county commission agreement

That affidavit stated Prevailing Wind Park agreed to ensure wind turbines constructed in Charles Mix County met a number of criteria related to noise, lighting, shadow flicker and ice. Among the criteria specified were that noise levels from turbines were not to exceed 43 dBA without a waiver at residences of those who weren't participating in the project and that either control systems would automatically shut down turbines or Prevailing Wind Park would do so manually when ice conditions were identified. Powers and Petrik asserted in their affidavit that those noise and ice criteria are not being met,
13 May 2020

Not so green energy: Hundreds of non-recyclable fiberglass wind turbine blades are pictured piling up in landfill

Incredible photos have revealed the final resting place of massive wind turbine blades that cannot be recycled, and are instead heaped up in piles in landfills. The municipal landfill in Casper, Wyoming, is the repository of at least 870 discarded blades, and one of the few locations in the country that accepts the massive fiberglass objects.
7 May 2020

Dakota County considering moratorium on wind farms

Broyhill referred to a number of books, studies and documentaries she said show the wind energy industry isn't as promising as supporters say. Broyhill talked about deceptive negotiating tactics when companies seek access to landowners' property. She also doesn't consider wind farms too environmentally friendly, given the tons of concrete and steel required for their construction and the fossil fuels burned by trucks to transport and build the turbines.
4 May 2020

S.D. regulators tell wind farm to get ready for sound tests, amid COVID-19 travel restrictions

A 60-day window starts July 1 for a South Dakota wind-power farm to show that the combined sound from its 57 turbines doesn’t exceed 40 decibels at the homes of anyone who’s not participating in the project. The state Public Utilities Commission voted 2-1 on Wednesday to continue requiring verification from Prevailing Wind Park. The project is in Bon Homme, Charles Mix and Hutchinson counties.
1 May 2020

PUC pushes back sound compliance period to July 1 for Prevailing Wind farm

Hanson was the most critical of the plan to delay the compliance period, especially as it affected non-participating property owners. Hanson also took issue with Agrimonti’s argument that the wind farm has not shown non-compliance, or that stipulating that turbines closest to the non-participating property owners be turned off would cause a financial hardship, as Agrimonti argued. “Obviously, if they have not tested those turbines, then they can’t show they are in compliance," Hanson said. "I would say it’s a superfluous argument, but it’s an interesting one. … Non-participants should not be the ones that carry the burden because someone from out of South Dakota can’t carry out the compliance.”
30 Apr 2020

PUC conditions not followed

The hearing was about the condition that the PUC imposed on Crowned Ridge/Next Era in the permit. They were to install low noise trailing edge blades on all turbines. They didn’t, and they got caught. They also got caught erecting towers taller than permitted, generators bigger than permitted along with a host of allegations about noise and shadow flicker violations. ...Crowned Ridge’s excuse was it was too cold, they didn’t order them early enough, as Commissioner Hanson compared it to “the dog ate my homework” excuse.
9 Feb 2020

South Dakota regulators approve waiver for wind farm project

The risk to the lake and the richly diverse wildlife that traverse it is among the reasons the Lake Erie Foundation has come out publicly opposed to a proposed offshore wind turbine development titled “Icebreaker Wind.” Lipaj was asked to lead a discussion regarding the topic at the Marblehead Peninsula Chamber of Commerce’s community business update meeting this week.
7 Jan 2020

Waiver request for $400M wind farm project deferred by S.D. regulators

Public Utilities Commission Chairman Gary Hanson wasn’t impressed with NextEra’s management of the project and failure to explain certain aspects of the project during previous hearings. “The compliance with the permit is foundation. A name plate, sound and flicker — these are not new to the process,” Hanson said. "At the very least this needs to be deferred until we get some answers.” Hanson said if the decisions isn’t deferred, his other option would be to deny the waiver.
31 Dec 2019

County board approves wind turbine dismantling work

Commissioner John Claggett said he was “deluged” with calls, asking why the county would accept wind turbines when the commission has not allowed wind turbines to be built in the county. He said governing bodies aren’t doing enough to hold wind energy companies and supporters accountable. “I’m getting asked, ‘We don’t have active wind farms here, why do we bring that in?'" he said.
10 Dec 2019

Energy firm continues investigation into cause of incident at wind farm

Construction manager Scott Creech confirmed an incident occurred Wednesday in Bon Homme County. However, he declined to provide more details on what caused the tipping of the crane, which was shown lying on the ground in social media photos. ...Creech also declined to confirm the crane’s height. However, Ronnie Hornstra, president of Prevailing Wind LLC, has told the Press & Dakotan "two of the only three mammoth cranes this size in the United States are on the project."
27 Sep 2019

http://www.windaction.org/posts?location=South+Dakota
back to top